PlanningRegister.ie
South Dublin County Council · LRD25A/0009W · Permission

Belgard Square East

199 apartments7 storeysMidsal Homes LimitedTallaght, South Dublin County Council

Approved on appeal May 2026.

  1. 19 Nov 2025Received
  2. 21 Jan 2026Approved
  3. 16 Feb 2026Appealed
  4. 27 May 2026Appeal: Approved with conditions
  5. 27 May 2031Approval runs out
Status
Appeal decided — granted No start yet
Decision
Approved · 21 Jan 2026
Size
199 apartments · up to 7 storeys
Uses
residential, apartments, retail, creche, mixed
Applicant
Midsal Homes Limited
Site
1.19 ha
Appeal
ACP 324080 · Approved with conditions

Building progress councils’ figures, Q2 2026

199 homes permitted; building has not started (Q2 2026).

199
homes proposed
199
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 199 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q4 2025000
Q1 2026000
Q2 202619900

The scheme

Midsal Homes Limited proposes a mixed-use development at Belgard Square East, Belgard Road and Old Blessington Road in Tallaght. The project includes 199 residential dwellings across two blocks ranging from one to seven storeys in height. It also features 2,123 square metres of non-residential floor space including retail units, a medical centre, and a crèche.

it provides 199 residential units and significant non-residential floor space

What the register says

The proposed development principally comprises: the demolition and removal of existing boundary walls and railings on the main development site's eastern, western and northern sides; and the construction of a mixed-use development in 2 No. blocks (Block A to the south and Block B to the north) with a gross floor area of 23,540 sq m (including basement of 275 sq m) and ranging in height from 1 No. to 7 No. storeys (with mezzanine level) over basement. The development includes a total of 199 No. residential dwellings (6 No. studios, 47 No. 1-bed, 98 No. 2-bed and 48 No. 3-bed) in the 2 No. blocks, with Block A comprising 49 No. 'senior living' apartment units and Block B comprising 150 No. 'standard' apartment units. The development also includes 2,123 sq m of non-residential floor space, with the following uses proposed: 4 No. retail units (totalling 331 sq m); 4 No. class 1 / class 2 commercial units (totalling 387 sq m); a bicycle sales and repair shop (81 sq m); an off-licence (64 sq m); a bar (151 sq m); a café (87 sq m); a medical centre (210 sq m); a dental practice (72 sq m); a pharmacy (195 sq m); a beauty/health salon (195 sq m); and a crèche (350 sq m) with external play area. The development also comprises: an undercroft car park accessed via a new entrance/exit at Belgard Square East which provides 58 No. car parking spaces; a gated service lane to the south of Block A, with entrances/exits off Belgard Square East and Belgard Road; 2 No. pedestrian/cycle crossings, at Belgard Square East and Belgard Road; continuation of the northbound cycle lane from Belgard Road onto Old Blessington Road; alteration to the median and northbound right turn at Belgard Road onto Abberley Square; cycle parking; internal communal amenity spaces for the senior living units; hard and soft landscaping, including public open space, communal amenity space and incidental spaces; private amenity spaces (as balconies and terraces facing all directions); boundary treatments; 2 No. sub-stations; plant/operational rooms; bin stores; public lighting; blue roofs; rooftop PV arrays; lift overruns and rooftop opening vents atop both blocks; 4 No. 0.3 m diameter microwave link dishes mounted on 2 No. steel support poles affixed to the Block B lift overrun, all enclosed in radio-friendly GRP shrouds; and all associated works above and below ground. Note for the mixed-use question below: there are too many non-residential uses proposes relative to the lines available, so we have provided the residential floor area and the combined non-residential floor area. See submitted materials for details of the individual non-residential uses. The main development site (approximately 0.91 Ha) is generally bound: to the north by Old Blessington Road; to the east by Belgard Road

Summary from the register record.

Planning timeline 6 steps

  • 19 Nov 2025
    Application lodged — LRD
  • 16 Feb 2026
    Appealed to An Coimisiún Pleanála — 324080
  • 27 May 2026
    Council decision — Grant
  • 27 May 2026
    Commission decision — Granted with conditions
  • 27 May 2026
    Final approval
  • 10 Jul 2031
    Approval runs out (estimate)

The site 1.19 ha

Boundary of Belgard Square East as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 4 applications in the last 10 years

Appeals inside the site 3 with An Coimisiún Pleanála

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.