Fingal County Council · LADP/002/24 · LA / State Authority Development
Mooretown
Building: 68 finished, 164 under construction of 274 homes (Q2 2026).
Swords, Fingal County Council
Building progress councils’ figures, Q2 2026
274
homes permitted
232
homes started on site
68
homes completed
completed · under construction · not started · 187 houses and 87 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 274 | 73 | 0 | |
| Q3 2025 | 274 | 73 | 0 | |
| Q4 2025 | 274 | 159 | 0 | |
| Q1 2026 | 274 | 159 | 0 | |
| Q2 2026 | 274 | 164 | 68 |
Source and licence
- Status
- Building started
- Decision
- Approved · 13 May 2024
- Site
- 9.47 ha
The scheme
This development is located at Mooretown, Swords, Co Dublin. It involves the construction of 274 residential units.
Summary from the councils' pipeline record.
The site 9.47 ha
Boundary of Mooretown as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 1 application in the last 10 years
Appeals inside the site 1 with An Coimisiún Pleanála
Commencement notices inside the site 9
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
- CommencedRathbeale Road, Swords, Fingal
Planning timeline 5 steps
- 13 May 2024Application lodged — LA / State Authority Development
- 13 May 2024Council decision — Grant
- 31 May 2024Final approval
- Q4 2024Building started
- 7 Dec 2024Approval runs out (estimate)
Other big developments nearby within 2 km
- Mai · first homes signed off 2023 · 322 m away
- 2 No. sites totalling approximately 6.34 Ha in the townland · building started 2026 · 344 m away
- Mill · 625 m away
- Estuary West Lands at Holybanks · withdrawn or invalid · 1.1 km away
- Holybanks · lodged 2022, not decided · 1.1 km away
- Main Street · building started 2024 · 1.8 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.