PlanningRegister.ie
Sligo County Council · 21334

Finisklin , Finisklin Road , Co Sligo

  1. 27 Aug 2021Received
  2. 20 Oct 2021Refused
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Appeal decided — refused
Decision
Refused · 20 Oct 2021
Council
Sligo County Council
Type
PERMISSION
Site
3.94 ha

What’s proposed

PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery and storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement

21334 is a planning application to Sligo County Council for pP - development consisting of a renewable energy development on a 3.9 hectare site. The, received on 27 Aug 2021; permission was refused on 20 Oct 2021.

Planning details

Reference
21334
Local authority
Sligo County Council
Status
Appeal decided — refused · register status “APPLICATION FINALISED
Received
27 Aug 2021
Observations close
1 Oct 2021 (closed 1819 days ago)
Decision due
21 Oct 2021 · decided 20 Oct 2021
Decision
Refused on 20 Oct 2021
Proposed development
PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery and storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement
As published by the register.
Site area
3.94 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 14 applications within 500 m in the last 5 years

Show all 14

Explore this area on the map →

Appeal

The register records appeal ABP-311963-21 (status unknown) but we have not matched the ACP case yet.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 458475). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/SligoCC/AppFileRefDetails/21334/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open