Galway County planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
2,520 homes in 53 sites of 10 or more have been granted permission in Galway County since 2021. A commencement notice was lodged for 51% of them. 974 still have a live permission and no start; — of those lapse within a year, and 86 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 7
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Gort-Kinvara | 10 | 617 | 43% | 286 | — | 68 |
| Tuam | 5 | 275 | 7% | 240 | — | — |
| Ballinasloe | 7 | 238 | 20% | 191 | — | — |
| Athenry-Oranmore | 17 | 909 | 68% | 133 | — | — |
| Conamara North | 3 | 95 | 32% | 65 | — | — |
| Loughrea | 7 | 195 | 70% | 59 | — | — |
| Conamara South | 4 | 191 | 91% | 0 | — | 18 |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2022 | 2 | 41 | 32% | 28 | — |
| 2023 | 9 | 380 | 100% | 0 | — |
| 2024 | 16 | 740 | 47% | 309 | 86 |
| 2025 | 16 | 623 | 54% | 286 | — |
| 2026 | 10 | 736 | 28% | 351 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 29 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 52% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Solus Holdings Unlimited Company | 1 | 65 | 0% | 65 | — |
| Solus Holding Unlimited Company | 1 | 37 | 0% | 37 | — |
| Acton MR Construction Limited | 1 | 28 | 0% | 28 | — |
| Regalview Tuam Limited | 1 | 26 | 0% | 26 | — |
| Leadlane (Loughrea) Limited | 3 | 92 | 83% | 16 | — |
| Goaley Crescent Contracts Limited | 1 | 14 | 0% | 14 | — |
| Greenstorm Limited | 1 | 12 | 0% | 12 | — |
| Coppinger Building & Civil Engineering Limited | 1 | 10 | 0% | 10 | — |
| Corestone 16 Limited | 1 | 209 | 100% | 0 | — |
| Burkeway Homes Limited | 2 | 139 | 87% | 0 | 18 |
| Athenry Ventures Limited | 1 | 133 | 100% | 0 | — |
| O'Malley Construction Company | 1 | 74 | 100% | 0 | — |
| Shane O'Connor & Enda Hallinan (JRBOC Limited) | 1 | 68 | 0% | 0 | 68 |
| JRBOC Oranmore Limited | 1 | 61 | 100% | 0 | — |
| Laurem Construction Limited | 1 | 49 | 100% | 0 | — |
| Tourlecan Developments Limited | 1 | 38 | 100% | 0 | — |
| Ardent Property Investment Limited | 1 | 37 | 100% | 0 | — |
| Leadlane (Ballinasloe)Limited | 1 | 36 | 100% | 0 | — |
| Jardonelle Limited | 1 | 33 | 100% | 0 | — |
| Greengrass Developments Limited | 1 | 28 | 100% | 0 | — |
| Corestone Limited | 1 | 18 | 100% | 0 | — |
| Callanan & Walsh Construction Co. Limited | 1 | 17 | 0% | 0 | — |
| RHOC Gort Limited | 1 | 16 | 100% | 0 | — |
| Carrigveagh Developments Limited | 1 | 16 | 100% | 0 | — |
| Hyman Properties Limited | 1 | 15 | 100% | 0 | — |
| Leadlane Limited | 1 | 14 | 100% | 0 | — |
| Kenny Developments Contracting Limited | 1 | 12 | 100% | 0 | — |
| C&N Higgins Development Limited | 1 | 11 | 100% | 0 | — |
| Bellville Building & Construction Galway Limited | 1 | 11 | 100% | 0 | — |
Permission, no start 20 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Lavally 2460115 | 234 | 23 Dec 2024 | Not started lapses in 3 years | Gort-Kinvara |
| Farrannamartin 2660906 | 149 | 29 Sept 2026 | Not started lapses in 5 years | Tuam |
| Headford 2461601 | 65 | 26 Aug 2025 | Not started lapses in 4 years | Tuam |
| Kilgarve 2660015 | 63 | 13 Oct 2026 | Not started lapses in 5 years | Ballinasloe |
| Athenry 2461674 | 60 | 9 Dec 2025 | Not started lapses in 4 years | Athenry-Oranmore |
| Pollboy & Dunlo 2461417 | 50 | 16 Jun 2025 | Not started lapses in 4 years | Ballinasloe |
| Caheronaun 2660187 | 43 | 9 Oct 2026 | Not started lapses in 5 years | Loughrea |
| Treanrevagh 2560911 | 39 | 5 Feb 2026 | Not started lapses in 5 years | Ballinasloe |
| Fough East 2460466 | 37 | 17 Feb 2025 | Not started lapses in 3 years | Conamara North |
| Prospect 2361574 | 37 | 18 Nov 2024 | Not started lapses in 3 years | Athenry-Oranmore |
| Dungory West 2660701 | 31 | 15 Oct 2026 | Not started lapses in 5 years | Gort-Kinvara |
| Ardbear 212264 | 28 | 9 May 2022 | Not started lapses in 4 years | Conamara North |
| Tirboy 2560998 | 26 | 3 Feb 2026 | Not started lapses in 4 years | Tuam |
| Moylough 2360472 | 24 | 10 Jun 2024 | Not started lapses in 3 years | Ballinasloe |
| Gort 2460322 | 21 | 3 Mar 2025 | Not started lapses in 3 years | Gort-Kinvara |
| Caheronaun 2560297 | 16 | 24 Jun 2025 | Not started lapses in 4 years | Loughrea |
| Ballyroe 2461556 | 15 | 11 Nov 2025 | Not started lapses in 4 years | Ballinasloe |
| Droim Na Gaoithe 2361411 | 14 | 3 Jun 2024 | Not started lapses in 3 years | Athenry-Oranmore |
| Athenry 2561369 | 12 | 22 Dec 2025 | Not started lapses in 4 years | Athenry-Oranmore |
| Carrowmoneash 2460822 | 10 | 7 Apr 2025 | Not started lapses in 3 years | Athenry-Oranmore |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness