Permitted, not started · Galway County · grants of 10+ homes since 2017

Galway County: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

2,748 homes in 71 sites of 10 or more have been granted permission in Galway County since 2017. A commencement notice was lodged for 41% of them. 1,258 still have a live permission and no start; — of those lapse within a year, and 199 have already lapsed.

2,748
homes permitted · 71 sites
41%
started · 1,138 homes
1,258
not started · live permission
—
lapse within 12 months
199
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2018820189%023
2019511781%022
202059844%055
2021511889%013
202236356%28—
2023831956%139—
20241571931%41386
20251662345%341—
202664900%337—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 73% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Gort Homes Developments Limited12340%234—
Corestone 16 Limited12090%209—
Burkeway Homes Limited21390%12118
O'Malley Construction Company1740%74—
Leadlane (Loughrea) Limited2710%71—
Solus Holdings Unlimited Company1650%65—
Cahermorris Developments Limited1390%39—
Solus Holding Unlimited Company1370%37—
Acton MR Construction Limited1280%28—
Regalview Tuam Limited1260%26—
Corestone Limited1180%18—
RHOC Gort Limited1160%16—
Leadlane Limited22442%14—
Goaley Crescent Contracts Limited1140%14—
Greenstorm Limited1120%12—
Coppinger Building & Civil Engineering Limited1100%10—
Athenry Ventures Limited1133100%0—
Ardstone Homes176100%0—
Shane O'Connor & Enda Hallinan (JRBOC Limited)1680%068
Laurem Construction Limited149100%0—
Drumque Limited148100%0—
Carbon Sole Power Limited147100%0—
Jardonelle Limited245100%0—
K King Construction Claregalway Limited139100%0—
Tourlecan Developments Limited138100%0—
Ardent Property Investment Limited137100%0—
Leadlane (Ballinasloe)Limited136100%0—
Sathel Limited1320%032
Roonith Properties Limited130100%0—
Greengrass Developments Limited128100%0—

Lapses within a year 0 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

Nothing in this list.

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.