Approved in Feb 2022. Built and signed off.

  1. 10 Sept 2021Received
  2. 20 Dec 2021Conditional
  3. 1 Feb 2022Final approval
  4. 20 Mar 2023Building started
  5. 11 Oct 2024Signed off
Status
Building started
Decision
Conditional · 20 Dec 2021
Council
Tipperary County Council
Type
PERMISSION
Units
36
Site
1.14 ha

What’s proposed

construction of 38 no. dwelling houses and associated site development works, including roads, footpaths, parking spaces, green areas and connection to the public services, to complete the final phase of the Drummin Village development

Planning details

Reference
211348
Local authority
Tipperary County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
10 Sept 2021
Decision due
22 Dec 2021 · decided 20 Dec 2021
Decision
Conditional on 20 Dec 2021
Site area
1.14 ha from the mapped boundary, not the council's figure
Applicant
Montpellier Drummin Developments Ltd council register

Live near Drummin Village?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 8 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 27 Aug 2024 · Builder told the council work was starting CN0118538TT
  • 11 Dec 2023 · Builder told the council work was starting CN0108029TT
  • 21 Jun 2023 · Builder told the council work was starting CN0101568TT
  • 20 Mar 2023 · Builder told the council work was starting CN0098447TT

Zoning

G5 — Open space and amenity

Land zoned to stay open — parks, playing fields, amenity corridors. Built development is very hard to justify, which also means the view is protected.

R1 — New residential

Zoned for new residential communities. This is where large housing schemes are expected to go, subject to the social and physical infrastructure arriving with them.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

211348 is a planning application to Tipperary County Council for construction of 38 no. dwelling houses and associated site development works, including, received on 10 Sept 2021; permission was granted with conditions on 20 Dec 2021.