Permitted, not started · South Dublin · grants of 10+ homes since 2017

South Dublin: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

25,758 homes in 185 sites of 10 or more have been granted permission in South Dublin since 2017. A commencement notice was lodged for 59% of them. 8,561 still have a live permission and no start; 552 of those lapse within a year, and 1,851 have already lapsed.

25,758
homes permitted · 185 sites
59%
started · 15,201 homes
8,561
not started · live permission
552
lapse within 12 months
1,851
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 7

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Lucan336,26352%2,491485
Clondalkin609,05668%2,038766
Firhouse-Bohernabreena272,86943%1,289131345
Rathfarnham-Templeogue131,95148%1,024
Tallaght Central202,50664%84131
Tallaght South202,12270%54642197
Palmerstown-Fonthill1299154%332127

By year granted

Granted inSitesHomesStartedNot startedLapsed
20171982880%0166
2018312,06378%11436
2019161,87768%0605
2020193,10385%224231
2021984246%170286
2022142,36077%552
2023264,67889%375127
2024131,89057%815
2025132,89346%1,532
2026255,2244%4,882

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 95% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cairn Homes Properties Limited184,88067%1,332172
South Dublin County Council11,2520%1,252
Kelland Homes Limited51,22731%844
Steeplefield Limited15880%588
Lagan Homes Ballycullen Limited15020%502
Hugh McGreevy & Sons Limited14530%453
Watfore Limited14360%436
Shannon Homes Dublin Unlimited Company14020%402
Evara Developments Limited543816%368
Quintain Developments Ireland Limited61,46776%355
Cape Wrath Hotel Unlimited Company12240%224
Stranwil Limited12040%204
Midsal Homes Limited11990%199
Square Foot Property Services Limited11700%170
ARP 4.2 Sustainable Communities (Ireland) Fund11690%169
MacCabe Durney Barnes Limited11310%131
Propiteer Ibis Red Cow Limited11150%115
Bluemont Developments (Firhouse) Limited11000%100
Kingscroft Developments Limited1900%90
Greenacre Residential DAC26100%86524
Anthony Neville Homes Limited1730%73
Clear Real Estate Holdings Limited1630%63
Emmaville Limited1550%55
Seabren Developments Limited1550%55
Hollyville Investments Limited1430%43
Deane and Deane Limited1300%30
Cavan Developments Limited1280%28
Old Nangor Road Limited1260%26
Ballymount Homes Limited1220%22
Fitzgibbon Brothers Limited1200%20

Permission, no start 44 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Lands comprising 3 sites Sites 3 SDZ25X/00011,25231 Mar 2026Not started lapses in 5 yearsLucan
Boherboy LRD25A/0012W61125 Jun 2026Not started lapses in 5 yearsBoherboy
former Chadwicks Builders Merchant site LRD25A/0005W58813 May 2026Not started lapses in 5 yearsGreenhills
Woodtown LRD25A/0003W5026 Mar 2026Not started lapses in 4 yearsWoodtown
Development Area 6 Kishoge Urban Centre SDZ25A/0012W49425 Aug 2025Not started lapses in 4 yearsClondalkin
Tubber Lane SDZ26A/0008W4535 May 2026Not started lapses in 5 yearsLucan
Units 16-21A-B LRD25A/0002W4364 Dec 2025Not started lapses in 4 yearsRathfarnham-Templeogue
Cooldown Commons and Fortunestown SD22A/013342110 Aug 2022Lapsing lapses in 11 monthsTallaght South
Taylors Land & Edmondstown Road LRD23A/000240222 Sept 2025Not started lapses in 4 yearsBallyboden
Finnstown SDZ24A/001135520 Jun 2024Not started lapses in 3 yearsLucan
Cappagh SDZ24A/0019W3182 Sept 2024Not started lapses in 3 years11th Lock
Ninth Lock Road and east of the R113 SDZ25A/0019W23323 Mar 2026Not started lapses in 4 yearsNeilstown
Garters Lane SHD3ABP-308088-2022421 Dec 2020Not started lapses in 4 yearsSaggart
Gollierstown SDZ25A/0050W21422 Jun 2026Not started lapses in 5 yearsLucan
Unit 5A-C LRD23A/000620416 Oct 2023Not started lapses in 2 yearsTallaght Central
Belgard Square East LRD25A/0009W19927 May 2026Not started lapses in 5 yearsTallaght
Glen Abbey Complex SHD3ABP-309916-2117021 Sept 2021Not started lapses in 4 yearsTallaght
approximately 1.32 Ha principally located at LRD26A/0002W1691 Sept 2026Not started lapses in 5 yearsTallaght Central
Stocking Lane SHD3ABP-311616-2113116 Feb 2022Lapsing lapses in 5 monthsFirhouse-Bohernabreena
IBIS Hotel and Monastery Gate SHD3ABP-314701-2211528 Jul 2023Not started lapses in 2 yearsClondalkin
Adamstown SDZ26A/0004W10731 Mar 2026Not started lapses in 5 yearsLucan
No. 2 Firhouse Road and the former Morton’s The Firhouse Inn LRD26A/0001W10010 Aug 2026Not started lapses in 5 yearsFirhouse
Units 66 and 67 LRD26A/0004W9910 Sept 2026Not started lapses in 5 yearsTallaght
Citywest Road SD24A/0279W9025 Mar 2025Not started lapses in 3 yearsTallaght South
Fortunestown Lane LRD24A/0006W861 Nov 2024Not started lapses in 3 yearsSaggart
Drury Mills & Drury Park SD24A/0092W7310 Feb 2026Not started lapses in 4 yearsMillbridge Cross
C. 09 ha landholding SDZ26A/0013W6328 Jul 2026Not started lapses in 5 yearsLucan
Scholarstown House SD25A/0150W552 Jun 2026Not started lapses in 5 yearsScholarstown
Firhouse Road SD24A/0228W5511 Aug 2025Not started lapses in 4 yearsFirhouse
A site of approximately 5.12 Ha, in the townlands of Gollierstown and Finnstown SDZ26A/0009W4711 Aug 2026Not started lapses in 5 yearsLucan
Main Street & New School Road SD24A/00714412 Mar 2026Not started lapses in 4 yearsPeamount Cross
junction of Kennelsfort Road Upper SD24A/0221W436 May 2025Not started lapses in 4 yearsPalmerstown-Fonthill
Main Street SD22A/02863026 Nov 2024Not started lapses in 3 yearsPeamount Cross
Rathmill Manor SD25A/0134W2824 Feb 2026Not started lapses in 4 yearsClondalkin
Finches Shopping Centre SD22A/0346267 Aug 2024Not started lapses in 3 yearsPalmerstown-Fonthill
playing pitch at SD22A/03652211 Jan 2023Not started lapses within a yearFirhouse-Bohernabreena
Larkfield Square SD25A/0203W2024 Feb 2026Not started lapses in 4 yearsPalmerstown-Fonthill
McEvoys Public House SD25A/0146W1527 Jan 2026Not started lapses in 4 yearsPeamount Cross
Gordon Park SD23A/0016133 May 2023Not started lapses in 2 yearsTallaght South
Citywest Village SD25A/0051W122 Sept 2025Not started lapses in 4 yearsFortunestown
Rookwood SD21A/02021124 Oct 2023Not started lapses in 2 yearsFirhouse-Bohernabreena
Vista Montana SD17A/0364114 May 2018Not started lapses in 5 yearsKnocklyon
Newlands Road SD25A/0193W1028 Jul 2026Not started lapses in 5 yearsPalmerstown-Fonthill
Combined sites of 'The Priory' and 'Leabeg' SD21A/0290106 Dec 2023Not started lapses in 2 yearsMarlfield

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'SDCC' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness