PlanningRegister.ie
South Dublin County Council · SDZ23A/0007 · SDZ Application

St. Helen's Gardens

Building started Dec 2023; approved Apr 2023.

Lucan, South Dublin County Council

Email me when the next phase is lodged

Status
Building started
Decision
Approved · 24 Apr 2023
Site
201 m²

Is it built?

  1. 2023Approved
  2. 2023Building started
  3. Not yetFirst homes signed off

The scheme

What the register says

Construction of a ground floor extension consisting of a playroom and bedroom to rear of existing house

Summary from the register record.

Planning timeline
  1. 28 Feb 2023Received
  2. 24 Apr 2023Approved
  3. 13 Dec 2023Building started

The site 201 m²

Boundary of St. Helen's Gardens from the planning application.

Planning applications inside the site 5 applications in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála
Commencement notices inside the site 1

Other big developments nearby within 2 km

Start notices are matched from the national building control register; a start on site can be missed.

Everything within 1 km on the map →