Mooretown

Building: 68 finished, 164 under construction of 274 homes (Q2 2026).

Swords, Fingal County Council

Building progress councils’ figures, Q2 2026

274
homes permitted
232
homes started on site
68
homes completed

completed · under construction · not started · 187 houses and 87 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 2025274730
Q3 2025274730
Q4 20252741590
Q1 20262741590
Q2 202627416468
Source and licence
Status
Building started
Decision
Approved · 13 May 2024
Site
9.47 ha

The scheme

This development is located at Mooretown, Swords, Co Dublin. It involves the construction of 274 residential units.

Summary from the councils' pipeline record.

The site 9.47 ha

Boundary of Mooretown as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 1 application in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála
Commencement notices inside the site 9
  • CommencedRathbeale Road, Swords, Fingalnotice 24 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 18 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council
  • CommencedRathbeale Road, Swords, Fingalnotice 17 Dec 2024 · Fingal County Council

Planning timeline 5 steps

  • 13 May 2024
    Application lodged — LA / State Authority Development
  • 13 May 2024
    Council decision — Grant
  • 31 May 2024
    Final approval
  • Q4 2024
    Building started
  • 7 Dec 2024
    Approval runs out (estimate)

Other big developments nearby within 2 km

Living near Mooretown?

Its progress and every other plan around it.

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.