Permitted, not started · Kerry · grants of 10+ homes since 2021

Kerry planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

3,187 homes in 55 sites of 10 or more have been granted permission in Kerry since 2021. A commencement notice was lodged for 51% of them. 1,112 still have a live permission and no start; 48 of those lapse within a year, and — have already lapsed.

3,187
homes permitted · 55 sites
51%
started · 1,629 homes
1,112
not started · live permission
48
lapse within 12 months
—
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 5

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Killarney221,51748%40618—
Tralee1594865%33330—
Listowel61906%178——
Corca Dhuibhne721353%100——
Kenmare531950%95——

By year granted

Granted inSitesHomesStartedNot startedLapsed
202129882%18—
2022924788%30—
2023856681%109—
20241258877%135—
2025946923%362—
2026151,21926%458—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 25 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 52% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Homeland Projects Limited22170%217—
Focus Housing Association CLG1670%67—
NED O'SHEA & SONS CONSTRUCTION (TRALEE Limited)2430%43—
HRP CONSTRUCTION1280%28—
TELLO DEVELOPMENTS (BALLYARD) LIMITED1250%25—
OCTAVIUS PROPERTY COMPANY LIMITED1180%18—
Goldstar 2 Limited1140%14—
THE SOCIETY OF ST VINCENT DE PAUL1120%12—
Cherryhill Developments Limited1120%12—
KPH Construction2325100%0—
Dipharma Unlimited Company12590%0—
Tulfarris CG Limited1147100%0—
AMHOLA OAKPARK LIMITED188100%0—
OHR DEVELOPMENTS LIMITED AND CHERRYHILL DEVELOPMENTS LIMITED180100%0—
Ross-Park Residential HS Limited170100%0—
Barraduff Homes Limited262100%0—
GM O' MURCHU CONSULTING Limited147100%0—
RUSHPARK DEVELOPMENTS LIMITED238100%0—
WRIGHTWOOD DEVELOPMENTS Limited117100%0—
X DEV REAL ESTATE Limited116100%0—
THERMO HOUSE Limited116100%0—
NAILUN LIMITED114100%0—
GOLDSTAR HOMES 2 Limited114100%0—
ZINBAR GROVE DEVELOPMENTS112100%0—
Xdev Real Estate Limited111100%0—

Work started 26 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
UPPER PARK ROAD 2396724930 Nov 2023Started notice 22 Apr 2024Killarney
Clash Road 256064024521 Jan 2026Started notice 4 Aug 2026Tralee
Port Road and St Margaret’s Road 246029522412 Nov 2024Started notice 18 Sept 2026Killarney
Cloon More 23601501475 Dec 2023Started notice 30 Jan 2026Tralee
OAKPARK ROAD 2115198824 May 2022Started notice 17 Jul 2025Tralee
Banshagh 2560351806 Oct 2025Started notice 7 Nov 2025Kenmare
BANSHAGH 211888025 Aug 2021Started notice 22 Apr 2024Kenmare
St. Margaret's Road & Dr. Hans Liebherr Road 2560435708 Jan 2026Started notice 2 Mar 2026Killarney
BALLYARD ROAD 226305221 Feb 2024Started notice 18 Apr 2024Tralee
KNOCKAVOTA 2213434711 Oct 2023Started notice 11 Oct 2024Corca Dhuibhne
PARKNADOON HOUSE 2212253923 Sept 2024Started notice 30 Dec 2025Tralee
Shronedarragh 23603343516 Apr 2024Started notice 23 Apr 2024Killarney
PÁIRC CHUIMIN 226603317 Jul 2024Started notice 26 Sept 2024Killarney
MONSIGNOR O'FLAHERTY ROAD 212713328 Jun 2022Started notice 1 Aug 2022Killarney
BALLYMULLEN ROAD/CLOONBEG 22173015 Feb 2024Started notice 17 Dec 2024Tralee
Shronedarragh 25602292714 Aug 2025Started notice 8 May 2026Killarney
KNOCKAVOTA 22117191 Sept 2022Started notice 23 Apr 2024Corca Dhuibhne
KNOCKAVOTA 22122191 Sept 2022Started notice 23 Apr 2024Corca Dhuibhne
ARDSHANAVOOLEY 239911726 Jan 2024Started notice 15 Apr 2024Killarney
SHRONEDARRAGH 22484165 Aug 2022Started notice 14 Jul 2023Killarney
CHERRY DRIVE 224166 Apr 2022Started notice 20 Mar 2023Corca Dhuibhne
TRALEE 236401425 Oct 2023Started notice 12 Dec 2023Tralee
SCRAHANE 22561427 Jul 2022Started notice 1 Sept 2022Killarney
Fearann Flainn 23604001220 Dec 2024Started notice 24 Jun 2026Listowel
GROVE 22379125 Jul 2022Started notice 2 Aug 2022Corca Dhuibhne
Shronedarragh 24606441128 Nov 2024Started notice 18 Dec 2024Killarney

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KERRY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness