Permitted, not started · Dún Laoghaire-Rathdown · grants of 10+ homes since 2021

Dún Laoghaire-Rathdown planning permission: the homes nobody has started

Data updated 13 Nov 2026 · register lag up to 7 days · sources & freshness

13,557 homes in 94 sites of 10 or more have been granted permission in Dún Laoghaire-Rathdown since 2021. A commencement notice was lodged for 43% of them. 7,085 still have a live permission and no start; 1,001 of those lapse within a year, and 231 have already lapsed.

13,557
homes permitted · 94 sites
43%
started · 5,803 homes
7,085
not started · live permission
1,001
lapse within 12 months
231
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 7

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Glencullen-Sandyford253,45632%2,207112—
Killiney-Shankill202,83142%1,639——
Dundrum82,44051%1,201115—
Stillorgan171,99244%881475231
Bray East15860%586——
Dún Laoghaire151,23159%458299—
Blackrock81,02164%113——

By year granted

Granted inSitesHomesStartedNot startedLapsed
202161,80150%669231
2022101,86353%879—
2023131,34637%852—
2024192,02448%1,048—
2025294,61744%2,514—
2026171,90621%1,123—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 14 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 31% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Shankill Property Investments Limited15860%586—
Homeland Silverpines Limited14630%463—
Ironborn Real Estate Limited14380%438—
Clonkeen Investments DAC12990%299—
Atlas GP Limited12550%255—
Palemink Limited11900%190—
Pembroke Partnership Limited11150%115—
Bridgeclip (Developments) Limited11120%112—
KW PRS ICAV11020%102—
1 Wyckham Land Limited1531100%0—
Cairn Homes Properties Limited1377100%0—
Baker Forge Properties Limited1276100%0—
Winterbrook Homes Limited12310%0231
Adroit Operations Limited1203100%0—

Under appeal 5 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Temple Hill and Temple Road LRD26A/0051/WEB25228 Jul 2026Under appeal decision pendingBlackrock
Woodside, Blackglen Road D25A/0941/WEB8724 Apr 2026Under appeal decision pendingLamb's Cross
133 and 152 Ballyogan Road D24A/0981/WEB492 May 2025Under appeal decision pendingGlencullen-Sandyford
Arva, 137 Glenageary Road Upper D26A/0137/WEB3229 Jun 2026Under appeal decision pendingDún Laoghaire
Saint Helen's D26A/0240/WEB186 Jul 2026Under appeal decision pendingDún Laoghaire

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'DLR' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 13 Nov 2026, 23:02
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.013 Nov 2026, 23:02open
An Coimisiún Pleanála case listCC BY 4.013 Nov 2026, 23:02open
Building Control Management System commencement noticesCC BY 4.013 Nov 2026, 23:02open

Recomputed weekly from the store; last built 13 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.