Approved in Nov 2024. Building started in 2025.
- 29 Aug 2024Received
- 22 Oct 2024Conditional
- 27 Nov 2024Final approval
- 7 May 2025Building started
Planning details
- Status
- Building startedi
- Decision
- Conditional · 22 Oct 2024
- Reference
- 2460308
- Received
- 29 Aug 2024
- Units
- 1
- Site
- 4,298 m²
What’s proposed
Development which will consist of the demolition of the existing detached garage to the rear, the construction of a single storey extension to the rear of the existing dwelling. The development will also consist of amendments to the existing fenestration and all ancillary site works
5 other applications within 500 m in the last year
Open the reportNearby 5 · 500 m · 12 months
Distance
Time
- Awaiting decisionLocated along the Blundelstown – Mullingar 110 kilovolt (kV) overhead line (OHL) , commencing within Blundelstown in the townland of Harlockstown Co. Meath , and extending to the existing Mullingar 110kV substation in the townland of Irishtown Cou
- Awaiting decisionHarlockstown , Dunboyne , Co Meath
- GrantedMacetown Cloghan , Mullingar , Co. Westmeath
- RefusedMacetown Cloghan , Mullingar , Co. Westmeath
- WithdrawnMacetown , Cloughan , Co. Westmeath
Homes nearby
Building started
- 7 May 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0128254WH
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2460308 is a planning application to Westmeath County Council for development which will consist of the demolition of the existing detached garage to the, received on 29 Aug 2024; permission was granted with conditions on 22 Oct 2024.