PlanningRegister.ie
Neighbourhoods · Dublin City · last 24 months · 162 electoral divisions

Where a decision takes longest — Dublin City neighbourhoods

Every neighbourhood ranked: applications, extensions, retention and refusals.

Data updated 31 Oct 2026 · register lag up to 7 days · sources & freshness

26.1
applications per 1,000 homes
48%
household works
14%
for work already done
10%
refused
25%
asked for more details

BusiestExtendingBuilt firstRefusalsSlowestFurther infoAppealsBuilding12 months24 months

All DublinDublin CityDún Laoghaire-RathdownFingalSouth Dublin

Where a decision takes longest 69 ranked

Median days from the council receiving an application to its decision. Eight weeks is the statutory clock; a further-information request stops it.

#Neighbourhoodmedian daysDecidedHouseholdsRetentionRefusedMedian days
1Inns Quay B94 days231,79728%9%94
2Arran Quay B93 days271,7053%4%93
3Clontarf West C64 days411,74919%2%64
4Terenure B64 days211,50211%5%64
5North City62 days662,18716%12%62
6Wood Quay B62 days231,84716%17%62
7Pembroke West A60 days532,2286%9%60
8Clontarf East D60 days411,0439%5%60
9North Dock B58 days523,5146%8%58
10Rathmines West C58 days261,11922%15%58
11Arran Quay E57 days221,64717%9%57
12Clontarf East B55 days852,73212%2%55
13South Dock55 days623,5518%15%55
14Pembroke East C55 days591,68113%3%55
15Rathmines East A55 days562,22710%21%55
16Pembroke West C55 days641,94512%8%55
17Royal Exchange A55 days531,67927%26%55
18Mansion House B55 days5133018%20%55
19Rathmines East C55 days511,33921%12%55
20Rathmines East B55 days422,41312%12%55
21Pembroke East B55 days471,4558%21%55
22Saint Kevin's55 days561,98619%21%55
23Drumcondra South A55 days352,23913%3%55
24Mansion House A55 days391,66217%8%55
25Ashtown A55 days504,55213%2%55
26Clontarf East C55 days391,19310%0%55
27Royal Exchange B55 days3361811%18%55
28Grace Park55 days412,3316%5%55
29Rathfarnham55 days371,99119%8%55
30Crumlin D55 days421,66121%17%55
31Whitehall B55 days351,66919%9%55
32Beaumont C55 days421,32720%0%55
33Clontarf West A55 days421,44310%2%55
34Pembroke East E55 days361,51117%14%55
35Drumcondra South C55 days381,28514%11%55
36Pembroke West B55 days421,4005%19%55
37Kilmainham C55 days302,08526%20%55
38Pembroke East A55 days372,0994%11%55
39Pembroke East D55 days351,9392%6%55
40Cabra East A55 days272,58420%7%55

Top 40 of 69Show all 69 →

Every council 31

#Councilmedian daysApplicationsRetentionRefusedMedian days
1Monaghan99 days1,32919%7%99
2Roscommon98 days1,35922%13%98
3Carlow83 days91418%9%83
4Offaly77 days1,61321%9%77
5Cork County67 days6,81221%8%67
6Kerry63 days2,64630%12%63
7Kilkenny63 days1,89822%7%63
8Kildare61 days3,30024%20%61
9Limerick61 days2,83720%10%61
10Mayo60 days2,74918%7%60
11Westmeath59 days1,38220%13%59
12Cavan58 days1,59623%5%58
13Tipperary56 days3,06730%4%56
14Waterford56 days2,26021%11%56
15Cork City56 days1,19419%7%56
16Dublin City55 days6,01314%10%55
17Meath55 days3,45920%13%55
18Clare55 days2,39920%6%55
19South Dublin55 days2,28715%12%55
20Laois55 days1,96423%7%55
21Galway City55 days69127%14%55
22Galway County54 days3,85824%13%54
23Fingal54 days3,46020%22%54
24Wexford54 days2,83627%16%54
25Wicklow54 days2,78520%14%54
26Leitrim53 days50227%4%53
27Dún Laoghaire-Rathdown52 days3,91611%13%52
28Louth52 days2,06629%15%52
29Sligo52 days1,12025%7%52
30Donegal50 days5,06924%7%50
31Longford50 days60319%14%50
How it is counted
  • A neighbourhood is a CSO electoral division; its households and population are the 2022 census totals of the small areas inside it. Every application, appeal and building-start notice is counted in the division where it is on the map.
  • Household works are applications whose description says extension, attic, dormer, porch, garden room, garage conversion and the like, and does not say apartments, units, commercial, retail or office.
  • Work already done (retention) is an application to keep something that was built without permission: its type or description says retention. Its grant rate is shown where at least ten were decided.
  • Decisions count grants and refusals only; invalid, withdrawn and undecided applications are left out of every rate. Days are from the council’s receipt date to its decision date.
  • A rate is printed only where the neighbourhood has at least 20 of the thing being rated in the window; smaller ones show counts and are not ranked.
  • Councils have no per-household figures outside Dublin: the census spine is loaded for the Dublin region only.
Sources: National Planning Application Database (NPAD), CSO Census 2022 Small Area Population Statistics, An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 31 Oct 2026, 02:43
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.031 Oct 2026, 02:43open
CSO Census 2022 Small Area Population StatisticsCC BY 4.031 Oct 2026, 02:43open
An Coimisiún Pleanála case listCC BY 4.031 Oct 2026, 02:43open
Building Control Management System commencement noticesCC BY 4.031 Oct 2026, 02:43open

Recomputed weekly from the store; last built 31 Oct 2026.

Homes permitted, not started · Grant rates by council · Sources & freshness