Permitted, not started · Dublin City · grants of 10+ homes since 2021

Dublin City planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

21,300 homes in 177 sites of 10 or more have been granted permission in Dublin City since 2021. A commencement notice was lodged for 54% of them. 6,943 still have a live permission and no start; 1,641 of those lapse within a year, and 2,675 have already lapsed.

21,300
homes permitted · 177 sites
54%
started · 11,430 homes
6,943
not started · live permission
1,641
lapse within 12 months
2,675
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 12

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Ballyfermot-Drimnagh164,09170%1,235——
South East Inner City192,92562%1,0954212
North Inner City335,30337%955992,198
Kimmage-Rathmines191,64142%946566—
Artane-Whitehall111,14736%695——
South West Inner City191,20042%681399—
Ballymun-Finglas1071843%410321—
Cabra-Glasnevin1796953%25563205
Clontarf1198274%254131—
Pembroke1257462%21820—
Clondalkin1780%78——
Donaghmede81,60181%50—260

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021195,67250%1542,675
2022367,12079%1,487—
2023241,98576%486—
2024312,68137%1,701—
2025372,21617%1,847—
2026301,6267%1,268—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 65% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Serendale Limited14570%457—
HPREF HSQ Investments Limited13990%399—
Trinity College Dublin13580%358—
Jamestown Village Limited13210%321—
Terenure Land Limited12080%208—
Savona Limited11310%131—
Matriciana Limited1860%86—
Focus Housing Association CLG2810%81—
O'Flynn Construction (Milltown) Limited1780%78—
Marbelsand Holdings Limited1710%71—
Fruit Market Development Company Limited1640%64—
Westridge Milltown Limited1630%63—
Lidl Ireland GmbH1600%60—
Cluid Housing Association211147%59—
Cabhrú Housing Association1530%53—
Sales Limited1510%51—
Ginxo Trading Limited1460%46—
Double E Investments Limited1420%42—
Gerard Kelly Holdings Limited1410%41—
Pembroke Partnership Limited1380%38—
Creedon Group Limited1330%33—
Lark Finance Limited1310%31—
October Two Limited1300%30—
Esprit Investments Limited1270%27—
Vesada Private Limited1270%27—
Sevona Limited1240%24—
Infield Developments Limited1230%23—
Somerton House Limited1210%21—
Raya Investments Limited1200%20—
Murphy and Gunn Limited1190%19—

Under appeal 4 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
1-6 Beresford Street WEB5590/251891 May 2026Under appeal decision pendingZhivago's Corner
Larch Hill Estate WEB5466/25399 Feb 2026Under appeal decision pendingDublin
Emmet Court WEB5546/251324 Apr 2026Under appeal decision pendingDublin
Terenure Business Park WEB1117/261127 Jul 2026Under appeal decision pendingTerenure

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'DCC' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open