Approved in May 2022. No sign of building yet.

  1. 25 Feb 2022Received
  2. 20 Apr 2022Conditional
  3. 24 May 2022Final approval
  4. 23 May 2032Approval runs out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 20 Apr 2022
Council
Tipperary County Council
Type
PERMISSION
Site
53.14 ha

Live near Kyleagarry Ballyryan East and Gortdrum?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

The development will consist of the construction of Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38KV substation (ca. 114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2) along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4) which incorporate at inverter and a transformer, 1. No. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9) 1. No. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. NIS will be submitted with the planning application

Planning details

Reference
22165
Local authority
Tipperary County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
25 Feb 2022
Observations close
1 Apr 2022 (closed 1655 days ago)
Decision due
21 Apr 2022 · decided 20 Apr 2022
Decision
Conditional on 20 Apr 2022
Proposed development
The development will consist of the construction of Solar PV development comprising photovoltaic panels laid out in arrays over a total development site area of ca. 54.5 ha, the construction of a 38KV substation (ca. 114.4m2 x 4.75m tall), a transformer unit (ca. 18m2 x 4m tall) and associated bund (ca. 55m2) along with ancillary development including: 17 no. Power Hubs (ca. 15.25m2 x 2.4) which incorporate at inverter and a transformer, 1. No. single storey communications building (11.1m2 x 2.5m), 1 no. single storey client side sub-station building (15.25m2 x 2.9) 1. No. single storey equipment storage building (7.5m2 x 2.7m), 7 no. CCTV cameras mounted on 4m high poles, perimeter security fencing and all ancillary works. NIS will be submitted with the planning application
As published by the register.
Site area
53.14 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 4 · 500 m · 5 years

Explore this area on the map →

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 6
    R135734; R135789

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

22165 is a planning application to Tipperary County Council for the development will consist of the construction of Solar PV development comprising, received on 25 Feb 2022; permission was granted with conditions on 20 Apr 2022.