Galway County: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
2,748 homes in 71 sites of 10 or more have been granted permission in Galway County since 2017. A commencement notice was lodged for 41% of them. 1,394 still have a live permission and no start; — of those lapse within a year, and 199 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2018 | 8 | 201 | 89% | 0 | 23 |
| 2019 | 5 | 117 | 81% | 0 | 22 |
| 2020 | 5 | 98 | 44% | 0 | 55 |
| 2021 | 5 | 118 | 89% | 0 | 13 |
| 2022 | 3 | 63 | 56% | 28 | — |
| 2023 | 8 | 319 | 56% | 139 | — |
| 2024 | 15 | 719 | 31% | 413 | 86 |
| 2025 | 16 | 623 | 45% | 341 | — |
| 2026 | 6 | 490 | 0% | 473 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 87% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Gort Homes Developments Limited | 1 | 234 | 0% | 234 | — |
| Corestone 16 Limited | 1 | 209 | 0% | 209 | — |
| Athenry Luxury Housing Developments Limited | 1 | 136 | 0% | 136 | — |
| Burkeway Homes Limited | 2 | 139 | 0% | 121 | 18 |
| Solus Holdings Unlimited Company | 2 | 102 | 0% | 102 | — |
| O'Malley Construction Company | 1 | 74 | 0% | 74 | — |
| Leadlane (Loughrea) Limited | 2 | 71 | 0% | 71 | — |
| Brackenside Investment Limited | 1 | 63 | 0% | 63 | — |
| Ghost Zapper Limited | 1 | 60 | 0% | 60 | — |
| Cahermorris Developments Limited | 1 | 39 | 0% | 39 | — |
| Solus Holding Unlimited Company | 1 | 37 | 0% | 37 | — |
| Acton MR Construction Limited | 1 | 28 | 0% | 28 | — |
| Regalview Tuam Limited | 1 | 26 | 0% | 26 | — |
| Silverstame Limited | 1 | 21 | 0% | 21 | — |
| Corestone Limited | 1 | 18 | 0% | 18 | — |
| RHOC Gort Limited | 1 | 16 | 0% | 16 | — |
| Leadlane Limited | 2 | 24 | 42% | 14 | — |
| Goaley Crescent Contracts Limited | 1 | 14 | 0% | 14 | — |
| Greenstorm Limited | 1 | 12 | 0% | 12 | — |
| Coppinger Building & Civil Engineering Limited | 1 | 10 | 0% | 10 | — |
| Athenry Ventures Limited | 1 | 133 | 100% | 0 | — |
| Ardstone Homes | 1 | 76 | 100% | 0 | — |
| Shane O'Connor & Enda Hallinan (JRBOC Limited) | 1 | 68 | 0% | 0 | 68 |
| Laurem Construction Limited | 1 | 49 | 100% | 0 | — |
| Drumque Limited | 1 | 48 | 100% | 0 | — |
| Carbon Sole Power Limited | 1 | 47 | 100% | 0 | — |
| Jardonelle Limited | 2 | 45 | 100% | 0 | — |
| JAPET Investments | 1 | 43 | 100% | 0 | — |
| K King Construction Claregalway Limited | 1 | 39 | 100% | 0 | — |
| Tourlecan Developments Limited | 1 | 38 | 100% | 0 | — |
Work started 37 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Cullairbaun 2560251 | 133 | 10 Jun 2025 | Started notice 8 Dec 2025 | |
| Frenchfort 171268 | 76 | 16 Jul 2018 | Started notice 29 Oct 2018 | |
| Ennis Road Gort 2360437 | 70 | 17 Jun 2024 | Started notice 10 Oct 2025 | |
| Droim Na Gaoithe & An Chreig Bhuí 2461773 | 62 | 5 Aug 2025 | Started notice 6 Apr 2026 | |
| Baunmore Gortnahown & Farranablake East 2461699 | 49 | 12 Aug 2025 | Started notice 23 Dec 2025 | |
| Forramoyle East 171314 | 48 | 16 Mar 2018 | Started notice 10 Sept 2018 | |
| Kilgarve Creagh 20989 | 47 | 28 Oct 2021 | Started notice 19 Nov 2021 | |
| Dungory West 2360774 | 45 | 27 Nov 2023 | Started notice 22 Apr 2024 | |
| Oranhill 21408 | 43 | 13 Oct 2023 | Started notice 15 Apr 2024 | |
| Summerfield Claregalway 181015 | 39 | 18 Feb 2019 | Started notice 14 Dec 2019 | |
| Caherroyn 2361431 | 38 | 11 Mar 2024 | Started notice 12 Apr 2024 | |
| Baile Uí Chuirc Thiar 2460796 | 37 | 27 Nov 2024 | Started notice 13 Dec 2024 | |
| Kilgarve 2260425 | 36 | 6 Feb 2023 | Started notice 10 Jul 2023 | |
| Cosmona 2460496 | 33 | 2 Dec 2024 | Started notice 17 Dec 2024 | |
| Clifden 2360160 | 30 | 8 Jan 2024 | Started notice 24 Sept 2024 | |
| Cartron 2360168 | 28 | 9 Oct 2023 | Started notice 29 Jul 2024 | |
| Kinvarra 1952 | 28 | 13 Mar 2019 | Started notice 30 Apr 2021 | |
| Cregg 201298 | 22 | 21 Sept 2022 | Started notice 9 Dec 2022 | |
| Lakeview Glenamaddy 20493 | 22 | 10 Mar 2021 | Started notice 1 Jun 2022 | |
| Vicarschoral Land 201601 | 22 | 15 Feb 2021 | Started notice 18 Oct 2022 | |
| An Cnocán Carrach 19314 | 20 | 13 Jan 2020 | Started notice 29 Nov 2024 | |
| Prospect 18355 | 19 | 15 Oct 2018 | Started notice 28 Apr 2022 | |
| Raheen 191077 | 17 | 14 Oct 2019 | Started notice 4 Jul 2024 | |
| Ballydavid South 2461555 | 16 | 3 Mar 2025 | Started notice 30 May 2025 | |
| Ard Na Speire 2260813 | 15 | 6 Mar 2023 | Started notice 24 Apr 2024 | |
| Carrigweir Tuam 20982 | 14 | 1 Dec 2021 | Started notice 24 May 2023 | |
| Cosmona 22748 | 13 | 26 Jun 2023 | Started notice 23 Apr 2024 | |
| ORANBEG 211661 | 13 | 30 May 2022 | Started notice 14 Mar 2023 | |
| St. Laurencesfields 19697 | 13 | 17 Feb 2020 | Started notice 5 Sept 2023 | |
| Mount Vernon Station Road Carrowmoneash & Millplot 2360752 | 12 | 19 Feb 2024 | Started notice 15 Apr 2024 | |
| Moycullen 171516 | 12 | 2 Jul 2018 | Started notice 10 Jul 2023 | |
| Cosmona 18227 | 12 | 4 Jun 2018 | Started notice 21 Aug 2018 | |
| Cullairbaun 2560448 | 11 | 22 Jul 2025 | Started notice 2 Dec 2025 | |
| Main Street 2460805 | 11 | 22 Jan 2025 | Started notice 24 Mar 2025 | |
| Letterfrack 181079 | 11 | 25 Feb 2019 | Started notice 23 Oct 2020 | |
| Killarainy 17812 | 11 | 10 Jan 2018 | Started notice 27 Mar 2019 | |
| Tullagh Upper 191683 | 10 | 8 Jun 2020 | Started notice 19 Oct 2020 |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.