The former Ford Distribution Site, Centre Park Road, Cork

Permission for the following Large Scale Residential Development (LRD)

Observations close 25 Nov 2026 5 days left
5 weeks from receipt (received 21 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 15 Dec 2026

The application

Reference
26/45115 · full record
Authority
Cork City Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
Marina Quarter Ltd.
Site area
1,921 m²
Received
21 Oct 2026
Decision due
15 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/corkcity/application-details/?ref=26/45115.
  2. Write your observation.Quote 26/45115 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Cork City Council takes it online with the submission or at the counter.
  4. Submit before 25 Nov 2026.Online through the register above, or in writing to the Planning Department, Cork City Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
M3
Neighbourhood centre
Neighbourhood and Local Centres: To protect, provide for or improve local facilities.cork city development plan 2022 2028 variation no 3 npf implementation8 Aug 2022 → 8 Aug 2028
R1
New residential
New Residential Neighbourhoods: To provide for new residential development in tandem with the provision of the necessary social and physical infrastructure.cork city development plan 2022 2028 variation no 3 npf implementation8 Aug 2022 → 8 Aug 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Cork City Council development plan zoning · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
Cork City Council development plan zoning—27 Sept 2026, 19:37open

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
26/44983Conditional permission19 Oct 2026390 mPermission for the demolition of an existing steel shed and the construction
26/44930Conditional permission21 Sept 2026235 mRetention Permission for a 45m high freestanding birdcage communications
26/44771Conditional permission8 Sept 2026458 mPermission is sought for development consisting of; (I) Proposed alterations
2544310Conditional20 Jan 20261221 mPermission for development at this time at the ESB Marina Power Generation Station, Centre Park Road, Cork, T12V0HH. The development will consist of: (1) Demolition of the following buildings/structures to ground level: Open Cycle Gas Turbine (OCGT) (c. 719 sq.m) and associated mechanical and electrical ancillaries incl. exhaust duct ( c. 349 sq.m) and stell stack (c. 60m in height); Store Building (c. 225 sq.m) and water treatment/ neutralization plant (c. 34 sq.m); Town Water Storage Tank (c. 158 sq.m) and Firefighting Pumphouse (c. 24 sq.m); Security Guards House at station entrance (35 sq.m); Redundant transformers (c. 12m x 34m x 5m); B Station Boiler House (attached to the A Station "red brick" power generation building) (c. 723 sq.m) Ancillary structures associated with Oil Tank Farm (i.e. pipe bridge across Centre Park Road) (c. 72m in length and c. 8m at highest point); Cooling water Pumphouse (c. 139 sq.m); (2) Installation of temporary cladding to the station A "redbrick" power generation building following the removal of boiler house 4 to keep the building weatherproof and secure. (3) All ancillary site services and site development works to facilitate the proposed demolition works.
2544034Conditional16 Sept 2025331 mPermission is sought for the construction of a single-storey side extension to an existing single-storey dwelling house, new raised decking area to the rear at ground-floor level to replace existing, alterations to existing side elevations, and all associated site works.
2543854Conditional25 Jun 202537 mPermission for the following Large Scale Residential Development (LRD) comprising modifications to part of the Strategic Housing Development permitted under ABP Ref No. 309059-20. The proposed modifications consist of the change of use of the management suite and multi-purpose room permitted in block 3, podium 1 to 2 no. retail units and 1 no. cafe, including signage at the Former Ford Distribution Site, Centre Park Road, Cork. The application may be inspected online at the following website set up by the applicant: www.thesouthdocksamendment.ie
2543663Conditional14 Apr 2025422 mPermission for construction of a new attic conversion with velux windows to existing roof, consisting of one number bedroom, gym and personal cinema and elevations to rear elevation for one number window to the existing two storey dwelling house.
2543588Conditional19 Mar 2025486 mPermission for retention of an existing storage shed to the eastern gable of our dwelling and permission for the construction of a ground floor extension to the rear and first floor extension to the eastern gable of our property

Appeals

ACP caseTypeOutcomeDecidedDistance
502197Refused22 Oct 2026458 m
501514Refused9 Sept 2026261 m
500276Granted with conditions29 May 2026262 m
500316Refused11 Dec 2025262 m
313277Refused27 May 202511 m
319981Refused9 Jan 2025474 m
318290Refused5 Jul 2024493 m
316759Split18 Oct 202329 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 21 Oct 2026 New application · observations close 25 Nov 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 29 Oct 2026, 23:05. Not legal advice — confirm the deadline with Cork City Council before relying on it.