PlanningRegister.ie
Permitted, not started · Galway County · grants of 10+ homes since 2017

Galway County: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

2,748 homes in 71 sites of 10 or more have been granted permission in Galway County since 2017. A commencement notice was lodged for 41% of them. 1,394 still have a live permission and no start; — of those lapse within a year, and 199 have already lapsed.

2,748
homes permitted · 71 sites
41%
started · 1,138 homes
1,394
not started · live permission
—
lapse within 12 months
199
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2018820189%023
2019511781%022
202059844%055
2021511889%013
202236356%28—
2023831956%139—
20241571931%41386
20251662345%341—
202664900%473—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 87% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Gort Homes Developments Limited12340%234—
Corestone 16 Limited12090%209—
Athenry Luxury Housing Developments Limited11360%136—
Burkeway Homes Limited21390%12118
Solus Holdings Unlimited Company21020%102—
O'Malley Construction Company1740%74—
Leadlane (Loughrea) Limited2710%71—
Brackenside Investment Limited1630%63—
Ghost Zapper Limited1600%60—
Cahermorris Developments Limited1390%39—
Solus Holding Unlimited Company1370%37—
Acton MR Construction Limited1280%28—
Regalview Tuam Limited1260%26—
Silverstame Limited1210%21—
Corestone Limited1180%18—
RHOC Gort Limited1160%16—
Leadlane Limited22442%14—
Goaley Crescent Contracts Limited1140%14—
Greenstorm Limited1120%12—
Coppinger Building & Civil Engineering Limited1100%10—
Athenry Ventures Limited1133100%0—
Ardstone Homes176100%0—
Shane O'Connor & Enda Hallinan (JRBOC Limited)1680%068
Laurem Construction Limited149100%0—
Drumque Limited148100%0—
Carbon Sole Power Limited147100%0—
Jardonelle Limited245100%0—
JAPET Investments143100%0—
K King Construction Claregalway Limited139100%0—
Tourlecan Developments Limited138100%0—

Work started 37 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Cullairbaun 256025113310 Jun 2025Started notice 8 Dec 2025
Frenchfort 1712687616 Jul 2018Started notice 29 Oct 2018
Ennis Road Gort 23604377017 Jun 2024Started notice 10 Oct 2025
Droim Na Gaoithe & An Chreig Bhuí 2461773625 Aug 2025Started notice 6 Apr 2026
Baunmore Gortnahown & Farranablake East 24616994912 Aug 2025Started notice 23 Dec 2025
Forramoyle East 1713144816 Mar 2018Started notice 10 Sept 2018
Kilgarve Creagh 209894728 Oct 2021Started notice 19 Nov 2021
Dungory West 23607744527 Nov 2023Started notice 22 Apr 2024
Oranhill 214084313 Oct 2023Started notice 15 Apr 2024
Summerfield Claregalway 1810153918 Feb 2019Started notice 14 Dec 2019
Caherroyn 23614313811 Mar 2024Started notice 12 Apr 2024
Baile Uí Chuirc Thiar 24607963727 Nov 2024Started notice 13 Dec 2024
Kilgarve 2260425366 Feb 2023Started notice 10 Jul 2023
Cosmona 2460496332 Dec 2024Started notice 17 Dec 2024
Clifden 2360160308 Jan 2024Started notice 24 Sept 2024
Cartron 2360168289 Oct 2023Started notice 29 Jul 2024
Kinvarra 19522813 Mar 2019Started notice 30 Apr 2021
Cregg 2012982221 Sept 2022Started notice 9 Dec 2022
Lakeview Glenamaddy 204932210 Mar 2021Started notice 1 Jun 2022
Vicarschoral Land 2016012215 Feb 2021Started notice 18 Oct 2022
An Cnocán Carrach 193142013 Jan 2020Started notice 29 Nov 2024
Prospect 183551915 Oct 2018Started notice 28 Apr 2022
Raheen 1910771714 Oct 2019Started notice 4 Jul 2024
Ballydavid South 2461555163 Mar 2025Started notice 30 May 2025
Ard Na Speire 2260813156 Mar 2023Started notice 24 Apr 2024
Carrigweir Tuam 20982141 Dec 2021Started notice 24 May 2023
Cosmona 227481326 Jun 2023Started notice 23 Apr 2024
ORANBEG 2116611330 May 2022Started notice 14 Mar 2023
St. Laurencesfields 196971317 Feb 2020Started notice 5 Sept 2023
Mount Vernon Station Road Carrowmoneash & Millplot 23607521219 Feb 2024Started notice 15 Apr 2024
Moycullen 171516122 Jul 2018Started notice 10 Jul 2023
Cosmona 18227124 Jun 2018Started notice 21 Aug 2018
Cullairbaun 25604481122 Jul 2025Started notice 2 Dec 2025
Main Street 24608051122 Jan 2025Started notice 24 Mar 2025
Letterfrack 1810791125 Feb 2019Started notice 23 Oct 2020
Killarainy 178121110 Jan 2018Started notice 27 Mar 2019
Tullagh Upper 191683108 Jun 2020Started notice 19 Oct 2020

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'GALWAYCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open