Fingal County Council · F16A/0152/E1A · Standard
Fingal Development
48 homesFingal County Council
Building progress councils’ figures, Q1 2025
All 48 permitted homes are built (Q1 2025).
48
homes permitted
48
homes started on site
48
homes completed
completed · under construction · not started · 48 houses and 0 apartments permitted
- Status
- Completed · activity on site: completed
- Decision
- Approved
- Size
- 48 homes
- Site
- 7.37 ha
The scheme
This application proposes a residential development consisting of 48 units. The project is located within the Fingal area.
because it involves the construction of 48 residential units
Summary from the councils' pipeline record.
The site 7.37 ha
Boundary of Fingal Development as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 6 applications in the last 10 years
- Appeal decidedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- GrantedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- GrantedLands in the Townlands of Ballymacartle and Greenwood, in the parish o
Appeals inside the site 3 with An Coimisiún Pleanála
- RefusedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsaley, North of Ashgrove & Baskin Cottages & Baskin Lane (L2955), Cloghran, Swords, Co. Dublin
- Granted with conditionsLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsaley, North of Ashgrove & Baskin Cottages & Baskin Lane (L2055), Cloghran, Swords, Co. Dublin
- Granted with conditionsBaskin Cottages, Baskin Lane, Cloghran, Co. Dublin.
Building work started inside the site 4 commencement notices
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
- CommencedLands in the townlands of Ballymacartle and Greenwood, Parish of Kinsa
Planning timeline 4 steps
- 20 Jul 2021Application lodged — Standard
- 13 Sept 2021Final approval
- Q1 2025Site completed — Site completed
- 13 Sept 2026Approval runs out (estimate)
Other big developments nearby within 2 km
- Teagasc Research Centre · 856 m away
- Auburn House · 1.2 km away
- Auburn House · 1.2 km away
- Belcamp Hall (Protected Struc · 1.5 km away
- Belcamp Hall · 1.5 km away
- Back Road · 1.5 km away
- Back Road and Kinsealy Lane · 1.5 km away
- Including part of the grounds of Lamorlaye · 1.5 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.