PlanningRegister.ie
Tipperary County Council · 2660893

Ballynilard, Tipperary, Co. Tipperary

Decision due 17 Dec.

  1. 11 Sept 2026Received
  2. 16 Oct 2026Observations closed
  3. 17 Dec 2026Decision due

An email when it’s decided. After that, only if it’s appealed or building starts.

Planning details

Status
With the council, no decision yet
Decision
Due 17 Dec 2026
Reference
2660893
Received
11 Sept 2026
Site
6.63 ha

What’s proposed

RED III application for development which comprises the construction of an anaerobic digestion facility to produce renewable biomethane, and a bio-based fertiliser from organic material. The total gross floor area of the proposed development (including internal plant areas and ancillary structures) will be c. 3,301 sq.m.

Show all

The development is a renewable energy development which is covered by the provisions of the Renewable Energy Directive III. The development will consist of the following: • Construction of 3 no. digesters (all c. 15.5m in height), 2 no. digestate storage structures (c. 15.5m and c. 12m in height), and a pump room and O2 generation structure (with a GFA of c. 27 sq.m. and a height of c. 2.6m), located in the northern section of the main site area. • 4 no. pasteurisation tanks (each c. 6m in height), a post pasteurisation cooling tank (c. 4m in height), and a pre fertiliser manufacturing tank (c. 4m in height), located to the southeast of the main digesters. • A liquid feed tank (c. 4m in height), a pump house (with a height of c. 2.6m and GFA of 14 sq.m), and a pump skid (c. 0.8m in height), located to the southwest of the main digesters. • A part single-storey and part two-storey reception hall (with a gross floor area (GFA) of c. 1,964 sq.m. and an overall height of c. 16.5m) to accommodate a laboratory, panel room, tool store, workshop, and storage areas, with a liquid feed intake adjacent to the reception hall, located in the central portion of the site. • A single-storey solid digestate storage and a nutrient recovery building (with a GFA of c. 880 sq.m and an overall height of c. 12.4m) located to the east of the reception hall, in the central portion of the site. • A pump house (with a height of c. 2.6m and GFA of 21 sq.m), a fuel storage tank (c. 1.6m in height), and a backup generator (c. 2.3m in height), located adjacent to the nutrient recovery building. • Odour abatement plant (with an overall height of c. 7m) and equipment and a digestate offtake area will be provided to the east of the solid digestate storage and nutrient recovery building. • construction of an emergency biogas flare (c. 11.3m in height), 2 no. biogas treatment skids (with an overall height of c. 4.1m), 2 no. biogas compression structures (with a height of c. 2.6m), a biogas upgrading module (with a maximum height of c. 4.6m and a GFA of c. 28 sq.m), a combined heat and power unit and panel room (with a height of c. 10m to top of flue), a biomethane boiler…

Cut short by the council feed. Full text ↗

1 other application within 500 m in the last year

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Protections nearby 250 m

  • Recorded monument · 10
    R135295; R135308
Where this comes from

National planning feed (NPAD), fetched 28 Oct 2026, 01:34.

Source: National Planning Application Database · fetched 28 Oct 2026, 01:34
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.028 Oct 2026, 01:34open
Summary

2660893 is a planning application to Tipperary County Council for RED III application for development which comprises the construction of an anaerobic, received on 11 Sept 2026; a decision is due by 17 Dec 2026.