Westmeath County Council · 22193
Macetown, Cloughan, Mullingar
Approved in Oct 2022. Building started in 2025.
- 14 Apr 2022Received
- 7 Sept 2022Conditional
- 19 Oct 2022Final approval
- 8 Mar 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 7 Sept 2022
- Reference
- 22193
- Received
- 14 Apr 2022
- Further information
- Requested 3 Jun 2022 · received 12 Aug 2022
- Units
- 1
- Site
- 1,938 m²
What’s proposed
To renovate existing cottage including demolishing previous extension and construct a new extension to rear, new wastewater treatment system and percolation area and all associated site works. Retention permission is also sought for existing sunroom as constructed at
5 other applications within 500 m in the last year
Open the reportNearby 5 · 500 m · 12 months
Distance
Time
- Awaiting decisionHarlockstown , Dunboyne , Co Meath
- Awaiting decisionLocated along the Blundelstown – Mullingar 110 kilovolt (kV) overhead line (OHL) , commencing within Blundelstown in the townland of Harlockstown Co. Meath , and extending to the existing Mullingar 110kV substation in the townland of Irishtown Cou
- GrantedMacetown Cloghan , Mullingar , Co. Westmeath
- RefusedMacetown Cloghan , Mullingar , Co. Westmeath
- WithdrawnMacetown , Cloughan , Co. Westmeath
Homes nearby
Building started
- 8 Mar 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0126132WH
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
22193 is a planning application to Westmeath County Council for to renovate existing cottage including demolishing previous extension and construct a, received on 14 Apr 2022; permission was granted with conditions on 7 Sept 2022.