PlanningRegister.ie
South Dublin County Council · SDZ22A/0018 · SDZ Application

Clonburris Development Areas CUCS3 & CSWS3

594 apartments7 storeysCairn Homes Properties Ltd.Dublin 22, South Dublin County Council

All 607 permitted homes are built (Q2 2026).

Also known as Clonburris SDZ.

  1. 15 Dec 2022Received
  2. 31 Oct 2023Approved
  3. 19 Dec 2023Building started
  4. 28 Oct 2025Signed off
Status
Building started
Decision
Approved · 31 Oct 2023
Size
594 apartments · up to 7 storeys
Uses
residential, apartments, office, retail, creche
Applicant
Cairn Homes Properties Ltd.
Site
5.20 ha

Building progress councils’ figures, Q2 2026

  1. 2023Approved
  2. 2023Building started
  3. 2025First homes signed off5 sign-offs

All 607 permitted homes are built (Q2 2026).

607
homes permitted
607
homes started on site
607
homes completed

completed · under construction · not started · 0 houses and 607 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 20256076070
Q3 20256076070
Q4 20256076070
Q1 2026607378229
Q2 20266070607

The scheme

Cairn Homes Properties Ltd. proposes a mixed-use development in the townland of Cappagh, Clonburris. The scheme includes 594 apartments across several blocks, along with office space, retail units, a creche, and an urban square. The project also provides for associated infrastructure, car parking, and public open space.

it is a large-scale development within the Clonburris Strategic Development Zone Planning Scheme 2019

What the register says

Construction of a mixed-use development comprising 594 apartments, office floorspace, 4 retail units, a creche and urban square in the Clonburris Development Areas CUCS3 & CSWS3 of the Clonburris SDZ Planning Scheme 2019 as follows, 594 apartments (255 one bedroom apartments, 307 two bedroom apartments and 32 three bedroom apartments (all apartments to have terrace or balcony; ancillary communal amenity spaces for residents) as follows; Block A (4 and 6 storeys with undercroft) comprises 96 apartments consisting of 36 one bedroom apartments, 48 two bedroom apartments and 12 three bedroom apartments (with creche c. 609sq. m at ground and first floor as well as play area; Block B (6 storeys with undercroft) comprises 77 apartments consisting of 44 one bedroom apartments, 28 two room apartments and 5 three bedroom apartments; Block D (5 and 7 storeys with undercroft) comprises 71 apartments consisting of 39 one bedroom apartments and 32 two bedroom apartments; Block E (6 storeys with undercroft) comprises 100 apartments consisting of 47 one bedroom apartments, 48 two bedroom apartments and 5 three bedroom apartments; Block F (5 and 7 storeys with undercroft) comprises 124 apartments consisting of 57 one bedroom apartments, 61 two bedroom apartments and 6 three bedroom apartments; Block G (1, 2 and 4 storeys with undercroft) comprises 65 apartments consisting of 16 one bedroom apartments, 45 two bedroom apartments and 4 three bedroom apartments; Block H (4 storeys with undercroft) comprises 61 apartments consisting of 16 one bedroom apartments and 45 two bedroom apartments; Mixed use development comprising, commercial office development in Block C of 6 storeys with parapet above to 7 storey equivalent on elevations (c. 4,516sq.m), 1 retail unit at ground floor of Block B (c.147.5sq. m) and 3 retail units at ground floor of Block E as follows (c.106.2sq.m, c.141.6sq.m and c.492.2sq.m respectively) as well as a creche (c. 609sq. m) at ground floor and first floor of Block A; Vehicular access will be from the permitted Clonburris Southern Link Street (SDZ20A/0021) and R 113 to the east; Public Open Space/landscaping of c. 0.52 hectares (urban square) and linear open space (0.72 hectares) as well as a series of communal open spaces to serve apartments over undercroft level (and internal communal open space c. 685 sq.m; The development will also provide for all associated works and infrastructure to facilitate the development to include all ancillary site development works including footpaths, landscaping boundary treatments, public, private open space areas, car parking (396 no. spaces in a mixture of undercroft spaces Block A, Block B&D and Block E&F) and bicycle parking (1,232 spaces at undercroft and surface levels), single storey ESB substations/bike/bin stores, green roofs, solar panels at roof level of apartments, plant areas within blocks and all ancillary site development/construction works; Permission is also sought for connection to water supply, and provision of foul drainage infrastructure. This application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area ' as defined by Statutory Instrument No. 604 of 2015; An Environmental Impact Assessment Report accompanies this planning application

Summary from the register record.

Planning timeline 6 steps

  • 15 Dec 2022
    Application lodged — DZ
  • 31 Oct 2023
    Council decision — Grant
  • 31 Oct 2023
    Final approval
  • 19 Dec 2023
    Building started
  • Q2 2026
    Site completed — Site completed
  • 14 Dec 2028
    Approval runs out (estimate)

The site 5.20 ha

Boundary of Clonburris Development Areas CUCS3 & CSWS3 as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 6 applications in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála

Building work started inside the site 6 commencement notices

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.