Carlow: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

1,330 homes in 34 sites of 10 or more have been granted permission in Carlow since 2017. A commencement notice was lodged for 54% of them. 196 still have a live permission and no start; 20 of those lapse within a year, and 350 have already lapsed.

1,330
homes permitted · 34 sites
54%
started · 722 homes
196
not started · live permission
20
lapse within 12 months
350
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
20171590%059
2018233100%0
2019424614%0211
202025340%032
20212103100%0
2022510280%20
2023297100%0
2024516729%7148
2025621566%74
2026525564%31

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 21 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 73% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Elmendorf Limited1640%64
Shamrock Square Limited1390%39
Woodlawn Developments1320%32
Cieval Limited1310%31
Woodlawns Development Limited1100%10
T Nolan Developments Limited1100%10
Nesselside Builders Limited314860%059
Carlow Estates11250%0125
MESD Ventures Limited1760%076
MB Homes Limited264100%0
Peter Bolger Consulting Limited1620%0
South Eastern Builders Limited149100%0
Stormbell Limited1480%048
BYRNE & BYRNE LIMITED146100%0
BroCon Properties Limited133100%0
Hatch Company Limited1320%032
Woodlawn Developments Limited128100%0
Bunclody Estates Limited127100%0
Johnstown Home Developments Limited121100%0
JC Brenco Development Limited116100%0
Dunneace Construction Limited114100%0

Permission, no start 7 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Link Road 2460145649 May 2025Not started lapses in 4 years
'Shamrock Square' at the junction of Green Lane Staplestown 23602073915 Mar 2024Not started lapses in 2 years
Montgomery Street Andy Murphy Road 23601013212 Feb 2024Not started lapses in 2 years
Gort Na Gréine 26600313126 Aug 2026Not started lapses in 5 years
Fenagh Rd 25600301026 Nov 2025Not started lapses in 4 years
Ard Bhile 212461012 Jul 2022Lapsing lapses in 10 months
Blackbog Grove 21981018 Jan 2022Lapsing lapses in 4 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CARLOW' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.