Avoca River Park , Arklow , Co. Wicklow
- 31 Aug 2021Received
- 13 May 2022Conditional
- 15 Jun 2022Final grant
- 14 Jun 2027Permission expires
- Status
- Granted with conditions
- Decision
- Conditional · 13 May 2022
- Council
- Wicklow County Council
- Type
- PERMISSION
- Site
- 4.92 ha
What’s proposed
Full ten-year planning permission for development on this site located at Avoca River Park, Arklow, Co. Wicklow. The proposed development is to be located within the townlands of Shelton Abbey and Marsh. The site is bound to the west by the site of a permitted data storage facility development (permitted under Reg. Ref.: 201285), to the north by the access road to Avoca River Park, to the south by undeveloped lands and to the east by undeveloped lands beyond which is the M11 motorway. The proposed development consists of the following: •All site clearance and enabling works required to facilitate the development. •Construction of 2 no. energy centre buildings (Energy Centre 1 and Energy Centre 2) each with a height to parapet level of c. 13.85 metres. •Energy Centre 1 will comprise a gross floor area (GFA) of 5,965 sq.m. within a single storey building and will accommodate 12 no. generators. 4 no. flues 33 metres in height will be accommodated along with south-western elevation of the building. •Energy Centre 2 will comprise a GFA of 9,180 sq.m. within a single storey building and will accommodate 18 no. generators. 6 no. flues 33 metres in height will be accommodated along the south-western elevation of the building. •Construction of a battery compound to provide electricity storage and backup power, located to the northeast of Energy Centre 2, to comprise 27 no. battery arrays within a compound area of c. 0.7 hectares. A single storey MV switch-room building (c. 181 sq.m. GFA) will be provided to the west of the battery compound. •Provision of a transformer compound (to the northwest of Energy Centre 1), along with a welfare building (c.38 sq.m. GFA).•Provision of fuel storage tanks (2 no.) within a bunded compound to the north of Energy Centre 2.•Construction of a new access from the existing estate access road to the north of the site, internal road network and circulation areas, footpaths, provision of 6 no. car parking spaces and 4 no. cycle parking spaces. •Landscaping and planting, boundary treatments, lighting, security fencing and all associated ancillary and site works including underground foul and storm water drainage network (including on-site wastewater treatment system) and utility cables
211080 is a planning application to Wicklow County Council for full ten-year planning permission for development on this site located at Avoca River, received on 31 Aug 2021; permission was granted with conditions on 13 May 2022.
Planning details
- Reference
- 211080
- Local authority
- Wicklow County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 31 Aug 2021
- Observations close
- 5 Oct 2021 (closed 1817 days ago)
- Decision due
- 15 May 2022 · decided 13 May 2022
- Decision
- Conditional on 13 May 2022
- Proposed development
- Full ten-year planning permission for development on this site located at Avoca River Park, Arklow, Co. Wicklow. The proposed development is to be located within the townlands of Shelton Abbey and Marsh. The site is bound to the west by the site of a permitted data storage facility development (permitted under Reg. Ref.: 201285), to the north by the access road to Avoca River Park, to the south by undeveloped lands and to the east by undeveloped lands beyond which is the M11 motorway. The proposed development consists of the following: •All site clearance and enabling works required to facilitate the development. •Construction of 2 no. energy centre buildings (Energy Centre 1 and Energy Centre 2) each with a height to parapet level of c. 13.85 metres. •Energy Centre 1 will comprise a gross floor area (GFA) of 5,965 sq.m. within a single storey building and will accommodate 12 no. generators. 4 no. flues 33 metres in height will be accommodated along with south-western elevation of the building. •Energy Centre 2 will comprise a GFA of 9,180 sq.m. within a single storey building and will accommodate 18 no. generators. 6 no. flues 33 metres in height will be accommodated along the south-western elevation of the building. •Construction of a battery compound to provide electricity storage and backup power, located to the northeast of Energy Centre 2, to comprise 27 no. battery arrays within a compound area of c. 0.7 hectares. A single storey MV switch-room building (c. 181 sq.m. GFA) will be provided to the west of the battery compound. •Provision of a transformer compound (to the northwest of Energy Centre 1), along with a welfare building (c.38 sq.m. GFA).•Provision of fuel storage tanks (2 no.) within a bunded compound to the north of Energy Centre 2.•Construction of a new access from the existing estate access road to the north of the site, internal road network and circulation areas, footpaths, provision of 6 no. car parking spaces and 4 no. cycle parking spaces. •Landscaping and planting, boundary treatments, lighting, security fencing and all associated ancillary and site works including underground foul and storm water drainage network (including on-site wastewater treatment system) and utility cablesAs published by the register.
- Site area
- 4.92 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 9 applications within 500 m in the last 5 years
- OpenIn the townlands of Askakeagh Ballymanus Killaduff Roddenagh Kilballyowen Killacloran Coolahullin , Tinnakilly Lower Ballymorris Lower Ballymorris Upper Templelusk Knockanmohill Ballinamona Garnagowlan , Kilcarra West Kilcarra East Glenart Shelton Ab
- GrantedSite at Avoca River Park Arklow Town Marsh 10 and 11 Ferrybank Road , within the townlands of Shelton Abbey Marsh and Ferrybank , Co. Wicklow
- GrantedAvoca River Park , Arklow , Co. Wicklow
- GrantedSite located at and to the east of Avoca River Park , Arklow , Co. Wicklow
- GrantedShelton Abbey , Arklow , Co. Wicklow
- GrantedSite at Avoca River Park , Arklow , Co. Wicklow
- GrantedSite located at Avoca River Park , Arklow , Co. Wicklow
- GrantedShelton Abbey Townland , Arklow , Co. Wicklow
Homes nearby
- WithdrawnClonkeen, Shelton, Arklow, Co. Wicklow, Y14 DY77
- SoldOak Tree Lodge, Vale Road, Arklow, Co. Wicklow
- Sold32 Glenart Drive, Lamberton, Arklow, Co. Wicklow
- Sold57 Woodlands Green, Arklow, Co. Wicklow
- For sale"Bayview", Kilbride, Arklow, Co. Wicklow, Y14 TD56
- Sold16 Glenart Drive, Lamberton, Arklow, Co. Wicklow
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 159626). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/WicklowCC/AppFileRefDetails/211080/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |