Permitted, not started · South Dublin · grants of 10+ homes since 2021

South Dublin planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

17,788 homes in 97 sites of 10 or more have been granted permission in South Dublin since 2021. A commencement notice was lodged for 53% of them. 7,934 still have a live permission and no start; 552 of those lapse within a year, and 368 have already lapsed.

17,788
homes permitted · 97 sites
53%
started · 9,464 homes
7,934
not started · live permission
552
lapse within 12 months
368
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 7

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Lucan225,25451%2,575——
Clondalkin296,54473%1,741——
Firhouse-Bohernabreena142,18530%1,278131241
Rathfarnham-Templeogue81,28320%1,024——
Tallaght Central997229%671——
Tallaght South71,00746%546421—
Palmerstown-Fonthill854358%99—127

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021668365%0241
2022132,33676%552—
2023264,67889%375127
2024131,89057%815—
2025132,89346%1,532—
2026265,30812%4,660—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 51% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
South Dublin County Council11,2520%1,252—
Cairn Homes Properties Limited27390%739—
Kelland Homes Limited16110%611—
Hugh McGreevy & Sons Limited14530%453—
Shannon Homes Dublin Unlimited Company14020%402—
Quintain Developments Ireland Limited387159%355—
Stranwil Limited12040%204—
Midsal Homes Limited11990%199—
ARP 4.2 Sustainable Communities (Ireland) Fund11690%169—
MacCabe Durney Barnes Limited11310%131—
Propiteer Ibis Red Cow Limited11150%115—
Evara Developments Limited214727%107—
Kingscroft Developments Limited1900%90—
Greenacre Residential DAC1860%86—
Seabren Developments Limited1550%55—
Hollyville Investments Limited1430%43—
Ballymount Homes Limited1220%22—
Greenwalk Development Limited1130%13—
Adwood Limited21,047100%0—
Capami Limited1523100%0—
Glenveagh Homes Limited1384100%0—
Tetrarch Residential Limited1274100%0—
Ardstone Homes Limited12410%0241
Hugh McGreevy & Sons Limited and Tierra Limited1174100%0—
Square Foot Property Services Limited1170100%0—
Montane Developments (Ireland) Unlimited Company1164100%0—
South Dublin County Council (Housing)3140100%0—
AAI Palmerstown Limited11270%0127
Cairn Homes Properties1122100%0—
Kavco C Town Project Limited186100%0—

Permission, no start 40 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Kishoge Development Area Sites 3, 4 and 5 SDZ25X/00011,25231 Mar 2026Not started lapses in 4 yearsLucan
Boherboy, Saggart LRD25A/0012W61125 Jun 2026Not started lapses in 5 yearsBoherboy
Former Chadwicks Builders Merchant LRD25A/0005W58813 May 2026Not started lapses in 5 yearsGreenhills
Woodtown Development LRD25A/0003W5026 Mar 2026Not started lapses in 4 yearsWoodtown
Kishoge Urban Centre SDZ25A/0012W49425 Aug 2025Not started lapses in 4 yearsClondalkin
Tubber Lane Residential Development SDZ26A/0008W4535 May 2026Not started lapses in 4 yearsLucan
Parkmore Industrial Estate LRD25A/0002W4364 Dec 2025Not started lapses in 4 yearsRathfarnham-Templeogue
Cooldown Commons and Fortunestown SD22A/013342110 Aug 2022Lapsing lapses in 9 monthsTallaght South
Taylor's Lane and Edmondstown Road LRD23A/000240222 Sept 2025Not started lapses in 4 yearsBallyboden
Aderrig Phase 4 SDZ24A/001135520 Jun 2024Not started lapses in 3 yearsLucan
Cappagh SDZ24A/0019W3182 Sept 2024Not started lapses in 3 years11th Lock
The Crossings Phase 3 SDZ25A/0050W21422 Jun 2026Not started lapses in 5 yearsLucan
Cookstown Industrial Estate LRD23A/000620416 Oct 2023Not started lapses in 2 yearsTallaght Central
Belgard Square East LRD25A/0009W19927 May 2026Not started lapses in 5 yearsTallaght
Whitestown Way Development LRD26A/0002W1691 Sept 2026Not started lapses in 5 yearsTallaght Central
Stocking Lane Development SHD3ABP-311616-2113116 Feb 2022Lapsing lapses in 3 monthsFirhouse-Bohernabreena
Ibis Hotel and Monastery Gate SHD3ABP-314701-2211528 Jul 2023Not started lapses in 2 yearsClondalkin
Tandy's Lane Village Phase 3 SDZ26A/0004W10731 Mar 2026Not started lapses in 4 yearsLucan
2 Firhouse Road and Former Morton's The Firhouse Inn LRD26A/0001W10010 Aug 2026Not started lapses in 5 yearsFirhouse
Fourth Avenue Cookstown Industrial Estate LRD26A/0004W9920 Oct 2026Not started lapses in 5 yearsTallaght
Citywest Avenue Development SD24A/0279W9025 Mar 2025Not started lapses in 3 yearsTallaght South
Fortunestown Lane and Parklands Parade LRD24A/0006W861 Nov 2024Not started lapses in 3 yearsSaggart
Kishoge Southwest Development Area SDZ25A/0044W8417 Sept 2026Not started lapses in 5 yearsLucan
C. 09 ha landholding SDZ26A/0013W6328 Jul 2026Not started lapses in 5 yearsLucan
Scholarstown House SD25A/0150W552 Jun 2026Not started lapses in 5 yearsScholarstown
Speaker Connolly Tavern SD24A/0228W5511 Aug 2025Not started lapses in 4 yearsFirhouse
A site of approximately 5.12 Ha, in the townlands of Gollierstown and Finnstown SDZ26A/0009W4711 Aug 2026Not started lapses in 5 yearsLucan
Main Street & New School Road Development SD24A/00714412 Mar 2026Not started lapses in 4 yearsPeamount Cross
The Silver Granite SD24A/0221W436 May 2025Not started lapses in 3 yearsPalmerstown-Fonthill
Main Street SD22A/02863026 Nov 2024Not started lapses in 3 yearsPeamount Cross
Rathmill Manor SD25A/0134W2824 Feb 2026Not started lapses in 4 yearsClondalkin
The Finches Public House SD22A/0346267 Aug 2024Not started lapses in 3 yearsPalmerstown-Fonthill
playing pitch at SD22A/03652211 Jan 2023Not started lapses within a yearFirhouse-Bohernabreena
Larkfield Square SD25A/0203W2024 Feb 2026Not started lapses in 4 yearsPalmerstown-Fonthill
McEvoys Public House SD25A/0146W1527 Jan 2026Not started lapses in 4 yearsPeamount Cross
Gordon Park SD23A/0016133 May 2023Not started lapses within a yearTallaght South
Citywest Village SD25A/0051W122 Sept 2025Not started lapses in 4 yearsFortunestown
Rookwood SD21A/02021124 Oct 2023Not started lapses in 2 yearsFirhouse-Bohernabreena
Newlands Road SD25A/0193W1028 Jul 2026Not started lapses in 5 yearsPalmerstown-Fonthill
Combined sites of 'The Priory' and 'Leabeg' SD21A/0290106 Dec 2023Not started lapses in 2 yearsMarlfield

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'SDCC' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.