PlanningRegister.ie
Kilkenny County Council · 2360556

Ballyconra , Ballyragget , Co Kilkenny

  1. 4 Dec 2023Received
  2. 2 Feb 2024Conditional
  3. 6 Mar 2024Final grant
  4. 5 Mar 2029Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional · 2 Feb 2024
Council
Kilkenny County Council
Type
PERMISSION
Site
3.27 ha

What’s proposed

for development at their Milk Processing Plant comprising: -Construction of a process building to accommodate two number evaporators, and associated equipment, associated plant and equipment rooms, roof mounted air handling equipment, a transformer enclosure and pipe and service bridges. -A link corridor connection to the existing Whey Factory. - Installation of 2 number water recovery silos affixed to concrete plinths. - Associated site works including earthworks, retaining walls, realignment of the existing internal roads to facilitate vehicle movements, drainage works and all associated site works including landscaping. This facility holds an industrial emissions licence issued by the Environmental Protection Agency

2360556 is a planning application to Kilkenny County Council for for development at their Milk Processing Plant comprising: -Construction of a process, received on 4 Dec 2023; permission was granted with conditions on 2 Feb 2024.

Planning details

Reference
2360556
Local authority
Kilkenny County Council
Status
Granted with conditions · register status “APPLICATION FINALISED
Received
4 Dec 2023
Observations close
17 Jan 2024 (closed 976 days ago)
Decision due
6 Feb 2024 · decided 2 Feb 2024
Decision
Conditional on 2 Feb 2024
Proposed development
for development at their Milk Processing Plant comprising: -Construction of a process building to accommodate two number evaporators, and associated equipment, associated plant and equipment rooms, roof mounted air handling equipment, a transformer enclosure and pipe and service bridges. -A link corridor connection to the existing Whey Factory. - Installation of 2 number water recovery silos affixed to concrete plinths. - Associated site works including earthworks, retaining walls, realignment of the existing internal roads to facilitate vehicle movements, drainage works and all associated site works including landscaping. This facility holds an industrial emissions licence issued by the Environmental Protection Agency
As published by the register.
Site area
3.27 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 10 applications within 500 m in the last 5 years

Show all 10

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 388621). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/2360556/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open