Ballyboe , Clonmel , Co. Tipperary
- 29 Mar 2021Received
- 21 May 2021Conditional
- 24 Jun 2021Final grant
- 29 Oct 2029Permission expires
- Status
- Granted with conditions
- Decision
- Conditional · 21 May 2021
- Council
- Tipperary County Council
- Type
- PERMISSION
- Site
- 19.91 ha
What’s proposed
amend the design of the approved development (Planning Ref: 19/600239) which comprises consent for the development of a temporary (30 years) solar farm with an export capacity of 12 MW comprising of photovoltaic panels on ground mounted frames with associated infrastructure including 4 no. inverter housing cabins, 1 no. control building, 1 no. customer cabin (substation), 1 no. DNO substation, temporary construction compound, ducting and electrical cabling, perimeter agricultural fencing, mounted CCTV cameras and internal access tracks subject to 16 conditions. Amendments proposed are: - - Although the height of the solar panels is increased from 2.7m to a maximum 3.2m, the glint and glare impacts will reduce due to advancements in the assessment and software used. The panel tilt angle will change from between 15 and 25 degrees to 15 and 30 degrees; - The number of solar modules will reduce from 39,168 to 30,060 and the number of pile driven poles installed will increase from 2,548 to 4,258; - Although there will be an increase in the number of Inverter Substations from 4 to 6, these have a lower noise output and will therefore result in lower noise impacts; - An increase in CCTV cameras along the perimeter fence from 8 to 12; - Although the road will remain at a width of 3.5m, the point where it connects from the southern to northern lands is moved to use the existing access; - An almost identical footprint which will increase by 0.03% to 4.08%; and – Increase the output from 12MW to 16MW
21403 is a planning application to Tipperary County Council for amend the design of the approved development (Planning Ref: 19/600239) which comprises, received on 29 Mar 2021; permission was granted with conditions on 21 May 2021.
Planning details
- Reference
- 21403
- Local authority
- Tipperary County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 29 Mar 2021
- Observations close
- 4 May 2021 (closed 1964 days ago)
- Decision due
- 23 May 2021 · decided 21 May 2021
- Decision
- Conditional on 21 May 2021
- Proposed development
- amend the design of the approved development (Planning Ref: 19/600239) which comprises consent for the development of a temporary (30 years) solar farm with an export capacity of 12 MW comprising of photovoltaic panels on ground mounted frames with associated infrastructure including 4 no. inverter housing cabins, 1 no. control building, 1 no. customer cabin (substation), 1 no. DNO substation, temporary construction compound, ducting and electrical cabling, perimeter agricultural fencing, mounted CCTV cameras and internal access tracks subject to 16 conditions. Amendments proposed are: - - Although the height of the solar panels is increased from 2.7m to a maximum 3.2m, the glint and glare impacts will reduce due to advancements in the assessment and software used. The panel tilt angle will change from between 15 and 25 degrees to 15 and 30 degrees; - The number of solar modules will reduce from 39,168 to 30,060 and the number of pile driven poles installed will increase from 2,548 to 4,258; - Although there will be an increase in the number of Inverter Substations from 4 to 6, these have a lower noise output and will therefore result in lower noise impacts; - An increase in CCTV cameras along the perimeter fence from 8 to 12; - Although the road will remain at a width of 3.5m, the point where it connects from the southern to northern lands is moved to use the existing access; - An almost identical footprint which will increase by 0.03% to 4.08%; and – Increase the output from 12MW to 16MWAs published by the register.
- Site area
- 19.91 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 3 applications within 500 m in the last 5 years
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 468547). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/21403/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |