  1. 12 Sept 2025Received
  2. 6 Nov 2025Approved
  3. 26 Nov 2025Appealed
  4. 2 Jun 2026Appeal: Approved
  5. 2 Jun 2026Final approval
  6. 2 Jun 2031Approval runs out
Status
Appeal decided — granted No start yet
Decision
Approved · 6 Nov 2025
Size
49 apartments · up to 6 storeys
Uses
residential, apartments
Applicant
Focus Housing Association CLG
Site
1,738 m²
Appeal
ACP 500351 · Approved

Building progress councils’ figures, Q3 2025

49 homes proposed; none permitted yet (Q3 2025).

49
homes proposed
0
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started

The scheme

Focus Housing Association CLG proposes a residential development at 28-34 Braithwaite Street and 63-66 Pimlico in Dublin 8. The project consists of 49 apartments set over two blocks ranging from 1 to 6 storeys in height. The development includes associated site works, landscaping, and bicycle parking.

it provides 49 new residential units

What the register says

Permission is sought by Focus Housing Association CLG for development at Nos. 28-34 Braithwaite Street and Nos. 63-66 Pimlico, Dublin 8 (bounded by No. 35 Braithwaite Street to the east and north, Nos. 61 and 62 Pimlico to the north, Braithwaite Street/Poole Street Playground to the west, and by St. Margaret’s Avenue and St. John’s Avenue to the south). The development will consist of the construction of a residential development of 49 no. apartments set over two blocks (connected at ground floor level) ranging from 1-6 storeys in height and consisting of 10 no. studios, 9 no. 1 bed units, 11 no. 2 bed (3-person) units and 19 no. 2 bed (4-person) units, with all apartments provided with private balconies/terraces to north, south, east and west elevations; bin store, plant room, maintenance and store rooms; 1 no. ESB substation; 107 no. bicycle parking spaces (79 no. spaces within bicycle stores at ground floor level and 28 no. spaces within communal courtyard; landscaping including recreational, exercise and play equipment; lighting; boundary treatments; upgrades to existing footpaths with new pedestrian gate to St. Margaret’s Avenue (emergency access/egress only); heat pumps and PV panels at roof level; and all associated engineering and site works necessary to facilitate the development

Summary from the register record.

Planning timeline 4 steps

  • 12 Sept 2025
    Application lodged — Standard
  • 6 Nov 2025
    Council decision — Grant permission
  • 26 Nov 2025
    Appealed to An Coimisiún Pleanála — 500351
  • 2 Jun 2026
    Commission decision — Granted

The site 1,738 m²

Boundary of 28-34 Braithwaite Street and 63-66 Pimlico as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 3 applications in the last 10 years

Appeals inside the site 3 with An Coimisiún Pleanála

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.