Fingal County Council · FW21A/0151

Lands adjacent to Huntstown Power Station, North Road, Finglas, Dublin

Approved in Mar 2025. Building started in 2025.

  1. 24 Feb 2022Received
  2. 20 Apr 2022Approved
  3. 16 May 2022Appealed
  4. 21 Mar 2025Appeal: Approved with conditions
  5. 21 Mar 2025Final approval
  6. 17 Oct 2025Building started
Status
Building startedi
Decision
Approved · 20 Apr 2022
Council
Fingal County Council
Type
Permission
Site
13.60 ha
Appeal
ACP 313583 · Approved with conditions

What’s proposed

In plain English

Demolition of two houses and construction of two data hall buildings

The applicant wants to knock down two existing houses to build two data hall buildings.

  • Includes the demolition of 2 residential dwellings
  • Construction of 2 data hall buildings
  • An Environmental Impact Assessment Report has been submitted
Written by AI from the council’s description

An AI model rewrote the council’s description below in everyday words on 9 Oct 2026. It was told to use only that text, and every number it wrote was checked against it. It says nothing about whether the application will be approved. The council’s wording and planning file are the record.

The council’s description

Demolition of 2 no. existing residential dwellings and ancillary

Planning details

Reference
FW21A/0151
Local authority
Fingal County Council
Status
Commenced · register status “Final Grant”
Received
24 Feb 2022
Decision due
20 Apr 2022 · decided 20 Apr 2022
Decision
Grant permission on 20 Apr 2022
Site area
13.60 ha from the mapped boundary, not the council's figure

Live near Lands adjacent to Huntstown Power…?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 6 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Appeal

ACP 313583 · Planning Appeal · decided · Approved with conditions 21 Mar 2025
received by the Commission 16 May 2022 · inspector's report · board order

Building started

  • 2 Sept 2026 · Builder told the council work was starting (seven-day notice) SN0014734FL
  • 2 Sept 2026 · Builder told the council work was starting (seven-day notice) SN0014726FL
  • 2 Sept 2026 · Builder told the council work was starting (seven-day notice) SN0014728FL
  • 2 Sept 2026 · Builder told the council work was starting (seven-day notice) SN0014727FL
  • 2 Jun 2026 · Builder told the council work was starting CN0142878FL
  • 26 Feb 2026 · Builder told the council work was starting (seven-day notice) SN0013822FL
  • 10 Nov 2025 · Builder told the council work was starting CN0135598FL
  • 17 Oct 2025 · Builder told the council small works were starting CN0134807FL

Zoning

RD - Road: N/A

C2.2 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

Protections nearby 250 m

  • EPA-licensed facility · 10
    Huntstown Power Company Limited; Viridian Power Limited
  • Recorded monument · 4
    Ring-ditch; Earthwork

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 15:18.

Source: National Planning Application Database · fetched 11 Sept 2026, 15:18
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 15:18open
Summary

FW21A/0151 is a planning application to Fingal County Council for demolition of 2 no. existing residential dwellings and ancillary, received on 24 Feb 2022; permission was granted on 20 Apr 2022.