Planning report · Dublin City Council · 500 m around the house · the last 12 months · 1 Nov 2026, 09:39

Eglinton Park

53.31772, -6.23612

Homes here mostly date from the 1970s. Home extensions nearby almost always get approved (93%). 38 homes approved 481 m away haven't started.

See on the mapWatch this area

How planning works, with this area's numbers

steps can overlap · medians for home extensions within 1.5 km, 10 years
  1. 1ApplySite notice up, plans online
  2. 2Comments5 weeks, €20. Comment to keep your right to appeal
  3. 3Decision8 weeks by law. Here 55 days
  4. 4Appeal window4 weeks after the decision
  5. 5AppealHere about 5 months
  6. 6PermissionLasts 5 years
  7. 7StartStart notice to the council. Here about 5 months after
  8. 8Sign-offCompletion cert, or the owner opts out
Question 1

What's the planning story of this house?

Figure 1

When it was built, and the rules since

Most homes here were built 1971–80, after planning permission began and before building regulations (1992).

Timeline from 1955: planning permission needed from October 1964, building regulations from June 1992, building records online from March 2014, sign-off opt-out from September 2015. Most homes here were built 1971–1980.1960197019801990200020102020Oct 1964permission neededJun 1992building regulationsMar 2014building records onlineSep 2015owners may opt out of sign-offThis houseAll of Eglinton ParkBuilt: most homes in this small area date from 1971–1980 (census estimate)most built2021: 2 files on Eglinton Park2022: 3 files on Eglinton Park5 files

Each line is a rule that applies to work done after it.

MeasuredEstimatecouncil register via NPAD · build years: CSO Census 2022, small area

On this site
R2
Zoning · Existing residential
No
Protected or listed · on the council's list
No
Vacant land tax · lived-in homes don't pay it
1 in 10
Radon (EPA) · homes with high radon
Zoning, protection, tax and flood: the detail
Zoning
What it says

Zone Z1 - DEV PLAN 2022-2028

ZoningR2 · Existing residential
What it says

Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

development plan 2022 2028 · 14 Dec 2022 – 31 Dec 2028

ZoningR2 · Existing residential
What it says

Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

development plan 2022 2028 variation no 11 · 14 Dec 2022 – 31 Dec 2028

Radon1 in 10 homes have high radon (EPA)

Not on this site: protected building, heritage inventory, monument zone, conservation area, EU nature site, EU bird site, natural heritage area, tree order, landslide risk, derelict list.

Licensed industrial sites within 1.0 km: Smurfit Paper Mills (338 m)

Vacant land taxNo lived-in homes don't pay it
Flood riskWithin 100 m OPW map area within 100 m · floodinfo.ie
Within 500 mCountFor example
Licensed industrial sites1Smurfit Paper Mills
Radon grid squares3
Monuments19House - 16th/17th century; Windmill
How we work this out
'On this site' means the record's own map outline touches the registered parcel (or a 12 m circle round the point where there is no parcel). Only the council's own list confirms a protected building; ask the council if in doubt. The council's map for the vacant land tax shows this spot inside an area of existing homes. Homes people live in, and their gardens, don't pay the tax. The OPW flood map's licence lets us show a yes/no only.
Sources: Development plan zoning (councils), EPA licensed sites, EPA radon map, Residential Zoned Land Tax maps, Constraint layers (bundle), OPW flood maps (CFRAM), Sites and Monuments Record · fetched 25 Oct 2026, 23:43
SourceLicenceFetchedLink
Development plan zoning (councils)CC BY 4.025 Oct 2026, 23:06open
EPA licensed sitesCC BY 4.027 Sept 2026, 19:36open
EPA radon mapCC BY 4.027 Sept 2026, 19:36open
Residential Zoned Land Tax mapsCC BY 4.025 Oct 2026, 23:43open
Constraint layers (bundle)CC BY 4.0, CC BY-NC-ND 4.027 Sept 2026, 19:37open
OPW flood maps (CFRAM)CC BY-NC-ND 4.0 · shown as a yes/no only11 Sept 2026, 19:11open
Sites and Monuments RecordCC BY 4.027 Sept 2026, 19:29open
How we work this out
Applications whose site outline (or map point) falls on this property. 'No sign building has started' means we found no notice to the council's building control office; small jobs don't always file one, so ask. A missing completion certificate is not proof of a problem: an owner can opt out of official sign-off for a house or extension built for themselves.
Sources: Building Control Management System (commencement notices), National Planning Application Database · fetched 1 Nov 2026, 05:02
SourceLicenceFetchedLink
Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
Question 2

Could you extend?

Nothing on this site restricts it: not protected, not in a conservation area.

Figure 2

What happened to applications like yours

Extensions are almost always approved here: 91–100% by type. A new house in a garden is harder: 80% approved, and 1 in 3 is asked for more information.

Single-storey rear112 decided · more info asked 10%
95% · council 97%
Two-storey rear69 decided · more info asked 30%
99% · council 96%
Two-storey side19 decided · more info asked 26%
100% · council 98%
Single-storey side13 decided · more info asked 15%
100% · council 99%
Attic or dormer164 decided · more info asked 15%
91% · council 96%
First-floor35 decided · more info asked 29%
91% · council 94%
Garage conversion20 decided · more info asked 10%
100% · council 99%
New house in a garden or site49 decided · more info asked 29%
80% · council 71%
Approved nearbyDublin overall

Decided applications within 1.5 km, received in the last 10 years. The kind of work is read from each description.

CalculatedOur classificationcouncil register via NPAD · 481 nearby, 5,627 council-wide

Figure 3

Eglinton Park, file by file since 2021

4 of 4 decided extensions on the road were approved.

5 planning files on Eglinton Park since 2021, by kind and decision.202120222023202420252026Extensions, atticsNo. 4 · 2021 · attic conversion / dormer · approved · WEB1932/21No. 1 · 2021 · two-storey rear · approved · WEB5153/21No. 22 · 2022 · attic conversion / dormer · approved · 3938/22No. 1 · 2022 · attic conversion / dormer · approved · WEB1064/22Porches, roofs, otherNo. 1 · 2022 · other work · approved · WEB1618/22New house in a side garden
ApprovedRefusedWithdrawn or invalid

5 files with "Eglinton Park" in the address within 600 m, other roads of the same name left out. Hover a dot for the house number and reference.

MeasuredOur classificationcouncil register via NPAD · 2021–2026

Extensions and refusals right beside you 5 within 250 m · 0 refused within 100 m

Extensions and refusals near you 5 extensions within 250 m · the last 12 months

2 approved3 no decision or withdrawn
KindAppliedApprovedRefused
Dormer or attic41—
Side11—

Refused within 100 m 0 in the last 12 months

Nothing refused this close in the last 12 months.

    How we work this out
    Home extensions are read from the application's description (extension, attic or dormer, porch, garage conversion, garden room), so a few may be missed or mislabelled. The kind is the first that fits: a dormer with a rear extension counts as a dormer. Refusal reasons come from An Coimisiún Pleanála's inspector reports, so they exist only where the refusal was appealed (Dún Laoghaire-Rathdown so far). The council's own reasons are on its planning file.
    Sources: National Planning Application Database, An Coimisiún Pleanála cases (ArcGIS feed) · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Question 3

    How long, and what if someone objects?

    Figure 4

    A home extension's journey here

    A decision takes 55 days. 1 in 5 is asked for more information, which adds about 70 days. Building starts about 5 months after permission.

    Comments open: 5 weeks · €20; Council decision: 55 days; If more info asked (1 in 5): 128 days; Appeal window: 4 weeks; If appealed: +155 days; Building starts: 151 days after permission0 mo3 mo6 mo9 mo12 mo15 moComments openComments close 5 weeks after the application is lodged5 weeks · €20Council decisionDecision: median 55 days, middle half 53–55 (n=436)55 daysIf more info asked (1 in 5)With further information: median 128 days (n=101)128 daysAppeal windowAnyone who commented can appeal within 4 weeks of the decision4 weeksIf appealedAt An Coimisiún Pleanála: median 155 days (n=128, all appeals within 1.5 km)+155 daysBuilding startsStart notice: median 151 days after permission (n=285)151 days after permissionSigned off386 days after the start, for the few who file. 63% of owners opt out of sign-off

    Bars are medians; whiskers show the middle half. Medians of separate steps don't add up exactly.

    Calculated538 decided home extensions, 287 start notices, 128 decided appeals · within 1.5 km, 10 years · NPAD, BCMS, An Coimisiún Pleanála

    Figure 5

    What appeals changed

    14 of 46 appealed refusals became permissions. 7 of 89 appealed approvals were reversed.

    Refusals appealed46 decided
    14 became permissions
    Approvals appealed89 decided
    7 reversed
    Ended approvedEnded refusedWithdrawn, invalid or other

    Every appeal decided within 1.5 km in 10 years, any kind of development.

    CalculatedAn Coimisiún Pleanála cases linked to the council file

    Appeals nearby 6 in the last 12 months

    None of 1 changed the council's decision

    • 324275 Granted with conditions · Milltown Park, Sandford Road, Dublin 6, D06V9K7 · 192 m report
    • 501334 Pending · Ashton's Public House , 11 Vergemount, Clonskeagh Road, Dublin 6 · 193 m
    • 500647 Granted with conditions · 68 Belmont Avenue, Donnybrook, Dublin 4, D04 Y8W6 · 455 m report
    • 500347 Withdrawn · 4, Vergemount Park, Dublin 6, D06 E0Y0 · 129 m
    • 323882 Invalid · Boole House, Beech Hill Office Campus, Beech Hill Road, Dublin 4,… · 479 m
    • 323883 Invalid · Whether the change of use from office building to temporary… · 428 m
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Courts Service legal diary (judicial reviews), National Planning Application Database · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Courts Service legal diary (judicial reviews)© the publisher31 Oct 2026, 23:12open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Question 4

    What's changing around you?

    Street map around Eglinton Park with 15 numbered planning items
    ⌖ the houseOpen for commentsApproved, not startedAppealNo decision yetApproved
    1. 16 Vergemount Hall, Clonskeagh Road WEB3418/26No decision yet · 265 m
    2. 2A site, which previously formed part of the overall RTÉ Campus WEBLRD6090/26-S3ANo decision yet · 481 m
    3. 3Errigal House 3129/21Approved, no sign building has started · 99 m
    4. 4The Eglinton 3386/22Approved, not started, approval runs out within a year · 277 m
    5. 54, Vergemount Park 500347Appeal: withdrawn · 129 m
    6. 6Milltown Park, Sandford Road 324275Appeal: approved with conditions · 192 m
    7. 7Ashton's Public House, 11 Vergemount 501334Appeal: no decision yet · 193 m
    8. 814 Eglinton Park, Donnybrook WEB2387/26No decision yet · 47 m
    9. 942 Eglinton Road, Donnybrook WEB2579/26No decision yet · 49 m
    10. 1015, Vergemount Park WEB1625/26Approved · 109 m
    11. 1150a Beech Hill Avenue, Donnybrook WEB1033/26Approved · 163 m
    12. 129 Terminus Mills, Clonskeagh Road WEB2507/26No decision yet · 223 m
    13. 1380 Donnybrook Manor, Donnybrook WEB1208/26Approved · 282 m
    14. 14Dublin Bus Depot at the corner of Stillorgan Road and Beaver Row, Dublin 4 WEB6090/25Approved · 301 m
    15. 15c. 0. 131 ha site at the Circle K petrol station at the junction of Donnybrook Road and Brookvale Road Donnybrook, Dublin 4 WEB2780/26No decision yet · 301 m
    Figure 6

    What happens to applications within 500 m

    Permission isn't building. Of 109 permissions since 2016, 49 show a start notice and 8 have a completion certificate. Most owners opt out of sign-off.

    159 applications lodged within 500 m. Council: 110 approved, 17 refused. After appeals: 109 approved. Of those: 8 signed off, 29 built with the owner's opt-out, 12 started, 60 with no start notice found, 0 ran out.LODGEDCOUNCIL DECISIONAFTER APPEALSWHAT HAPPENED NEXT110: lodged → approved17: lodged → refused22: lodged → withdrawn or invalid10: lodged → undecided106: approved → approved14: refused → refused22: withdrawn or invalid → withdrawn10: undecided → undecided1 approved by the council, undecided after an appeal1 approved by the council, refused after an appeal2 approved by the council, withdrawn or invalid after an appeal3 refused by the council, approved after an appeal60: approved → no start notice found29: approved → built, owner opted out12: approved → started, not signed off8: approved → signed off159 lodged159 lodged110 approved110 approved17 refused17 refused22 withdrawn or invalid22 withdrawn or invalid10 undecided10 undecided109 approved109 approved15 refused15 refused24 withdrawn24 withdrawn11 undecided11 undecided60 no start notice found60 no start notice found29 built, owner opted out29 built, owner opted out12 started, not signed off12 started, not signed off8 signed off8 signed off

    Purple bands are refusals turned into permissions on appeal. "No start notice found" includes small jobs that never needed one and notices we couldn't match.

    Measured159 applications in 10 years · NPAD, An Coimisiún Pleanála, BCMS start notices and completion certificates

    Figure 7

    The next 30 days

    6 deadlines within 500 m; the first closes 3 Nov 2026.

    6 deadlines in the next 30 days: 2026-11-03 WEBLRD6090/26-S3A: application received — PROTECTED STRUCTURE: Cairn Homes Montrose Limited intend to apply for Permission for a Large-Scale Residential Developme; 2026-11-04 WEB3014/26: GRANT PERMISSION — CHANGE OF USE: We, Donnybrook Fair Limited, intend to apply for permission for development at 87-91 Morehampton Road, Do; 2026-11-05 WEB3418/26: application received — RETENTION: Retention Permission for developement at this site: 6 Vergemount Hall, Clonskeagh Road, Dublin 6 (D06 V6R2). ; 2026-11-12 WEB3477/26: application received — PROTECTED STRUCTURE: We, Muckross Park Developments Limited, intend to apply for permission for development on a site of; 2026-11-16 WEB3116/26: GRANT PERMISSION — - Conversion of store rooms to habitable accommodation at ground floor level. - Minor modifications to internal layouts ; 2026-11-17 WEB3512/26: application received — CHANGE OF USE: Planning Permission for the following development at 10 Main Street, Donnybrook, Dublin 4: a) Change of utoday6 Nov11 Nov16 Nov21 Nov26 Nov1 DecWEBLRD6090/26-S3A: application received — PROTECTED STRUCTURE: Cairn Homes Montrose Limited intend to apply for Permission for a Large-Scale Residential Developme · 481 m away · 2026-11-03WEB3014/26: GRANT PERMISSION — CHANGE OF USE: We, Donnybrook Fair Limited, intend to apply for permission for development at 87-91 Morehampton Road, Do · 481 m away · 2026-11-04WEB3418/26: application received — RETENTION: Retention Permission for developement at this site: 6 Vergemount Hall, Clonskeagh Road, Dublin 6 (D06 V6R2). · 265 m away · 2026-11-05WEB3477/26: application received — PROTECTED STRUCTURE: We, Muckross Park Developments Limited, intend to apply for permission for development on a site of · 481 m away · 2026-11-12WEB3116/26: GRANT PERMISSION — - Conversion of store rooms to habitable accommodation at ground floor level. - Minor modifications to internal layouts · 481 m away · 2026-11-16WEB3512/26: application received — CHANGE OF USE: Planning Permission for the following development at 10 Main Street, Donnybrook, Dublin 4: a) Change of u · 481 m away · 2026-11-17
    Comments closeTime to appeal ends
    • Comments close 3 Nov 20262 days left
      2application received — PROTECTED STRUCTURE: Cairn Homes Montrose Limited intend to apply for Permission for a…
      €20 to the council · 481 m away
    • Time to appeal ends 4 Nov 20263 days left
      WEB3014/26 · GRANT PERMISSION — CHANGE OF USE: We, Donnybrook Fair Limited, intend to apply for permission for development at 87-91…
      €220 to An Coimisiún Pleanála (€110 observer) · 481 m away
    • Comments close 5 Nov 20264 days left
      1WEB3418/26 · application received — RETENTION: Retention Permission for developement at this site: 6 Vergemount Hall, Clonskeagh…
      €20 to the council · 265 m away
    • Comments close 12 Nov 202611 days left
      WEB3477/26 · application received — PROTECTED STRUCTURE: We, Muckross Park Developments Limited, intend to apply for permission for…
      €20 to the council · 481 m away
    • Time to appeal ends 16 Nov 202615 days left
      WEB3116/26 · GRANT PERMISSION — - Conversion of store rooms to habitable accommodation at ground floor level. - Minor modifications…
      €220 to An Coimisiún Pleanála (€110 observer) · 481 m away
    • Comments close 17 Nov 202616 days left
      WEB3512/26 · application received — CHANGE OF USE: Planning Permission for the following development at 10 Main Street, Donnybrook,…
      €20 to the council · 481 m away

    Measuredcouncil registers and An Coimisiún Pleanála · deadlines worked out from the dates on file

    Figure 8

    Approved, stalled or planned, not built yet

    38 homes 481 m away were approved Oct 2026 with no start notice yet; the permission runs to Oct 2031. BusConnects Core Bus Corridors is planned 992 m away.

    Former Donnybrook Laundry · 38 homes: 38 homes approved Oct 2026, not started; Errigal House · 28 homes: 28 homes approved Dec 2023, not started; The Eglinton · 20 homes: 20 homes approved, not started; runs out Aug 2027; BusConnects Core Bus…: core bus corridor (DLR County Development Plan 2022-2028)20222023202420252026202720282029203020312032Former Donnybrook Laundry · 38 homes481 m · WEB5434/2538 homes approved Oct 2026, not started38 homes approved Oct 2026, not startedErrigal House · 28 homes99 m · 3129/2128 homes approved Dec 2023, not started28 homes approved Dec 2023, not startedThe Eglinton · 20 homes277 m · 3386/2220 homes approved, not started; runs out Aug 202720 homes approved, not started; runs out Aug 2027BusConnects Core Bus…992 m · plannedcore bus corridor (DLR County Development Plan 2022-2028)today

    Each row is a dated fact from a public register: no score and no forecast.

    Measuredcouncil registers, BCMS, derelict sites registers, development plan layers (CC BY 4.0)

    Sites that could change 3 within 500 m

    Approved, not started, approval running out 1

    • The Eglinton · 20 homes approved, not started; runs out Aug 2027 · 277 m

    Approved, not started 2

    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), Derelict sites registers, Council meetings (ModernGov), National Planning Application Database, Residential Zoned Land Tax maps · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    Derelict sites registersCC BY 4.026 Oct 2026, 23:09open
    Council meetings (ModernGov)Public1 Nov 2026, 02:24open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Residential Zoned Land Tax mapsCC BY 4.025 Oct 2026, 23:43open
    Figure 9

    Applications within 500 m, by year

    Between 18 and 35 a year; busiest 2023. 87% of decisions were approvals.

    2021: 25, 2022: 26, 2023: 35, 2024: 18, 2025: 24, 2026: 310102030402021: 17 approved2021: 7 refused2021: 1 withdrawn or invalid25’21*2022: 23 approved2022: 1 refused2022: 2 withdrawn or invalid26’222023: 28 approved2023: 5 refused2023: 2 withdrawn or invalid35’232024: 17 approved2024: 1 refused18’242025: 14 approved2025: 3 refused2025: 7 withdrawn or invalid24’252026: 11 approved2026: 10 withdrawn or invalid2026: 10 undecided31’26*
    ApprovedRefusedWithdrawn or invalidUndecided

    2021 and 2026 are part years (*). Exemption requests and time extensions are left out.

    Measuredcouncil register via NPAD

    Open for comments €20 to comment

    Every application within 500 m 36 in the last 12 months

    See every application on the map

    How we work this out
    Descriptions are shortened by the national planning database (to 80 characters in Dún Laoghaire-Rathdown, 70 in Fingal), and it does not publish applicants' names.
    Sources: National Planning Application Database, An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices) · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    Building work nearby 8 in the last 12 months
    2 not signed off6 no sign-off needed
    • Stillorgan Road, Dublin 4, D04 P8W6 · 1 Sept 2026 · 7-day notice not signed off · WEBLRD6092/25-S3 · 457 m
    • 4 Stillorgan Road, Dublin 4, D04 H9W4 · 31 Aug 2026 · start notice not signed off · WEB2183/26 · 470 m
    • 14 Belmont Avenue, Dublin 4, D04 P890 · 24 Aug 2026 · start notice, opted out no sign-off needed · WEB6033/25 · 463 m
    • 3 Vergemount Park, Dublin, Dublin 6, D06 T1X0 · 4 Apr 2026 · start notice, opted out no sign-off needed · WEB2637/25 · 157 m
    • 71 Belmont Avenue, Donnybrook, Dublin 4, D04 AX97 · 27 Mar 2026 · short notice no sign-off needed · WEB1535/25 · 495 m
    • 4 Vergemount Park, Dublin, Dublin 6, D06 E0Y0 · 21 Jan 2026 · start notice, opted out no sign-off needed · WEB5063/25 · 143 m
    • 12 Donnybrook Court, Dublin, Dublin 4, D04 E8P6 · 16 Jan 2026 · start notice, opted out no sign-off needed · WEB1308/25 · 160 m
    • 1 Vergemount Park, Clonskeagh, Dublin 6, D06YY29 · 17 Dec 2025 · start notice, opted out no sign-off needed · WEB2431/25 · 215 m
    How we work this out
    Each row is a notice the builder sent to the council's building control office before work started. One notice can cover many homes. 'Signed off as finished' means a completion certificate is on file; work done under an opt-out or a short notice doesn't need one.
    Source: Building Control Management System (commencement notices) · fetched 1 Nov 2026, 03:07
    SourceLicenceFetchedLink
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    Homes coming 86 not started
    How we work this out
    Schemes of 10 or more homes approved since 2021, from the council and An Coimisiún Pleanála registers. 'Building started' means the builder told the council's building control office that work was starting (a commencement notice).
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database, Social housing construction status report · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Social housing construction status reportCC BY-SA 4.023 Oct 2026, 23:02open
    Named places nearby: estate, schemes, crèches, schools

    Named places estate, developments, inspections

    Developments within 1.0 km

    SchemeHomesProgressDistance
    Milltown Park636636 not started (2026-Q2)192 m
    Former Smurfit Paper Mills Site167—222 m
    Former Paper Mills Site3030 not started (2026-Q2)223 m
    The Eglinton2020 not started (2026-Q2)261 m
    Circle K Donnybrook84no activity on site reported (2025-Q2)303 m
    Donnybrook4848 not started (2025-Q2)336 m
    Former Donnybrook Laundry38no activity on site reported (2026-Q2)336 m
    RTE Campus at Montrose51015 being built · 495 not started (2026-Q2)414 m

    Who applies most nearby

    • Cairn Homes Montrose Limited — 3 applications, latest 29 Sept 2026
    • Muckross Park Developments Limited — 2 applications, latest 8 Oct 2026
    • Tesco Ireland Limited — 2 applications, latest 11 Aug 2026

    Crèches and schools inspected

    NameLatest inspectionDistance
    Little Steps Montessori · Crèche22 Apr 2026 · report · Tusla Early Years Inspectorate256 m
    David Lloyd Leisure Creche · Crèche5 Aug 2025 · report · Tusla Early Years Inspectorate304 m
    Giraffe Childcare Elm Park · Crèche15 Apr 2026 · report · Tusla Early Years Inspectorate512 m
    Giraffe Childcare Donnybrook · Crèche22 Jan 2025 · report · Tusla Early Years Inspectorate512 m
    The Teresian School (Segovia Trust) · Crèche30 Sept 2024 · report · Tusla Early Years Inspectorate620 m
    Daisychain Montessori & Childcare · Crèche3 Sept 2025 · report · Tusla Early Years Inspectorate843 m
    How we work this out
    Organisations only: a person named on an application is never listed. Inspection dates and links are the publisher's; read their report for the findings.
    Sources: Dublin housing delivery pipeline, National Planning Application Database, Applicant organisations (from the CRO), Department of Education school list, Tusla early years register · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    Dublin housing delivery pipelineCC BY 4.026 Oct 2026, 23:00open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Applicant organisations (from the CRO)Derived by Planning Register25 Oct 2026, 23:01—
    Department of Education school listCC BY 4.027 Oct 2026, 23:04open
    Tusla early years registerPublic register28 Oct 2026, 23:19open
    How busy is this area Busier than most of Dublin City Council.
    Homes approved
    Here66
    Council middle50
    Homes started
    Here622
    Council middle105
    How we work this out
    Homes approved counts schemes of 10 or more homes (one-off houses are not included). Homes started counts every home in a notice that building work was starting. The council figure is the middle value across the council's built-up squares of the same area (3.1 km², about a 1 km circle), so half of them saw more and half fewer.
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.030 Oct 2026, 23:01open
    Building Control Management System (commencement notices)CC BY 4.01 Nov 2026, 03:07open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Question 5

    What's the area like?

    Figure 10

    This street block against the council

    46% owner-occupied (council 47%).

    Homes built before 1971
    48% · council 52%
    Homes built since 2001
    3% · council 19%
    Owner-occupied
    46% · council 47%
    Rented
    50% · council 45%
    Children under 15
    14% · council 15%
    Aged 65 and over
    13% · council 13%
    Households with 2+ cars
    30% · council 19%
    Work mainly from home
    14% · council 12%
    This small area (219 people)Dublin

    MeasuredCSO Census 2022, Small Area Population Statistics (CC BY 4.0) · small area 268129001

    Bus
    198 m
    Clonskeagh Hospital · 11 · busiest stop within 500 m: 30 an hour at peak
    Planned
    992 m
    BusConnects Core Bus Corridors, City to Bray
    Radon
    1 in 10
    homes here likely high (EPA). Test it
    Flood
    Yes
    OPW flood map area within 100 m
    Nearest school
    417 m
    St Marys Central NS, 587 pupils
    Homes sold nearby
    58
    in 3 years (Property Price Register)
    Schools, stops and the council

    Schools

    • St Marys Central NS · primary · 587 pupils · 417 m
    • Muckross Park College · postprimary · 709 pupils · 613 m
    • The Teresian School · postprimary · 230 pupils · 626 m
    • Sandford Parish National School · primary · 196 pupils · 877 m
    • Gonzaga College · postprimary · 576 pupils · 891 m

    Stops 33

    • Clonskeagh Hospital · 11 · 4/hour at peak · 198 m
    • Clonskeagh Hospital · 11 · 3/hour at peak · 232 m
    • Donnybrook Stdm · 116, 118, 11B, 181, 32X, 39A · 29/hour at peak · 309 m
    • Clonskeagh Road · 11 · 4/hour at peak · 314 m
    • Eglinton Road · 11 · 3/hour at peak · 328 m
    • Donnybrook Dpot · 116, 118, 133, 39A, 41X, 740 · 30/hour at peak · 331 m
    • Donnybrook Stdm · 116, 11B, 32X, 39A, 41X, 46n · 24/hour at peak · 346 m
    • Donnybrook Dpot · 116, 120A, 126U, 133, 180, 181 · 23/hour at peak · 377 m

    Schools growing or shrinking planning in 3 years · pupils last year

    • St Marys Central NS · 417 m-3.3% pupils (587)
    • Muckross Park College · 613 m-0.4% pupils (709)
    • The Teresian School · 626 m-3.8% pupils (230)
    • Sandford Parish National School · 877 m-2% pupils (196)
    • Gonzaga College · 891 m+0.5% pupils (576) · an extension 2024, approved

    Open consultations

    Council meetings 20 items

    Public land

    • Dublin City Council · 0.21 ha · 218 m
    • Córas Iompair Éireann · 2.83 ha · 220 m
    • Córas Iompair Éireann · 1.14 ha · 257 m
    • Dublin City Council · 0.25 ha · 326 m
    • The Office of Public Works · 0.14 ha · 359 m
    • Dublin City Council · 1.03 ha · 366 m
    Sources: Public transport stops and routes (NTA GTFS), Department of Education school list, National Planning Application Database, Council consultation portals, Council meetings (ModernGov), Land Development Agency public land register, cso_saps_2022, National Transport Authority, Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0), dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0), EPA strategic noise maps, Fingal County Council · fetched 1 Nov 2026, 05:02
    SourceLicenceFetchedLink
    Public transport stops and routes (NTA GTFS)CC BY 4.025 Oct 2026, 23:02open
    Department of Education school listCC BY 4.027 Oct 2026, 23:04open
    National Planning Application DatabaseCC BY 4.01 Nov 2026, 05:02open
    Council consultation portalsPublic1 Nov 2026, 01:08open
    Council meetings (ModernGov)Public1 Nov 2026, 02:24open
    Land Development Agency public land registerCC BY 4.011 Sept 2026, 16:43open
    cso_saps_2022CC BY 4.0—open
    National Transport AuthorityCC BY 4.0——
    Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)CC BY 4.0——
    dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)CC BY 4.0——
    EPA strategic noise mapsCC BY 4.0——
    Fingal County CouncilCC BY 4.0——
    Question 6

    What to ask, and who

    1. Flood risk area within 100 m: can you insure it?
      Ask for: A flood-cover quote before sale agreed.
      Insurer
    2. High radon area (1 in 10 homes): has it been tested?
      Ask for: Radon test results.
      Seller
    3. 28 homes approved 99 m away (Errigal House), not started: what is planned?
      Ask for: The planning file for 3129/21.
      Council
    4. Application 265 m away open for comments until 5 Nov 2026: comment?
      Ask for: The plans on the council's website (€20 to comment).
      Council
    5. Any work done without planning permission?
      Ask for: An opinion of compliance for the whole house.
      Seller · solicitor
    Reference

    Where this is, the terms, the sources

    Electoral division
    Rathmines East B
    Electoral area
    Pembroke
    Council
    Dublin City Council
    Everything we found, as a list 8 lines
    • Zoned R2 (existing residential); not protected; no vacant land tax; flood risk area within 100 m; high radon area.
    • 3 sites nearby could change: 3 approved schemes.
    • 4 applications open for comments nearby; nearest closes 5 Nov 2026.
    • 86 homes approved nearby, not started; largest 38 at Former Donnybrook Laundry.
    • Donnybrook Dpot (bus 116, 118) 331 m away: 30 an hour at morning peak; 156 from all stops within 500 m. Planned: BusConnects Core Bus Corridors 992 m away, core bus corridor (DLR County Development Plan 2022-2028).
    • Here (2022 census): 50% rent (council 45%); 24% of homes empty (council 8%); most built 1971–1980; 31% drive to work (council 28%); population down 6% since 2016.
    • 5 home extensions within 250 m since 2026. Most were dormers or attic conversions.
    • Around here the council decides in a median 55 days (about 8 weeks); 1 in 5 is asked for more information.
    What the terms mean 8 terms
    • Vacant land tax (Residential Zoned Land Tax (RZLT)): A yearly tax of 3% of the land's value on land that is zoned for homes and serviced but left unbuilt.
    • Building started (Commencement notice (BCMS)): The builder must tell the council's building control office 14 to 28 days before work starts.
    • Signed off as finished (Certificate of Compliance on Completion): A certificate filed when a building is finished, confirming it meets the building regulations.
    • Approved (Grant of permission): The council said yes, usually with conditions.
    • Approval ran out without being built (Permission lapsed / expired): Most permissions last five years.
    • Comment on an application (Observation / submission): Anyone can comment on a planning application within five weeks of it being lodged, for a €20 fee.
    • Appeal (Appeal to An Coimisiún Pleanála): The applicant, or anyone who commented in time, can appeal the council's decision within four weeks.
    • What the land is zoned for (Zoning objective): The council's development plan sets what each area is for: homes, shops, open space and so on.
    Sources and licences 31
    SourcePublisherLicenceFetched
    EPA strategic noise maps—CC BY 4.0—
    Fingal County Council—CC BY 4.0—
    Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)—CC BY 4.0—
    National Transport Authority—CC BY 4.0—
    services-eu1.arcgis.comAn Coimisiún PleanálaCC BY 4.030 Oct 2026
    data.nbco.gov.ieNational Building Control Office (BCMS)CC BY 4.01 Nov 2026
    data.gov.ieVarious (see each layer)CC BY 4.0, CC BY-NC-ND 4.027 Sept 2026
    gis.epa.ieEnvironmental Protection AgencyCC BY 4.027 Sept 2026
    s3.eu-west-1.amazonaws.comOffice of Public WorksCC BY-NC-ND 4.0 · flag only11 Sept 2026
    gis.epa.ieEnvironmental Protection AgencyCC BY 4.027 Sept 2026
    services-eu1.arcgis.comNational Monuments Service (SMR)CC BY 4.027 Sept 2026
    dlrcoco.citizenspace.comLocal authorities (consultation portals)Public1 Nov 2026
    www2.courts.ie—© the publisher31 Oct 2026
    cso.ie—CC BY 4.0—
    dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)—CC BY 4.0—
    services-eu1.arcgis.comLocal authorities (derelict sites registers)CC BY 4.026 Oct 2026
    services.arcgis.comDublin local authorities (housing delivery pipeline)CC BY 4.026 Oct 2026
    esbnetworks.ie—© the publisher · flag only11 Sept 2026
    transportforireland.ieNational Transport AuthorityCC BY 4.025 Oct 2026
    lda.ieLand Development AgencyCC BY 4.011 Sept 2026
    meetings.fingal.ieLocal authorities (council meetings)Public1 Nov 2026
    services.arcgis.comDepartment of Housing (National Planning Application Database)CC BY 4.01 Nov 2026
    organisationsPlanning Register (derived from applications and the CRO register)Derived by Planning Register25 Oct 2026
    services-eu1.arcgis.comTailte ÉireannCC BY 4.011 Sept 2026
    services-eu1.arcgis.comCSO, Tailte Éireann, OpenStreetMap contributorsCC BY 4.04 Oct 2026
    propertypriceregister.ieProperty Services Regulatory Authority (PPR)© PSRA, PSI licence1 Nov 2026
    services.arcgis.comLocal authorities (RZLT maps)CC BY 4.025 Oct 2026
    gov.ieDepartment of EducationCC BY 4.027 Oct 2026
    gov.ieDepartment of HousingCC BY-SA 4.023 Oct 2026
    tusla.ieTusla (Early Years Inspectorate)Public register28 Oct 2026
    services.arcgis.comLocal authorities via the Department of Housing (GZT / MyPlan)CC BY 4.025 Oct 2026
    Measured
    counted from a public register
    Calculated
    a rate or median we worked out from those counts
    Our classification
    we sorted it by reading each description
    Estimate
    inferred from another source (census, map data)
    Rule summary
    the law, simplified: check before relying on it
    How we work this out
    Generated 1 Nov 2026, 09:39 from the Planning Register store; nothing was fetched live. Not a legal search: the council's planning file is the record. Deadlines come from published dates under the Planning and Development Act 2000: confirm with the council before relying on them. Street map © OpenStreetMap contributors; building outlines © Overture Maps Foundation. The text version carries every figure with its source, for an AI assistant.