Drummin Village, Borrisokane Road, Nenagh
Approved in Feb 2022. Built and signed off.
- 10 Sept 2021Received
- 20 Dec 2021Conditional
- 1 Feb 2022Final approval
- 20 Mar 2023Building started
- 11 Oct 2024Signed off
- Status
- Building started
- Decision
- Conditional · 20 Dec 2021
- Council
- Tipperary County Council
- Type
- PERMISSION
- Units
- 36
- Site
- 1.14 ha
What’s proposed
construction of 38 no. dwelling houses and associated site development works, including roads, footpaths, parking spaces, green areas and connection to the public services, to complete the final phase of the Drummin Village development
Planning details
- Reference
- 211348
- Local authority
- Tipperary County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 10 Sept 2021
- Decision due
- 22 Dec 2021 · decided 20 Dec 2021
- Decision
- Conditional on 20 Dec 2021
- Site area
- 1.14 ha from the mapped boundary, not the council's figure
- Applicant
- Montpellier Drummin Developments Ltd council register
Nearby 8 · 500 m · 12 months
- Granted30 Brookville Green , Nenagh , Co. Tipperary
- Awaiting decisionDrummin Village , Borrisokane Road , Nenagh
- GrantedDroim an Oir , Dromin Road Drummin , Nenagh Co. Tipperary
- RefusedDrummin , Borrisokane Road , Nenagh
- WithdrawnDrummin , Borrisokane Road , Nenagh
- GrantedDrummin Village , Borrisokane Road , Nenagh
- WithdrawnDrummin Village , Borrisokane Road , Nenagh
- WithdrawnDrummin Village , Borrisokane Road , Nenagh Co. Tipperary
- Granted37 The Close , Drumin Village , Nenagh Co Tipperary
- Withdrawn37 The Close , Drumin Village , Nenagh Co Tipperary
- Commenced23 Dromin Road , Nenagh , Co.Tipperary
- Granted51 The Square Drummin Village , Nenagh , Co. Tipperary
- Granted37 The Close , Drumin Village , Nenagh Co Tipperary
- Granted51 The Square Drummin Village , Nenagh , Co. Tipperary
- Withdrawn51 The Square , Drummin Village , Nenagh Co. Tipperary
- CommencedHelvic , Dromin Road , Nenagh
- Granted16 Dromin Road , Nenagh , Co. Tipperary
- GrantedNenagh College , Drummin , Nenagh
- CommencedDrummin , Borrisokane Road , Nenagh
- WithdrawnDrummin , Borrisokane Road , Nenagh
- CommencedDromin Road , Drummin Nenagh , Co. Tipperary
- CommencedDromin Road , Drummin Nenagh , Co. Tipperary
- CommencedDromin Road , Drummin , Nenagh Co. Tipperary
- CommencedDromin Road , Drummin , Nenagh Co. Tipperary
- Granted8 Brookville Green , Nenagh , Co Tipperary
- Withdrawn8 Brookville Green , Nenagh , Co Tipperary
- CommencedHelvic , Dromin Road , Nenagh
Homes nearby
- For sale72 The Avenue, Drummin Village, Nenagh, Co. Tipperary, E45 HN81
- For sale3 The Close, Drummin Village, Nenagh, Co. Tipperary, E45 H298
- For saleDroim an Óir, Nenagh, Co. Tipperary
- For sale43 Brookville Green, Nenagh, Co. Tipperary, E45 HH28
- For sale3 Bruach Tailte, Nenagh, Co. Tipperary, E45 A497
- For sale8 Oaklawn Drive, Nenagh, Co. Tipperary, E45 CH61
Building started
- 27 Aug 2024 · Builder told the council work was starting CN0118538TT
- 11 Dec 2023 · Builder told the council work was starting CN0108029TT
- 21 Jun 2023 · Builder told the council work was starting CN0101568TT
- 20 Mar 2023 · Builder told the council work was starting CN0098447TT
Zoning
Land zoned to stay open — parks, playing fields, amenity corridors. Built development is very hard to justify, which also means the view is protected.
Zoned for new residential communities. This is where large housing schemes are expected to go, subject to the social and physical infrastructure arriving with them.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
211348 is a planning application to Tipperary County Council for construction of 38 no. dwelling houses and associated site development works, including, received on 10 Sept 2021; permission was granted with conditions on 20 Dec 2021.