South Dublin County Council · SD208/0007 · LA / State Authority Development
Belgard Square North
Built: all 133 homes are finished (Q1 2026).
Tallaght, South Dublin County Council
Building progress councils’ figures, Q1 2026
completed · under construction · not started
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 133 | 133 | 0 | |
| Q3 2025 | 133 | 133 | 0 | |
| Q4 2025 | 133 | 133 | 0 | |
| Q1 2026 | 133 | 0 | 133 |
Source and licence
- Status
- Built
- Decision
- Approved · 12 Oct 2020
- Site
- 4,963 m²
The site 4,963 m²
Boundary of Belgard Square North as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 3 applications in the last 10 years
Planning timeline 5 steps
- 10 Aug 2020Application lodged — LA / State Authority Development
- 12 Oct 2020Council decision — Grant
- 12 Oct 2020Final approval
- Q2 2023Building started
- Q1 2026Site completed — Site completed
Other big developments nearby within 2 km
- Cookstown Industrial Estate Development · approved 2025, no start notice · 197 homes · 23 m away
- Airton Road Extension · approved 2022, no start notice · 83 m away
- Unit 21, Cookstown Industrial Estate · refused 2023 · 131 homes · 5 storeys · 178 m away
- South Dublin County Council County Hall and Library · lodged 2026, not decided · 190 m away
- Unit 73 Cookstown Industrial Estate · refused 2021 · 64 homes · 6 storeys · 215 m away
- Old Blessington Road · approved 2023, no start notice · 293 m away
- Civic Theatre · lodged 2026, not decided · 299 m away
- The Former ABB Site · refused 2025 · 334 homes · 13 storeys · 316 m away