South Dublin County Council · SD17A/0468 · Standard
Oldcourt Road
Built: all 71 homes are finished (Q1 2026).
Firhouse, South Dublin County Council
Building progress councils’ figures, Q1 2026
71
homes permitted
71
homes started on site
71
homes completed
completed · under construction · not started · 55 houses and 16 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 71 | 16 | 55 | |
| Q3 2025 | 71 | 16 | 55 | |
| Q4 2025 | 71 | 16 | 55 | |
| Q1 2026 | 71 | 0 | 71 |
Source and licence
- Status
- Built
- Decision
- Approved · 13 Sept 2018
- Site
- 3.79 ha
The site 3.79 ha
Boundary of Oldcourt Road as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 6 applications in the last 10 years
- Granted18 The Close, Ballycullen Gate, Dublin 24, D24TW0D
- Granted10, The View, Ballycullen Gate, Firhouse, Dublin 24
- Granted5, The Rise, Ballycullen Gate, Dublin 24
- CommencedSouth/South-West of Oldcourt Road, Oldcourt, Dublin 24
- CommencedOldcourt Road, Firhouse, Dublin 24.
- RefusedSite South of Oldcourt Road, Firhouse, Dublin 24
Commencement notices inside the site 7
- CommencedThe Rise, Oldcourt, South Dublin
- CommencedBallycullen Gate, Oldcourt, South Dublin
- CommencedBallycullen Gate, Oldcourt, South Dublin
- CommencedBallycullen Gate, Oldcourt, South Dublin
- CommencedThe Court, Ballycullen Gate, Oldcourt, South Dublin
- CommencedThe Court, Ballycullen Gate, Oldcourt, South Dublin
- CommencedThe Court, Ballycullen Gate, Oldcourt, South Dublin
Planning timeline 6 steps
- 22 Dec 2017Application lodged — Standard
- 13 Sept 2018Council decision — Grant
- Q2 2022Building started
- 6 Mar 2023Final approval
- Q1 2026Site completed — Site completed
- 19 Apr 2028Approval runs out (estimate)
Other big developments nearby within 2 km
- Oldcourt Residential Development · first homes signed off 2026 · 71 homes · 3 storeys · 30 m away
- Bohernabreena, Oldcourt and Killininny Development · building started 2026 · 523 homes · 4 storeys · 128 m away
- D24 Neighbourhood · lodged 2022, not decided · 911 m away
- Woodtown · approval ran out 2026 · 329 homes · 5 storeys · 1.0 km away
- Woodtown Development · approved 2026, no start notice · 502 homes · 4 storeys · 1.0 km away
- Knocklyon Park · refused 2023 · 1.5 km away
- SDCC Lands @28 Locations · lodged 2026, not decided · 1.5 km away
- Speaker Connolly Tavern · building started 2026 · 55 homes · 6 storeys · 1.6 km away