Kyleagarry Kyle Ballyryan East and Gortdrum, Donohill, Co. Tipperary
Decided on appeal.
- 19 Dec 2019Received
- 29 Jun 2020Refused
- Status
- Appeal decided — refused
- Decision
- Refused · 29 Jun 2020
- Council
- Tipperary County Council
- Type
- PERMISSION
- Site
- 71.22 ha
Live near Kyleagarry Kyle Ballyryan East and…?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 ha
Planning details
- Reference
- 19601430
- Local authority
- Tipperary County Council
- Status
- Appeal decided — refused · register status “APPLICATION FINALISED”
- Received
- 19 Dec 2019
- Observations close
- 3 Feb 2020 (closed 2436 days ago)
- Decision due
- 29 Jun 2020 · decided 29 Jun 2020
- Decision
- Refused on 29 Jun 2020
- Proposed development
- the construction of a 43MW Solar PV development comprising of ca. 155,000 no. photovoltaic panels laid out in arrays, the construction of a 38 kV substation, (ca. 114.9m2 X 4.75m tall) and transformer unit (ca. 15.25m2 X 2.4m tall) along with associated ancillary development including: 24 no. Power Hubs (ca. 15.25m” X 2.4m), which incorporate the inverters and the transformers within the same unit, 1 no. single storey communications building (11.1m” X 2.5m), 1 no. single storey client building (15.25m2 X 2.9m), 1 no. single storey equipment storage container (7.5m” X 2.7m), 15 no. CCTV cameras mounted on 4m high poles; and perimeter security fencing. The proposed development will also see the installation of ten (10 no.) ISO shipping container units for the purpose of battery storage (30.5 m” X 2.9m). The total development area will be ca. 70.5 haAs published by the register.
- Site area
- 71.22 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 5 · 500 m · 5 years
Appeal
Appeal 307702-20 (status unknown), not yet matched.
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- Recorded monument · 10
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
19601430 is a planning application to Tipperary County Council for the construction of a 43MW Solar PV development comprising of ca. 155,000 no., received on 19 Dec 2019; permission was refused on 29 Jun 2020.