Permitted, not started · Galway County · grants of 10+ homes since 2021

Galway County planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

2,520 homes in 53 sites of 10 or more have been granted permission in Galway County since 2021. A commencement notice was lodged for 51% of them. 974 still have a live permission and no start; — of those lapse within a year, and 86 have already lapsed.

2,520
homes permitted · 53 sites
51%
started · 1,284 homes
974
not started · live permission
—
lapse within 12 months
86
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 7

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Gort-Kinvara1061743%286—68
Tuam52757%240——
Ballinasloe723820%191——
Athenry-Oranmore1790968%133——
Conamara North39532%65——
Loughrea719570%59——
Conamara South419191%0—18

By year granted

Granted inSitesHomesStartedNot startedLapsed
202224132%28—
20239380100%0—
20241674047%30986
20251662354%286—
20261073628%351—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 29 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 52% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Solus Holdings Unlimited Company1650%65—
Solus Holding Unlimited Company1370%37—
Acton MR Construction Limited1280%28—
Regalview Tuam Limited1260%26—
Leadlane (Loughrea) Limited39283%16—
Goaley Crescent Contracts Limited1140%14—
Greenstorm Limited1120%12—
Coppinger Building & Civil Engineering Limited1100%10—
Corestone 16 Limited1209100%0—
Burkeway Homes Limited213987%018
Athenry Ventures Limited1133100%0—
O'Malley Construction Company174100%0—
Shane O'Connor & Enda Hallinan (JRBOC Limited)1680%068
JRBOC Oranmore Limited161100%0—
Laurem Construction Limited149100%0—
Tourlecan Developments Limited138100%0—
Ardent Property Investment Limited137100%0—
Leadlane (Ballinasloe)Limited136100%0—
Jardonelle Limited133100%0—
Greengrass Developments Limited128100%0—
Corestone Limited118100%0—
Callanan & Walsh Construction Co. Limited1170%0—
RHOC Gort Limited116100%0—
Carrigveagh Developments Limited116100%0—
Hyman Properties Limited115100%0—
Leadlane Limited114100%0—
Kenny Developments Contracting Limited112100%0—
C&N Higgins Development Limited111100%0—
Bellville Building & Construction Galway Limited111100%0—

Permission, no start 20 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Lavally 246011523423 Dec 2024Not started lapses in 3 yearsGort-Kinvara
Farrannamartin 266090614929 Sept 2026Not started lapses in 5 yearsTuam
Headford 24616016526 Aug 2025Not started lapses in 4 yearsTuam
Kilgarve 26600156313 Oct 2026Not started lapses in 5 yearsBallinasloe
Athenry 2461674609 Dec 2025Not started lapses in 4 yearsAthenry-Oranmore
Pollboy & Dunlo 24614175016 Jun 2025Not started lapses in 4 yearsBallinasloe
Caheronaun 2660187439 Oct 2026Not started lapses in 5 yearsLoughrea
Treanrevagh 2560911395 Feb 2026Not started lapses in 5 yearsBallinasloe
Fough East 24604663717 Feb 2025Not started lapses in 3 yearsConamara North
Prospect 23615743718 Nov 2024Not started lapses in 3 yearsAthenry-Oranmore
Dungory West 26607013115 Oct 2026Not started lapses in 5 yearsGort-Kinvara
Ardbear 212264289 May 2022Not started lapses in 4 yearsConamara North
Tirboy 2560998263 Feb 2026Not started lapses in 4 yearsTuam
Moylough 23604722410 Jun 2024Not started lapses in 3 yearsBallinasloe
Gort 2460322213 Mar 2025Not started lapses in 3 yearsGort-Kinvara
Caheronaun 25602971624 Jun 2025Not started lapses in 4 yearsLoughrea
Ballyroe 24615561511 Nov 2025Not started lapses in 4 yearsBallinasloe
Droim Na Gaoithe 2361411143 Jun 2024Not started lapses in 3 yearsAthenry-Oranmore
Athenry 25613691222 Dec 2025Not started lapses in 4 yearsAthenry-Oranmore
Carrowmoneash 2460822107 Apr 2025Not started lapses in 3 yearsAthenry-Oranmore

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness