Carlow planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

846 homes in 24 sites of 10 or more have been granted permission in Carlow since 2021. A commencement notice was lodged for 71% of them. 133 still have a live permission and no start; 10 of those lapse within a year, and 48 have already lapsed.

846
homes permitted · 24 sites
71%
started · 603 homes
133
not started · live permission
10
lapse within 12 months
48
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 3

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Carlow1557679%12310—
Tullow717767%10—48
Muinebeag29333%0——

By year granted

Granted inSitesHomesStartedNot startedLapsed
2022510290%10—
2023297100%0—
2024516748%3948
2025621566%74—
2026626573%10—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 9 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 25% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
T Nolan Developments Limited1100%10—
Stormbell Limited1480%048
Woodlawn Developments132100%0—
Cieval Limited131100%0—
Woodlawn Developments Limited128100%0—
Johnstown Home Developments Limited121100%0—
MB Homes Limited118100%0—
JC Brenco Development Limited116100%0—
Woodlawns Development Limited110100%0—

Work started 17 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Browneshill Road Lower & Link Road 25600638312 Jan 2026Started notice 14 Apr 2026Carlow
Cois Dara 23798119 Sept 2023Started notice 17 Oct 2023Carlow
Cois Dara 215245428 Jun 2022Started notice 21 Jul 2022Carlow
Hacketstown Road 24601315319 Feb 2025Started notice 13 Mar 2025Carlow
Kernanstown Link Road 25601754626 Jun 2026Started notice 20 Jul 2026Carlow
Mortarstown 24603984622 Dec 2025Started notice 9 Mar 2026Carlow
Abbey St 25602283325 Mar 2026Started notice 21 Sept 2026Tullow
Montgomery Street Andy Murphy Road 23601013212 Feb 2024Started notice 18 Apr 2024Carlow
Gort Na Gréine 26600313126 Aug 2026Started notice 14 Oct 2026Muinebeag
Ard Bhile 24604202825 Jul 2025Started notice 5 Feb 2026Tullow
Carrigduff 2368275 Mar 2024Started notice 30 Oct 2024Tullow
Shillelagh Road 23601642129 May 2024Started notice 25 Jun 2024Tullow
Graiguecullen 212721818 Jul 2022Started notice 24 Jan 2024Carlow
Friars Green 222441628 Jul 2023Started notice 27 Mar 2024Carlow
Limegrove 24601771419 Jun 2025Started notice 1 Jul 2026Carlow
Co. Carlow 213511025 Aug 2022Started notice 12 Oct 2022Carlow
Ard Bhile 212461012 Jul 2022Started notice 9 Sept 2022Tullow

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CARLOW' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness