Lands at Mabestown
Building: 40 under construction of 52 homes (Q2 2026).
Beakonshaw Mabes LimitedMalahide, Fingal County Council
Email me when the next phase is lodged
Also known as Malahide Road.
- Status
- Building started
- Council decision
- Refuse permission · 10 Oct 2023
- Uses
- residential
- Applicant
- Beakonshaw Mabes Limited
- Site
- 1.55 ha
- Appeal
- ACP 318393 · Approved with conditions · 27 Jan 2025
Building progress councils’ figures, Q2 2026
- 2025Approved on appeal
- 2025Building started
- Not yetFirst homes signed off
completed · under construction · not started
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 52 | 0 | 0 | |
| Q4 2025 | 52 | 5 | 0 | |
| Q1 2026 | 52 | 19 | 0 | |
| Q2 2026 | 52 | 40 | 0 |
Source and licence
The scheme
Beakonshaw Mabes Limited proposes a residential development on lands at Mabestown, Malahide Road. The project involves the construction of 52 units on a 1.55 hectare site located east of the R107. Permission was granted following an appeal to An Bord Pleanála.
What the register says
The site is located east of the R107
Summary from the register record.
Planning timeline 7 steps
- 18 Aug 2023Application lodged — Standard
- 10 Oct 2023Council decision — Refuse
- 6 Nov 2023Appealed to An Coimisiún Pleanála — ABP-318393-23
- 27 Jan 2025Commission decision — Granted
- 9 May 2025Final approval
- Q4 2025Building started
- 23 Mar 2030Approval runs out (estimate)
The site 1.55 ha
Boundary of Lands at Mabestown as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 2 applications in the last 10 years
Appeals inside the site 3 with An Coimisiún Pleanála
Other big developments nearby within 2 km
- Including part of the grounds of Lamorlaye · 134 m away
- Auburn House · withdrawn or invalid · 203 m away
- Back Road · approved 2025, no start notice · 744 m away
- Back Road and Kinsealy Lane · 744 m away
- Kinsealy Lane · building started 2026 · 846 m away
- Teagasc Research Centre · building started 2026 · 1.5 km away
- Seamount Road and Seamount Abbey · approved 2023, no start notice · 1.9 km away
Start notices are matched from the national building control register; a start on site can be missed.
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.