Homes here mostly date from 1919–1945. Home extensions nearby almost always get approved (95%). 201 homes approved 1.9 km away haven't started.

See on the mapWatch this area
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.

How planning works, with this area's numbers

steps can overlap · medians for home extensions within 1.5 km, 10 years
  1. 1ApplySite notice up, plans online
  2. 2Comments5 weeks, €20. Comment to keep your right to appeal
  3. 3Decision8 weeks by law. Here 46 days
  4. 4Appeal window4 weeks after the decision
  5. 5AppealAt An Coimisiún Pleanála
  6. 6PermissionLasts 5 years
  7. 7StartStart notice to the council. Here about 5 months after
  8. 8Sign-offCompletion cert, or the owner opts out
Question 1

What's the planning story of this house?

Figure 1

When it was built, and the rules since

Most homes here were built 1919–45, before planning permission was needed.

Timeline from 1915: planning permission needed from October 1964, building regulations from June 1992, building records online from March 2014, sign-off opt-out from September 2015. Most homes here were built 1919–1945.19201930194019501960197019801990200020102020Oct 1964permission neededJun 1992building regulationsMar 2014building records onlineSep 2015owners may opt out of sign-offThis houseAll of BryanstownBuilt: most homes in this small area date from 1919–1945 (census estimate)most built2017: 1 file on Bryanstown2018: 2 files on Bryanstown2019: 1 file on Bryanstown2020: 2 files on Bryanstown2021: 1 file on Bryanstown2022: 1 file on Bryanstown2024: 3 files on Bryanstown2025: 4 files on Bryanstown15 files

Each line is a rule that applies to work done after it.

MeasuredEstimatecouncil register via NPAD · build years: CSO Census 2022, small area

On this site
R2
Zoning · Existing residential
No
Protected or listed · on the council's list
No
Vacant land tax · lived-in homes don't pay it
Zoning, protection, tax and flood: the detail
ZoningR2 · Existing residential
What it says

Existing Residential: To protect and enhance the amenity and character of existing residential communities.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

louth county development plan · 11 Nov 2021 – 1 Jan 2027

Monument zone1 within 100 m Mound, Bryanstown

Not on this site: protected building, heritage inventory, conservation area, EU nature site, EU bird site, natural heritage area, tree order, landslide risk, derelict list.

Licensed industrial sites within 1.0 km: Superwarm Homes (Limerick) Limited (558 m); Tirlán Limited (699 m)

Vacant land taxNo lived-in homes don't pay it
Flood riskNone mapped within 2.0 km
Within 2.0 kmCountFor example
Heritage inventory buildings324Boyne View; Mary's Villa
Radon grid squares1
Monuments108Ritual site - holy well; Church
How we work this out
'On this site' means the record's own map outline touches the registered parcel (or a 12 m circle round the point where there is no parcel). Only the council's own list confirms a protected building; ask the council if in doubt. The council's map for the vacant land tax shows this spot inside an area of existing homes. Homes people live in, and their gardens, don't pay the tax. The OPW flood map's licence lets us show a yes/no only. Land on the vacant land tax map nearby: 44 on the draft 2027 map; 44 on the final 2026 map.
Sources: zoning, constraints.smr, epa_leap, rzlt, constraints, constraints.niah, constraints.radon · fetched 4 Oct 2026, 23:11
SourceLicenceFetchedLink
zoningCC-BY-4.04 Oct 2026, 23:11open
constraints.smrCC-BY-4.027 Sept 2026, 19:29open
epa_leapCC-BY-4.05 Oct 2026, 23:09open
rzltCC-BY-4.04 Oct 2026, 23:59open
constraintsmixed — CC-BY-4.0 except OPW flood (CC-BY-NC-ND-4.0, publishable=false)27 Sept 2026, 19:37open
constraints.niahCC-BY-4.027 Sept 2026, 19:35open
constraints.radonCC-BY-4.027 Sept 2026, 19:36open
How we work this out
Applications whose site outline (or map point) falls on this property. 'No sign building has started' means we found no notice to the council's building control office; small jobs don't always file one, so ask. A missing completion certificate is not proof of a problem: an owner can opt out of official sign-off for a house or extension built for themselves.
Sources: bcms, npad · fetched 9 Oct 2026, 23:23
SourceLicenceFetchedLink
bcmsCC-BY-4.09 Oct 2026, 23:23open
npadCC-BY-4.010 Oct 2026, 01:42open
Question 2

Could you extend?

Nothing on this site restricts it: not protected, not in a conservation area.

Figure 2

What happened to applications like yours

Extensions are almost always approved here: 88–100% by type. A new house in a garden is harder: 95% approved, and 1 in 2 are asked for more information.

Single-storey rear51 decided · more info asked 16%
98% · council 98%
Two-storey rear27 decided · more info asked 33%
93% · council 95%
Single-storey side25 decided · more info asked 24%
100% · council 100%
Attic or dormer17 decided · more info asked 12%
88% · council 93%
First-floor23 decided · more info asked 13%
96% · council 95%
New house in a garden or site22 decided · more info asked 50%
95% · council 68%
Approved nearbyLouth overall

Decided applications within 1.5 km, received in the last 10 years. The kind of work is read from each description.

CalculatedOur classificationcouncil register via NPAD · 165 nearby, 2,235 council-wide

Figure 3

Bryanstown, file by file since 2017

6 of 6 decided extensions on the road were approved. New houses in side gardens or on sites: 2 of 2.

15 planning files on Bryanstown since 2017, by kind and decision.2017201820192020202120222023202420252026Extensions, atticsNo. 129 · 2017 · other extension · approved · 17382No. 10 · 2018 · attic conversion / dormer · approved · 18345No. 9 · 2018 · rear · approved · 18700No number · 2022 · other extension · approved · 221365No. 72 · 2025 · single-storey rear · approved · 2525No. 20 · 2025 · attic conversion / dormer · approved · 2560132Porches, roofs, otherNo number · 2019 · other work · approved · 19763No number · 2020 · other work · approved · 201022No. 35 · 2020 · other work · approved · 20172No number · 2021 · other work · approved · 21249No. 21 · 2024 · other work · approved · 2460474No number · 2025 · other extension · approved · 2560187No number · 2025 · other work · approved · 2560463New house in a side gardenNo. 10 · 2024 · new house · approved · 246013310No. 20 · 2024 · new house · approved · 2460134
ApprovedRefusedWithdrawn or invalid

15 files with "Bryanstown" in the address within 600 m, other roads of the same name left out. Hover a dot for the house number and reference.

MeasuredOur classificationcouncil register via NPAD · 2017–2026

Extensions and refusals right beside you 3 within 250 m · 0 refused within 100 m

Extensions and refusals near you 3 extensions within 250 m · the last 12 months

1 approved1 refused1 no decision or withdrawn
KindAppliedApprovedRefused
Rear201
Single-storey rear11—

On Bailtíní Mhuire: 4 extensions in 10 years, 100% of all applications approved; most common two-storey rear.

Refused within 100 m 0 in the last 12 months

Nothing refused this close in the last 12 months.

    How we work this out
    Home extensions are read from the application's description (extension, attic or dormer, porch, garage conversion, garden room), so a few may be missed or mislabelled. The kind is the first that fits: a dormer with a rear extension counts as a dormer. Refusal reasons come from An Coimisiún Pleanála's inspector reports, so they exist only where the refusal was appealed (Dún Laoghaire-Rathdown so far). The council's own reasons are on its planning file.
    Sources: npad, acp · fetched 10 Oct 2026, 01:42
    SourceLicenceFetchedLink
    npadCC-BY-4.010 Oct 2026, 01:42open
    acpCC-BY-4.09 Oct 2026, 23:03open
    Sources: acp, bcms, npad · fetched 9 Oct 2026, 23:03
    SourceLicenceFetchedLink
    acpCC-BY-4.09 Oct 2026, 23:03open
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    npadCC-BY-4.010 Oct 2026, 01:42open
    Question 3

    How long, and what if someone objects?

    Figure 4

    A home extension's journey here

    A decision takes 46 days. 1 in 5 is asked for more information, which adds about 144 days. Building starts about 5 months after permission.

    Comments open: 5 weeks · €20; Council decision: 46 days; If more info asked (1 in 5): 192 days; Appeal window: 4 weeks; Building starts: 161 days after permission0 mo3 mo6 mo9 mo12 mo15 moComments openComments close 5 weeks after the application is lodged5 weeks · €20Council decisionDecision: median 46 days, middle half 44–50 (n=172)46 daysIf more info asked (1 in 5)With further information: median 192 days (n=42)192 daysAppeal windowAnyone who commented can appeal within 4 weeks of the decision4 weeksBuilding startsStart notice: median 161 days after permission (n=57)161 days after permissionSigned off412 days after the start, for the few who file. 56% of owners opt out of sign-off

    Bars are medians; whiskers show the middle half. Medians of separate steps don't add up exactly.

    Calculated214 decided home extensions, 57 start notices · within 1.5 km, 10 years · NPAD, BCMS, An Coimisiún Pleanála

    Figure 5

    What appeals changed

    3 of 12 appealed refusals became permissions. 4 of 19 appealed approvals were reversed.

    Refusals appealed12 decided
    3 became permissions
    Approvals appealed19 decided
    4 reversed
    Ended approvedEnded refusedWithdrawn, invalid or other

    Every appeal decided within 1.5 km in 10 years, any kind of development.

    CalculatedAn Coimisiún Pleanála cases linked to the council file

    Appeals nearby 5 in the last 12 months
    • 501863 Pending · 'Bells Court' Scholes Lane , and adjacent lands to the rear of Nos.… · 1.2 km
    • 500970 Refused · Donore Road, Drogheda, Co. Louth · 1.4 km
    • 501565 Open · 3 Singleton Cottages , Drogheda , Co. Louth, A92 Y67F · 2.0 km
    • 500759 Granted with conditions · Hanwell House, Beamore Road, Bryanstown Co. Meath A92 F9D3 · 1.2 km
    • 324143 Pending · 10 Shop Street, Drogheda, Co. Louth, A92 AXD5. · 826 m
    Sources: acp, courts, npad · fetched 9 Oct 2026, 23:03
    SourceLicenceFetchedLink
    acpCC-BY-4.09 Oct 2026, 23:03open
    courtsall-rights-reserved10 Oct 2026, 01:25open
    npadCC-BY-4.010 Oct 2026, 01:42open
    Question 4

    What's changing around you?

    Street map around Bailtíní Mhuire with 15 numbered planning items
    ⌖ the houseOpen for commentsWindow closingApproved, not startedBuilding site that stopped
    1. 1The Yard of No. 1 Palace Street, Drogheda 2660629No decision yet · 833 m
    2. 2103 Shrewsbury Manor, Greenhills Newtownstalaban 2660658No decision yet · 1.2 km
    3. 3Site to the rear of Corrigan’s Pub 91-93 George’s Street, and rear of 94 and 95 George’s Street and the Boyne Centre at Bolton Street 2660619No decision yet · 1.3 km
    4. 434 Silverstream Avenue Stameen, Drogheda 2660660No decision yet · 1.6 km
    5. 512-13 Thomas Street, Drogheda 2660073Approved with conditions · 957 m
    6. 6The Cloister, 13 Beaubec 2660543Approved with conditions · 991 m
    7. 774-76 West Street, Drogheda 2660525Approved with conditions · 1.2 km
    8. 8Bayview House and Bayview Cottage 2360286Approved, no sign building has started · 170 m
    9. 9Saint Mary's Villas, Drogheda 201086Building site that stopped · 185 m
    10. 10Knockmount 201022Approved, not started, approval runs out within a year · 251 m
    11. 11Twenties Lane, Drogheda 071507Building site that stopped · 626 m
    12. 12Cord Road Greenhills Road North Strand Road 22504Approved, no sign building has started · 888 m
    13. 1326 28 29 30 & 31 George's Street & Trinity Gardens 21396Approved, no sign building has started · 1.4 km
    14. 14Gravel Walk 2360028Approved, no sign building has started · 1.5 km
    15. 15Boyne Road 2360053Approved, no sign building has started · 1.6 km
    Figure 6

    What happens to applications within 500 m

    Permission isn't building. Of 71 permissions since 2016, 18 show a start notice and 6 have a completion certificate.

    74 applications lodged within 500 m. Council: 72 approved, 2 refused. After appeals: 71 approved. Of those: 6 signed off, 9 built with the owner's opt-out, 3 started, 35 with no start notice found, 18 ran out.LODGEDCOUNCIL DECISIONAFTER APPEALSWHAT HAPPENED NEXT72: lodged → approved2: lodged → refused71: approved → approved2: refused → refused1 approved by the council, refused after an appeal35: approved → no start notice found9: approved → built, owner opted out3: approved → started, not signed off6: approved → signed off18: approved → ran out74 lodged74 lodged72 approved72 approved2 refused2 refused71 approved71 approved3 refused3 refused35 no start notice found35 no start notice found9 built, owner opted out9 built, owner opted out3 started, not signed off3 started, not signed off6 signed off6 signed off18 ran out18 ran out

    Purple bands are refusals turned into permissions on appeal. "No start notice found" includes small jobs that never needed one and notices we couldn't match.

    Measured74 applications in 10 years · NPAD, An Coimisiún Pleanála, BCMS start notices and completion certificates

    Figure 7

    The next 30 days

    7 deadlines within 2.0 km; the first closes 14 Oct 2026.

    7 deadlines in the next 30 days: 2026-10-14 2660619: application received — Permission and Retention: The development consists of (A) Demolition of the former store (c. 84 sqm) located to the rea; 2026-10-16 2660543: CONDITIONAL — Permission for the conversion of an existing garage to habitable space, extension of dwelling over converted garage and ; 2026-10-16 2660073: CONDITIONAL — Retention and Permission for the following: a) The retention of the change of use from public house to residential use ; 2026-10-16 2660629: application received — Retention permission for a food truck, ancillary corrugated structures containing, a kitchen, food storage area and a W.; 2026-10-16 2660525: CONDITIONAL — Retention and Permission for development to Protected Structure Ref. No. DB-239 (NIAH Ref. No. 13618011) and located wit; 2026-10-29 2660660: application received — Permission for the following: 1. Proposed new single storey extension to rear of existing dwelling. 2. Alterations to ; 2026-10-29 2660658: application received — Retention Permission: The development consists of: 1. Retention permission for the subdivision of 103 Shrewsbury Manor today15 Oct20 Oct25 Oct30 Oct4 Nov9 Nov2660619: application received — Permission and Retention: The development consists of (A) Demolition of the former store (c. 84 sqm) located to the rea · 1.3 km away · 2026-10-142660543: CONDITIONAL — Permission for the conversion of an existing garage to habitable space, extension of dwelling over converted garage and · 991 m away · 2026-10-162660073: CONDITIONAL — Retention and Permission for the following: a) The retention of the change of use from public house to residential use · 957 m away · 2026-10-162660629: application received — Retention permission for a food truck, ancillary corrugated structures containing, a kitchen, food storage area and a W. · 833 m away · 2026-10-162660525: CONDITIONAL — Retention and Permission for development to Protected Structure Ref. No. DB-239 (NIAH Ref. No. 13618011) and located wit · 1.2 km away · 2026-10-162660660: application received — Permission for the following: 1. Proposed new single storey extension to rear of existing dwelling. 2. Alterations to · 1.6 km away · 2026-10-292660658: application received — Retention Permission: The development consists of: 1. Retention permission for the subdivision of 103 Shrewsbury Manor · 1.2 km away · 2026-10-29
    Comments closeTime to appeal ends
    • Comments close 14 Oct 20264 days left
      32660619 · application received — Permission and Retention: The development consists of (A) Demolition of the former store (c. 84…
      €20 to the council · 1.3 km away
    • Time to appeal ends 16 Oct 20266 days left
      62660543 · CONDITIONAL — Permission for the conversion of an existing garage to habitable space, extension of dwelling over…
      €220 to An Coimisiún Pleanála (€110 observer) · 991 m away
    • Time to appeal ends 16 Oct 20266 days left
      52660073 · CONDITIONAL — Retention and Permission for the following: a) The retention of the change of use from public house to…
      €220 to An Coimisiún Pleanála (€110 observer) · 957 m away
    • Comments close 16 Oct 20266 days left
      12660629 · application received — Retention permission for a food truck, ancillary corrugated structures containing, a kitchen,…
      €20 to the council · 833 m away
    • Time to appeal ends 16 Oct 20266 days left
      72660525 · CONDITIONAL — Retention and Permission for development to Protected Structure Ref. No. DB-239 (NIAH Ref. No. 13618011)…
      €220 to An Coimisiún Pleanála (€110 observer) · 1.2 km away
    • Comments close 29 Oct 202619 days left
      42660660 · application received — Permission for the following: 1. Proposed new single storey extension to rear of existing…
      €20 to the council · 1.6 km away
    • Comments close 29 Oct 202619 days left
      22660658 · application received — Retention Permission: The development consists of: 1. Retention permission for the subdivision…
      €20 to the council · 1.2 km away

    Measuredcouncil registers and An Coimisiún Pleanála · deadlines worked out from the dates on file

    Figure 8

    Approved, stalled or planned, not built yet

    201 homes 1.9 km away were approved Nov 2021 with no start notice yet; the permission runs to Nov 2026. 2 building sites nearby stopped before sign-off. DART+ Coastal North is planned 284 m away.

    Dublin Road · 201 homes: 201 homes approved, not started; runs out Nov 2026; Boyne Road · 192 homes: 192 homes approved Dec 2023, not started; Twenties Lane, Drogheda · 144 homes: 144 homes, started Sep 2017, never signed off; 26 28 29 30 & 31 George's… · 57 homes: 57 homes approved Dec 2021, not started; DART+ Coastal North, Drogheda…: railway order approved (An Coimisiún Pleanála; applied July 2024); DART+ Coastal North, DART+…: railway order approved (An Coimisiún Pleanála; applied July 2024)2017201820192020202120222023202420252026202720282029Dublin Road · 201 homes1.9 km · SH311028201 homes approved, not started; runs out Nov 2026201 homes approved, not started; runs out Nov 2026Boyne Road · 192 homes1.6 km · 2360053192 homes approved Dec 2023, not started192 homes approved Dec 2023, not startedTwenties Lane, Drogheda · 144 homes626 m · 071507144 homes, started Sep 2017, never signed off144 homes, started Sep 2017, never signed off26 28 29 30 & 31 George's… · 57 homes1.4 km · 2139657 homes approved Dec 2021, not started57 homes approved Dec 2021, not startedDART+ Coastal North, Drogheda…284 m · plannedrailway order approved (An Coimisiún Pleanála; applied July 2024)DART+ Coastal North, DART+…297 m · plannedrailway order approved (An Coimisiún Pleanála; applied July 2024)today

    Each row is a dated fact from a public register: no score and no forecast.

    Measuredcouncil registers, BCMS, derelict sites registers, development plan layers (CC BY 4.0)

    Sites that could change 21 within 2.0 km

    Building site that stopped 2

    • 9Saint Mary's Villas, Drogheda · 55 homes, started Jun 2023, never signed off · 185 m
    • 11Twenties Lane, Drogheda · 144 homes, started Sep 2017, never signed off · 626 m

    Approved, not started, approval running out 3

    Approved, not started 6

    Empty land zoned for homes 10

    • 6.1 ha zoned for homes · no homes built on it yet · 441 m
    • 4.1 ha zoned for homes · no homes built on it yet · 903 m
    • 2.1 ha zoned for homes · no homes built on it yet · 1.0 km
    • 1.2 ha zoned for homes · no homes built on it yet · 1.1 km
    • 0.8 ha zoned for homes · no homes built on it yet · 1.1 km
    • 0.2 ha zoned for homes · no homes built on it yet · 1.1 km
    • 0.5 ha zoned for homes · no homes built on it yet · 1.2 km
    • 1.3 ha zoned for homes · no homes built on it yet · 1.2 km
    • 6.6 ha zoned for homes · no homes built on it yet · 1.3 km
    • 0.5 ha zoned for homes · no homes built on it yet · 1.4 km

    Not covered here: council land to be sold, empty land zoned for homes (Dublin only).

    Sources: acp, bcms, derelict, npad · fetched 9 Oct 2026, 23:03
    SourceLicenceFetchedLink
    acpCC-BY-4.09 Oct 2026, 23:03open
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    derelictCC-BY-4.05 Oct 2026, 09:35open
    npadCC-BY-4.010 Oct 2026, 01:42open
    Figure 9

    Applications within 500 m, by year

    Between 5 and 12 a year; busiest 2025. 97% of decisions were approvals.

    2017: 6, 2018: 6, 2019: 8, 2020: 5, 2021: 9, 2022: 10, 2023: 5, 2024: 10, 2025: 12, 2026: 3051015202017: 6 approved6’17*2018: 6 approved6’182019: 7 approved2019: 1 refused8’192020: 5 approved5’202021: 9 approved9’212022: 10 approved10’222023: 5 approved5’232024: 10 approved10’242025: 12 approved12’252026: 2 approved2026: 1 refused3’26*
    ApprovedRefusedWithdrawn or invalidUndecided

    2017 and 2026 are part years (*). Exemption requests and time extensions are left out.

    Measuredcouncil register via NPAD

    Open for comments €20 to comment

    Every application within 2.0 km 101 in the last 12 months

    See every application on the map

    How we work this out
    Descriptions are shortened by the national planning database (to 80 characters in Dún Laoghaire-Rathdown, 70 in Fingal), and it does not publish applicants' names.
    Sources: npad, acp, bcms · fetched 10 Oct 2026, 01:42
    SourceLicenceFetchedLink
    npadCC-BY-4.010 Oct 2026, 01:42open
    acpCC-BY-4.09 Oct 2026, 23:03open
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    Building work nearby 44 in the last 12 months
    7 signed off as finished23 not signed off14 no sign-off needed
    • 94 Maple Drive, Drogheda, Louth, A92 EH6N · 16 Oct 2026 · 1 homes · start notice, opted out no sign-off needed · 2560091 · 1.1 km
    • 9 Stameen Lawns, Drogheda, Louth, A92 C6XV · 12 Oct 2026 · 1 homes · short notice no sign-off needed · 2560481 · 1.5 km
    • Rathmullan Park, Drogheda, Louth · 12 Oct 2026 · 4 homes · start notice not signed off · 2474 · 1.9 km
    • Marsh Road, Drogheda, Louth, A92 HF5F · 5 Oct 2026 · 7-day notice not signed off · 572 m
    • Block 3, PH#9 Avourwen, Drogheda, Meath · 26 Sept 2026 · 30 homes · 7-day notice not signed off · 2460832 · 1.2 km
    • Block 2, PH#9 Avourwen, Duleek rd, Drogheda, Meath · 26 Sept 2026 · 30 homes · 7-day notice not signed off · 2460832 · 1.3 km
    • 90 Five Oaks, Drogheda, Louth, A92 X3P6 · 24 Sept 2026 · 1 homes · start notice, opted out no sign-off needed · 211379 · 1.5 km
    • Block 1, PH#9 Avourwen, Duleek rd, Drogheda, Meath · 16 Sept 2026 · 30 homes · 7-day notice not signed off · 2460832 · 1.4 km
    • 7 Donore Avenue, Drogheda, Louth · 31 Aug 2026 · start notice not signed off · 21-760 · 1.3 km
    • 39 West Street, Drogheda, Louth, A92 XRX9 · 27 Aug 2026 · 1 homes · short notice no sign-off needed · 2660074 · 1.2 km
    • 104 Newfield Estate, Drogheda, Louth, A92 YR8D · 17 Aug 2026 · 1 homes · start notice, opted out no sign-off needed · 2660115 · 1.5 km
    • Marsh Road, Drogheda, Louth, A92 N627 · 10 Aug 2026 · 7-day notice signed off · 572 m
    • 3 Legavoureen Park, Drogheda, Louth, A92 E51W · 10 Aug 2026 · 1 homes · start notice, opted out no sign-off needed · 2560433 · 313 m
    • Windmill Road, Moneymore,, Drogheda, Louth, A92 VW28 · 27 Jul 2026 · 7-day notice not signed off · 2560729 · 1.7 km
    • 20 Saint Laurence Street, Drogheda, Louth, A92 FP2N · 10 Jul 2026 · 7-day notice signed off · 834 m
    • Mayoralty Street, Drogheda, Louth · 9 Jul 2026 · 7-day notice signed off · 19/490 · 761 m
    • 9 Mount Saint Oliver, Drogheda, Louth, A92 K3VN · 3 Jul 2026 · 1 homes · start notice, opted out no sign-off needed · 2660152 · 746 m
    • Marsh Road, Drogheda, Louth · 24 Jun 2026 · 7-day notice not signed off · 2260005 · 932 m
    • 6 Bolton Street, Drogheda, Louth, A92 AW97 · 22 Jun 2026 · 2 homes · start notice not signed off · 21/808 · 1.3 km
    • Unit 2 Boyne Business Park, Drogheda, Louth, A92 HE00 · 19 Jun 2026 · start notice not signed off · 2460683 · 1.9 km
    • Windmill Road, Drogheda, Louth, A92 VW28 · 18 Jun 2026 · 7-day notice not signed off · 2460385 · 1.7 km
    • Marsh Road, Drogheda, Louth · 16 Jun 2026 · 7-day notice not signed off · 1.1 km
    • Marsh Road, Drogheda, Louth, A92 W271 · 15 Jun 2026 · 7-day notice signed off · 572 m
    • Scarlet Street, Drogheda, Louth, A92 DD73 · 8 Jun 2026 · start notice not signed off · 2460490 · 1.1 km
    • North Road, Drogheda, Louth · 18 May 2026 · 7-day notice not signed off · 2560096 · 1.9 km
    • 15 Copper Close, Drogheda, Louth, A92 H97E · 1 May 2026 · short notice no sign-off needed · 2560576 · 922 m
    • 168 Marian Park, Drogheda, Louth, A92 R2NP · 22 Apr 2026 · 1 homes · start notice, opted out no sign-off needed · 2560822 · 1.2 km
    • 62 Pearse Park, Drogheda, Louth, A92Y016 · 17 Apr 2026 · 1 homes · 7-day notice not signed off · 2560474 · 1.2 km
    • 55 Ballsgrove, Drogheda, Louth, A92 YEF8 · 14 Apr 2026 · 1 homes · start notice, opted out no sign-off needed · 2560611 · 1.7 km
    • Scoth Hall Shopping Centre Marsh Road, Drogheda, Louth, A92 FW99 · 9 Apr 2026 · 7-day notice signed off · 572 m
    • 15 Park View, Drogheda, Louth, A92 HPC6 · 3 Apr 2026 · 7-day notice not signed off · 24214 / 24226 · 1.4 km
    • 80 West Street, Drogheda, Louth, A92 XH95 · 28 Mar 2026 · 5 homes · 7-day notice not signed off · 1.2 km
    • Windmill Road, Moneymore,, Drogheda, Louth, A92 VW28 · 26 Mar 2026 · 7-day notice not signed off · 1.6 km
    • Bryanstown Cross Route, Drogheda, Meath, 000000 · 26 Mar 2026 · 98 homes · start notice not signed off · 22/1365 · 507 m
    • Dominic Street, Drogheda, Louth, A92 R968 · 27 Feb 2026 · start notice not signed off · 2560706 · 1.2 km
    • Roslyn, 4 Greenhills Villas, Drogheda, Louth · 6 Feb 2026 · 1 homes · start notice, opted out no sign-off needed · 2560438 · 1.0 km
    • 6 Stockwell Lane, Drogheda, Louth, A92 RD32 · 4 Feb 2026 · 1 homes · 7-day notice not signed off · 2560458 · 1.0 km
    • Coolfore, Drogheda, Louth, A92E9DK · 28 Dec 2025 · start notice, opted out no sign-off needed · 20194 · 626 m
    • Drogheda MacBride railway station, Drogheda, Louth, A92 W422 · 18 Dec 2025 · start notice not signed off · 368 m
    • 16 Saint Mary's Villas, Drogheda, Louth, A92 ENX0 · 14 Nov 2025 · 1 homes · start notice, opted out no sign-off needed · 2460487 · 62 m
    • 20 Saint Laurence Street, Drogheda, Louth, A92 FP2N · 12 Nov 2025 · start notice signed off · 834 m
    • Unit 8, Boyne Centre, Bolton Street, Drogheda, Louth, A92 YN40 · 10 Nov 2025 · start notice signed off · 2560284 · 1.3 km
    • 1 Oaten Vale, Drogheda, Louth, A92 PK2N · 5 Nov 2025 · 1 homes · start notice not signed off · 20959 · 1.0 km
    • Scarlet Street, Drogheda, Louth, A92 T268 · 13 Oct 2025 · short notice no sign-off needed · 2560355 · 1.1 km
    How we work this out
    Each row is a notice the builder sent to the council's building control office before work started. One notice can cover many homes. 'Signed off as finished' means a completion certificate is on file; work done under an opt-out or a short notice doesn't need one.
    Source: bcms · fetched 9 Oct 2026, 23:23
    SourceLicenceFetchedLink
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    Homes coming 657 not started
    How we work this out
    Schemes of 10 or more homes approved since 2019, from the council and An Coimisiún Pleanála registers. 'Building started' means the builder told the council's building control office that work was starting (a commencement notice).
    Sources: acp, bcms, npad, social_housing · fetched 9 Oct 2026, 23:03
    SourceLicenceFetchedLink
    acpCC-BY-4.09 Oct 2026, 23:03open
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    npadCC-BY-4.010 Oct 2026, 01:42open
    social_housingCC-BY-SA-4.09 Oct 2026, 23:01open
    Named places nearby: estate, schemes, crèches, schools

    Named places estate, developments, inspections

    Estate: Bailtíní Mhuire · 9 applications in 10 years · 100% approved · most common: two-storey rear

    Crèches and schools inspected

    NameLatest inspectionDistance
    Little Treasures Preschool · Crèche13 Jan 2026 · report · Tusla Early Years Inspectorate462 m
    Peter Pan Crèche & Montessori · Crèche12 Jun 2025 · report · Tusla Early Years Inspectorate530 m
    Little Steps Creche & Pre-School · Crèche25 Sept 2025 · report · Tusla Early Years Inspectorate892 m
    Peter Pan Crèche & Montessori · Crèche11 Apr 2024 · report · Tusla Early Years Inspectorate948 m
    How we work this out
    Organisations only: a person named on an application is never listed. Inspection dates and links are the publisher's; read their report for the findings.
    Sources: estates, schools, tusla_ey · fetched 27 Sept 2026, 20:18
    SourceLicenceFetchedLink
    estatesODbL-1.0 (OSM) + CC-BY-SA-4.0 (NHDS) + CC-BY-4.0 (Kildare)27 Sept 2026, 20:18open
    schoolsCC-BY-4.027 Sept 2026, 23:32open
    tusla_eypublic (Tusla statutory register; acknowledgement required, no open licence stated)5 Oct 2026, 23:33open
    How busy is this area Busier than most of Louth County Council.
    Homes approved
    Here226
    Council middle0
    Homes started
    Here177
    Council middle2
    How we work this out
    Homes approved counts schemes of 10 or more homes (one-off houses are not included). Homes started counts every home in a notice that building work was starting. The council figure is the middle value across the council's built-up squares of the same area (3.1 km², about a 1 km circle), so half of them saw more and half fewer.
    Sources: acp, bcms, npad · fetched 9 Oct 2026, 23:03
    SourceLicenceFetchedLink
    acpCC-BY-4.09 Oct 2026, 23:03open
    bcmsCC-BY-4.09 Oct 2026, 23:23open
    npadCC-BY-4.010 Oct 2026, 01:42open
    Question 5

    What's the area like?

    Figure 10

    This street block against the council

    97% of homes built before 1971 (council 28%). 79% owner-occupied (council 67%).

    Homes built before 1971
    97% · council 28%
    Homes built since 2001
    0% · council 33%
    Owner-occupied
    79% · council 67%
    Rented
    12% · council 28%
    Children under 15
    12% · council 21%
    Aged 65 and over
    34% · council 14%
    Households with 2+ cars
    39% · council 38%
    Work mainly from home
    15% · council 10%
    This small area (281 people)Louth

    MeasuredCSO Census 2022, Small Area Population Statistics (CC BY 4.0) · small area 147039002

    Bus
    217 m
    Drogheda Stn · 101, 101X, D4 · busiest stop within 500 m: 7 an hour at peak
    Planned
    284 m
    DART+ Coastal North, Drogheda (MacBride)
    Nearest school
    262 m
    Sacred Heart Secondary School, 717 pupils
    Homes sold nearby
    530
    in 3 years, 53 new (Property Price Register)
    Schools, stops and the council

    Schools

    • Sacred Heart Secondary School · postprimary · 717 pupils · 262 m
    • St Marys Parish Primary School · primary · 967 pupils · 292 m
    • St Mary's Diocesan School · postprimary · 917 pupils · 586 m
    • ABACAS School · primary · 31 pupils · 880 m
    • S N Aonghusa · primary · 147 pupils · 1.1 km
    • Scoil na mBraithre Sn · primary · 359 pupils · 1.1 km
    • S N Naomh Peadar · primary · 92 pupils · 1.3 km
    • S N Ard Mhuire C · primary · 315 pupils · 1.4 km

    Stops 68

    • Drogheda Stn · 101, 101X, D4, D5 · 7/hour at peak · 217 m
    • Drogheda Stn · 101, 101X, 163, D4, D5 · 4/hour at peak · 241 m
    • Drogheda Stn · 163 · 0/hour at peak · 281 m
    • Drogheda (MacBride) · Belfast - Dublin, Dublin - Belfast, Dublin - Drogheda/Dundalk, Dublin - Europort · 4/hour at peak · 284 m
    • Bryanstown Mnr · D4, D5 · 4/hour at peak · 328 m
    • St Mary's Hospital · 101, 101X, 163, D4, D5 · 7/hour at peak · 365 m
    • St Mary's Hospital · 101, 101X, 163, D4, D5 · 4/hour at peak · 393 m
    • Bryanstown Mnr · D4, D5 · 4/hour at peak · 490 m

    Schools growing or shrinking planning in 3 years · pupils last year

    • Sacred Heart Secondary School · 262 m+1.6% pupils (717)
    • St Marys Parish Primary School · 292 m-0.5% pupils (967)
    • St Mary's Diocesan School · 586 m+0.2% pupils (917)
    • ABACAS School · 880 m0% pupils (31)
    Sources: gtfs, schools, npad, consult, moderngov, lda_lands, cso_saps_2022, National Transport Authority, Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0), dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0), EPA strategic noise maps, Fingal County Council · fetched 4 Oct 2026, 23:41
    SourceLicenceFetchedLink
    gtfsCC-BY-4.04 Oct 2026, 23:41open
    schoolsCC-BY-4.027 Sept 2026, 23:32open
    npadCC-BY-4.010 Oct 2026, 01:42open
    consultpublic10 Oct 2026, 01:23open
    moderngovpublic10 Oct 2026, 01:24open
    lda_landsCC-BY-4.011 Sept 2026, 16:43open
    cso_saps_2022CC BY 4.0—open
    National Transport AuthorityCC BY 4.0——
    Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)CC BY 4.0——
    dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)CC BY 4.0——
    EPA strategic noise mapsCC BY 4.0——
    Fingal County CouncilCC BY 4.0——
    Question 6

    What to ask, and who

    1. 54 homes approved 170 m away (Bayview House and Bayview…), not started: what is planned?
      Ask for: The planning file for 2360286.
      Council
    2. Stalled build 185 m away (Saint Mary's Villas, Drogheda): what happens next?
      Ask for: The planning file for 201086.
      Council
    3. Application 833 m away open for comments until 16 Oct 2026: comment?
      Ask for: The plans on the council's website (€20 to comment).
      Council
    4. Any work done without planning permission?
      Ask for: An opinion of compliance for the whole house.
      Seller · solicitor
    Reference

    Where this is, the terms, the sources

    Townland
    Bryanstown
    Electoral division
    St. Lawrence Gate
    Electoral area
    Drogheda Urban
    Council
    Louth County Council
    Everything we found, as a list 8 lines
    • Zoned R2 (existing residential); not protected; no vacant land tax.
    • 21 sites nearby could change: 2 stalled builds, 9 approved schemes, 10 empty zoned plots.
    • 4 applications open for comments nearby; nearest closes 16 Oct 2026.
    • 657 homes approved nearby, not started; largest 201 at Dublin Road.
    • St Mary's Hospital (bus 101, 101X) 365 m away: 7 an hour at morning peak; 35 from all stops within 500 m. Planned: DART+ Coastal North Drogheda (MacBride) 284 m away, railway order approved (An Coimisiún Pleanála; applied July 2024).
    • Here (2022 census): 79% owner-occupied (council 67%); 11% of homes empty (council 8%); most built 1919–1945; 54% drive to work (council 59%); population up 4% since 2016.
    • 3 home extensions within 250 m since 2026. Most were rear extensions. 1 rear extension refused. On Bailtíní Mhuire: 4 in 10 years, 100% approved.
    • The council decides in a median 52 days (about 7 weeks); 40% are asked for more information.
    What the terms mean 9 terms
    • Vacant land tax (Residential Zoned Land Tax (RZLT)): A yearly tax of 3% of the land's value on land that is zoned for homes and serviced but left unbuilt.
    • Building started (Commencement notice (BCMS)): The builder must tell the council's building control office 14 to 28 days before work starts.
    • Signed off as finished (Certificate of Compliance on Completion): A certificate filed when a building is finished, confirming it meets the building regulations.
    • Approved (Grant of permission): The council said yes, usually with conditions.
    • Approval ran out without being built (Permission lapsed / expired): Most permissions last five years.
    • Comment on an application (Observation / submission): Anyone can comment on a planning application within five weeks of it being lodged, for a €20 fee.
    • Appeal (Appeal to An Coimisiún Pleanála): The applicant, or anyone who commented in time, can appeal the council's decision within four weeks.
    • What the land is zoned for (Zoning objective): The council's development plan sets what each area is for: homes, shops, open space and so on.
    • Building site that stopped (Commenced, no completion certificate): A housing build that told the council it was starting at least three years ago, passed its own planned finish date, and has never been signed off as finished.
    Sources and licences 29
    SourcePublisherLicenceFetched
    EPA strategic noise maps—CC BY 4.0—
    Fingal County Council—CC BY 4.0—
    Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)—CC BY 4.0—
    National Transport Authority—CC BY 4.0—
    services-eu1.arcgis.comAn Coimisiún PleanálaCC-BY-4.09 Oct 2026
    data.nbco.gov.ieNational Building Control Office (BCMS)CC-BY-4.09 Oct 2026
    data.gov.ieVarious (see each layer)mixed — CC-BY-4.0 except OPW flood (CC…27 Sept 2026
    services-eu1.arcgis.comNational Inventory of Architectural HeritageCC-BY-4.027 Sept 2026
    gis.epa.ieEnvironmental Protection AgencyCC-BY-4.027 Sept 2026
    services-eu1.arcgis.comNational Monuments Service (SMR)CC-BY-4.027 Sept 2026
    dlrcoco.citizenspace.com | https:Local authorities (consultation portals)public10 Oct 2026
    www2.courts.ie—all-rights-reserved10 Oct 2026
    cso.ie—CC BY 4.0—
    dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)—CC BY 4.0—
    services-eu1.arcgis.comLocal authorities (derelict sites registers)CC-BY-4.05 Oct 2026
    data.epa.ieEnvironmental Protection Agency (LEAP licence register)CC-BY-4.05 Oct 2026
    overpass-api.deOpenStreetMap contributors, NHDS, Kildare County CouncilODbL-1.0 (OSM) + CC-BY-SA-4.0 (NHDS) +…27 Sept 2026
    transportforireland.ieNational Transport AuthorityCC-BY-4.04 Oct 2026
    lda.ieLand Development AgencyCC-BY-4.011 Sept 2026
    meetings.fingal.ieLocal authorities (council meetings)public10 Oct 2026
    services.arcgis.comDepartment of Housing (National Planning Application Database)CC-BY-4.010 Oct 2026
    services-eu1.arcgis.comTailte ÉireannCC-BY-4.011 Sept 2026
    services-eu1.arcgis.comCSO, Tailte Éireann, OpenStreetMap contributorsCC-BY-4.04 Oct 2026
    propertypriceregister.ieProperty Services Regulatory Authority (PPR)PSI — PSRA re-use terms (psr.ie/re-use…10 Oct 2026
    services.arcgis.comLocal authorities (RZLT maps)CC-BY-4.04 Oct 2026
    gov.ieDepartment of EducationCC-BY-4.027 Sept 2026
    gov.ieDepartment of HousingCC-BY-SA-4.09 Oct 2026
    tusla.ieTusla (Early Years Inspectorate)public (Tusla statutory register; ackn…5 Oct 2026
    services.arcgis.comLocal authorities via the Department of Housing (GZT / MyPlan)CC-BY-4.04 Oct 2026
    Measured
    counted from a public register
    Calculated
    a rate or median we worked out from those counts
    Our classification
    we sorted it by reading each description
    Estimate
    inferred from another source (census, map data)
    Rule summary
    the law, simplified: check before relying on it
    How we work this out
    Generated 10 Oct 2026, 19:59 from the Planning Register store; nothing was fetched live. Not a legal search: the council's planning file is the record. Deadlines come from published dates under the Planning and Development Act 2000: confirm with the council before relying on them. Street map © OpenStreetMap contributors; building outlines © Overture Maps Foundation. The text version carries every figure with its source, for an AI assistant.