Approved Feb 2025; first homes signed off Sep 2025.
- 6 Dec 2024Received
- 10 Feb 2025Approved
- 21 Jul 2025Building started
- 18 Sept 2025Signed off
- Status
- Building started
- Decision
- Approved · 10 Feb 2025
- Applicant
- Clonburris Infrastructure Limited
- Site
- 31.79 ha
Is it built?
- 2025Approved
- 2025Building started
- 2025First homes signed off1 sign-off
The scheme
What the register says
The development will consist of works located inside the Clonburris SDZ relating to the Stage 2 roads, public parks/open space areas and services infrastructure works (as part of a separate concurrent application) as per the Clonburris SDZ Planning Scheme (2019) to facilitate the future development of the northern part of the overall SDZ comprising: A) The construction of c. 2.3km of a new Link Street Clonburris Northern Link Street (CNLS) and approximately 800m of side streets including ancillary cycle facilities, pedestrian crossings, traffic signals, footpaths, car parking (79 no. spaces) public lighting as well as services infrastructure (including ESB, Comms, gas main, trunk surface water sewer, and watermain) and ancillary works. B) Provision/upgrade of 12 signalised junctions (5 new and 7 upgraded) as follows: Junction 1: R136 & Adamstown Avenue/Thomas Omer Way, Junction 3: R113 & Thomas Omer Way / Ninth Lock Road, Junction 4: CNLS & R136, Junction 6: CNLS, Junction 8: CNLS & R113, Junction 9: CNLS/Neilstown Road & Ninth Lock, Junction 24: CNLS/Neilstown Road & Ninth Lock, Junction 28: R136 & Adamstown Avenue/Thomas Omer Way, Junction 2: CNLS & Thomas Omer Way, Junction 5: CNLS, Junction 7: CNLS, Junction 27: R136 & Adamstown Avenue/Thomas Omer Way along with minor priority-controlled junctions are proposed along the street alignment to provide access to existing development and future development cells within the Clonburris SDZ. C) Approximately 2 km of upgrade of existing streets, including minor priority-controlled junctions are proposed along the street alignment to provide access to existing development and future development cells within the Clonburris SDZ, including pedestrian crossings. D) Provision of 2 main public parks centrally (Na Cluainte Park North) c. 2.78 ha and in the eastern part of the subject lands (c. 0.77 ha) both to include open water attenuation areas. E) Drainage infrastructure works to include surface water attenuation areas, Sustainable Urban Drainage Systems (SUDs) as well as landscaped areas including attenuation ponds and the provision of underground attenuation. Provision of surface water drainage and waste supply trunk infrastructure within the proposed road corridors; wastewater infrastructure including a foul pumping station (known as pumping station no.3) and foul pipe network within proposed road corridors to facilitate drainage connections to future development within the SDZ lands. The easterly section of the development will collect surface water and discharge into an existing outfall situated within Moorfield Walk whereas the western surface water catchment will connect (as part of a separate concurrent application) to an existing surface water outfall on the Griffeen Road (and ultimately to an existing Griffeen River outfall). F) Provision of trunk watermain infrastructure within the CNLS as well as connections to the permitted watermain infrastructure as part of SDZ20A/0021. G) Permission is also sought for all ancillary site development and landscape works associated with the development, including hard and soft landscaping, (tree pits, boundary treatments, road marking, signage, enabling works and temporary construction works, (including site accommodation, site compounds, and temporary construction boundary fencing) as well as temporary project signage (at 6 no. locations) and provision of underground utility connections under the Dublin - Cork Railway line (at 3 no. locations) and Irish water diversions. This application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area, as defined by Statutory Instrument No. 604 of 2015
Summary from the register record.
The site 31.79 ha
Boundary of Kishoge from the planning application.
Planning applications inside the site 20 applications in the last 10 years
- OpenAt this site of c. 0.75 hectares, to the west of Lockhouse Drive within the townland of Cappagh and Clonburris Great and Gallanstown, ‘Clonburris’, Dublin 22,, all on wider lands bounded generally by lands known as ‘Seven Mills/Parkleigh’ to the ea
- GrantedLands comprising 3 sites Sites 3, 4 and 5, within Kishoge Development Area of Clonburris SDZ in the townlands of, Kishoge, Esker South Grange & Balgaddy, Clonburris, Co. Dublin.
- CommencedWest of the Ninth Lock Road and east of the R113, Fonthill Road, Clonburris, Dublin 22
- CommencedWithin the townlands of Kishoge, Balgaddy, Neillstown and Cappagh, Clondalkin & Lucan, Dublin 22
- Granted4 No. sites A) Along Griffeen Road Griffeen Glen Drive, Balgaddy Road and, B) Grange Castle Road Junction Lucan Co. Dublin, C) Thomas Omer Way/Ninth Lock Road, & D) Ninth Lock Road/Neilstown Road, Clondalkin, Dublin 22.
- GrantedThomas Omer Way,, (east of Kishoge Community College), Balgaddy, Lucan, CO DUBLIN
- CommencedDevelopment Area 9 Kishoge South East, Sub Sectors KSE-S1 and KSE-S2, Clonburris SDZ, within the townland of Kishoge, Clonburris, Dublin 22.
- GrantedWithin the townlands of Neilstown, Clonburris, Dublin 22, all on wider lands bounded by, D22 E2KA
Show 12 more
- GrantedLynch’s Lane tothe east of the R136 Outer Ring Road and south of Thomas Omer Way, Kishoge, Lucan,Dublin
- GrantedWithin the townland of Cappagh, Clonburris, Dublin 22
- GrantedAt Bus stop no. 4607, Griffeen Avenue (westbound), Griffeen, Dublin 22
- RefusedLucan East Educate Together N. S, Kishogue Cross, Lucan, Co Dublin
- WithdrawnAt Bus stop no. 4607, Griffeen Avenue (westbound), Griffeen, Dublin 22
- GrantedIn the townland of Neillstown, Clonburris, Dublin 22
- CommencedWithin the townland of Cappagh, Clonburris, Dublin 22
- Appeal decidedLucan East Educate Together N.S, Kishogue Cross, Lucan, Co Dublin
- CommencedThomas Omer Way, Balgaddy, Lucan, Dublin
- CommencedKishogue South West, Lynches Lane, East of R136 Outer Ring Road, DUBLIN
- GrantedLynch's Park, Lucan, Co. Dublin
- CommencedKishogue Cross, Griffeen Avenue, Lucan, Co. Dublin
Appeals inside the site 3 with An Coimisiún Pleanála
Building work started inside the site 5 commencement notices
- CommencedWest of the Ninth Lock Road and east of the R113, Fonthill Road, Clonburris, Dublin 22
- CommencedWithin the townlands of Kishoge, Balgaddy, Neillstown and Cappagh, Clondalkin & Lucan, Dublin 22
- CommencedKishogue Cross, Griffeen Avenue, Lucan, Co. Dublin
- CommencedKishogue Cross, Griffeen Avenue, Lucan, Co. Dublin
- CommencedKishogue Cross, Griffeen Avenue, Lucan, Co. Dublin
Other big developments nearby within 2 km
- Thomas Omer Way · 0 m away
- Cappagh and Clonburris · 278 m away
- Clonburris Development Areas CSW-S1 & CSW-S2 · 565 homes · 4 storeys · 278 m away
- Cappagh · 2 homes · 292 m away
- Clonburris South West · 569 homes · 6 storeys · 292 m away
- Clonburris Great · 377 m away
- Neilstown · 495 m away
- Neillstown · 643 m away