Fingal County Council · PARTXI/006/22 · LA / State Authority Development
Seatown Road Development
Building: all 36 homes are under construction (Q2 2026).
Swords, Fingal County Council
Building progress councils’ figures, Q2 2026
completed · under construction · not started
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 36 | 36 | 0 | |
| Q3 2025 | 36 | 36 | 0 | |
| Q4 2025 | 36 | 36 | 0 | |
| Q1 2026 | 36 | 36 | 0 | |
| Q2 2026 | 36 | 36 | 0 |
Source and licence
- Status
- Building started
- Decision
- Approved · 13 Mar 2023
- Site
- 4,846 m²
The scheme
Fingal County Council proposes a residential development at Seatown Road in Swords. The project consists of 36 housing units on a 0.48 hectare site.
Summary from the councils' pipeline record.
The site 4,846 m²
Boundary of Seatown Road Development as the Dublin councils map it in the housing pipeline.
Commencement notices inside the site 1
- Commenced2 Seatown Road, Swords, Fingal
Planning timeline 5 steps
- 13 Mar 2022Application lodged — LA / State Authority Development
- 13 Mar 2023Council decision — Grant
- 13 Mar 2023Final approval
- Q3 2024Building started
- 26 Apr 2028Approval runs out (estimate)
Other big developments nearby within 2 km
- Swords Business Park · 399 m away
- Main Street · building started 2024 · 469 m away
- Estuary West Lands at Holybanks · withdrawn or invalid · 581 m away
- Holybanks · lodged 2022, not decided · 586 m away
- Barrysparks and Crowscastle (lands generally bound by the R1 · approved 2026, no start notice · 693 m away
- Mountgorry · approved 2024 · 1.0 km away
- Fosterstown North · 1.1 km away
- Site 10 · lodged 2026, not decided · 182 homes · 1.1 km away