Building started Dec 2023; approved Apr 2023.
Lucan, South Dublin County Council
Email me when the next phase is lodged
- Status
- Building started
- Decision
- Approved · 24 Apr 2023
- Site
- 201 m²
Is it built?
- 2023Approved
- 2023Building started
- Not yetFirst homes signed off
The scheme
What the register says
Construction of a ground floor extension consisting of a playroom and bedroom to rear of existing house
Summary from the register record.
Planning timeline
- 28 Feb 2023Received
- 24 Apr 2023Approved
- 13 Dec 2023Building started
The site 201 m²
Boundary of St. Helen's Gardens from the planning application.
Planning applications inside the site 5 applications in the last 10 years
Appeals inside the site 1 with An Coimisiún Pleanála
Commencement notices inside the site 1
Other big developments nearby within 2 km
- Adamstown · approved 2023 · 343 homes · 5 storeys · 0 m away
- St. Helens Plaza Apartment Block · first homes signed off 2026 · 80 homes · 5 storeys · 0 m away
- Finnstown & Gollierstown · approved 2024, no start notice · 62 m away
- Aderrig · first homes signed off 2023 · 81 m away
- Aderrig Phase 4 · approved 2024, no start notice · 5 homes · 101 m away
- Finnstown, Adamstown · building started 2024 · 350 homes · 7 storeys · 101 m away
- Adamstown Boulevard Development Area · approved 2025, no start notice · 886 homes · 9 storeys · 120 m away
- Stratton Square · approved 2022, no start notice · 139 m away
Start notices are matched from the national building control register; a start on site can be missed.