Carlow planning permission: the homes nobody has started
Data updated 30 Oct 2026 · register lag up to 7 days · sources & freshness
846 homes in 24 sites of 10 or more have been granted permission in Carlow since 2021. A commencement notice was lodged for 71% of them. 133 still have a live permission and no start; 10 of those lapse within a year, and 48 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 3
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2022 | 5 | 102 | 90% | 10 | — |
| 2023 | 2 | 97 | 100% | 0 | — |
| 2024 | 5 | 167 | 48% | 39 | 48 |
| 2025 | 6 | 215 | 66% | 74 | — |
| 2026 | 6 | 265 | 73% | 10 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 9 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 25% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| T Nolan Developments Limited | 1 | 10 | 0% | 10 | — |
| Stormbell Limited | 1 | 48 | 0% | 0 | 48 |
| Woodlawn Developments | 1 | 32 | 100% | 0 | — |
| Cieval Limited | 1 | 31 | 100% | 0 | — |
| Woodlawn Developments Limited | 1 | 28 | 100% | 0 | — |
| Johnstown Home Developments Limited | 1 | 21 | 100% | 0 | — |
| MB Homes Limited | 1 | 18 | 100% | 0 | — |
| JC Brenco Development Limited | 1 | 16 | 100% | 0 | — |
| Woodlawns Development Limited | 1 | 10 | 100% | 0 | — |
Permission, no start 5 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Link Road 2460145 | 64 | 9 May 2025 | Not started lapses in 4 years | Carlow |
| 'Shamrock Square' at the junction of Green Lane Staplestown 2360207 | 39 | 15 Mar 2024 | Not started lapses in 2 years | Carlow |
| Monastery 2660277 | 10 | 22 Oct 2026 | Not started lapses in 5 years | Carlow |
| Fenagh Rd 2560030 | 10 | 26 Nov 2025 | Not started lapses in 4 years | Tullow |
| Blackbog Grove 2198 | 10 | 18 Jan 2022 | Lapsing lapses in 2 months | Carlow |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CARLOW' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 30 Oct 2026, 10:12
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 30 Oct 2026, 10:12 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 30 Oct 2026, 10:12 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 30 Oct 2026, 10:12 | open |
Recomputed weekly from the store; last built 30 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.