PlanningRegister.ie
Permitted, not started · Kerry · grants of 10+ homes since 2017

Kerry: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

3,608 homes in 79 sites of 10 or more have been granted permission in Kerry since 2017. A commencement notice was lodged for 58% of them. 989 still have a live permission and no start; 119 of those lapse within a year, and 117 have already lapsed.

3,608
homes permitted · 79 sites
58%
started · 2,094 homes
989
not started · live permission
119
lapse within 12 months
117
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
201759180%018
2018613482%024
20196135100%0
2020824074%062
2021514779%1813
2022925160%101
2023856681%109
20241258877%135
2025946923%362
20261198732%264

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 90% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Homeland Projects Limited326919%217
OFSolutions Limited1850%85
SOCIAL HOUSING COMPANY1720%72
Focus Housing Association CLG1670%67
NKP LIMITED1490%49
Rodcliff Construction Limited1450%45
NED O'SHEA & SONS CONSTRUCTION (TRALEE Limited)2430%43
ZANKA DEVELOPMENTS1430%43
RUSHPARK DEVELOPMENTS LIMITED2380%38
IPH KILLARNEY HOLDINGS LIMITED1330%33
HRP CONSTRUCTION1280%28
AGC Ventures Limited T and A Atlantic Golf Construction1270%27
TELLO DEVELOPMENTS (BALLYARD) LIMITED1250%25
Cherryhill Developments Limited33741%22
OCTAVIUS PROPERTY COMPANY LIMITED1180%18
Ballylongford Developments Limited1180%18
Goldstar 2 Limited1140%14
THE SOCIETY OF ST VINCENT DE PAUL1120%12
KPH Construction3574100%0
Dipharma Unlimited Company12590%0
Portal Asset Holdings Limited1224100%0
Tulfarris CG Limited2186100%0
AMHOLA OAKPARK LIMITED188100%0
Ruden Homes Limited1850%0
Ross-Park Residential HS Limited170100%0
GERARD GRIFFIN CONSTRUCTION AND DEVELOPMENTS Limited270100%0
EVANS AND KELLIHER CONSTRUCTION LIMITED168100%0
LSG PROPERTY DEVELOPMETNS LIMITED167100%0
HOMELY DEVELOPMENTS Limited166100%0
Barraduff Homes Limited262100%0

Permission, no start 25 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Ross Road 256068213430 Sept 2025Not started lapses in 4 years
Greenville LRD Development 24601201026 Aug 2024Not started lapses in 3 years
Bell Height 25600388524 Jul 2026Not started lapses in 5 years
Cloghers 25605748330 Jul 2026Not started lapses in 5 years
Grove 2460764728 Oct 2025Not started lapses in 4 years
Woodlands Industrial Estate 25605856729 Sept 2025Not started lapses in 4 years
N22 AND BALLYCASHEEN ROAD 237594927 Jan 2025Not started lapses in 3 years
Lios Iarr Estate 25607884522 Apr 2026Not started lapses in 5 years
PARK 22894315 Feb 2023Not started lapses within a year
MONSIGNOR O'FLAHERTY ROAD 212713328 Jun 2022Lapsing lapses in 9 months
JAMES STREET/CANAL NEW ROAD/BASIN VIEW 219383027 Jan 2022Lapsing lapses in 4 months
JOHN STREET 22542286 Jan 2023Not started lapses in 3 years
Church Road 25601722712 Mar 2026Not started lapses in 4 years
TRALEE BAY AND WETLANDS ECO AND ACTIVITY CENTRE 23251257 Jun 2023Not started lapses in 2 years
CLANMAURICE 23831922 Feb 2024Not started lapses in 2 years
KNOCKAVOTA 22117191 Sept 2022Lapsing lapses in 11 months
KNOCKAVOTA 22122191 Sept 2022Lapsing lapses in 11 months
Ballymacassy Main Street 24609221823 Dec 2025Not started lapses in 4 years
BALLYCASHEEN 213321824 May 2021Lapsing lapses in 2 months
Scrahane 2460277142 Aug 2024Not started lapses in 3 years
NO. 10 BASIN ROAD/RAE STREET BUNGALOWS 22523132 Mar 2023Not started lapses within a year
SHRONEDARRAGH 25211226 Feb 2026Not started lapses in 4 years
Bellview Woods 25607371219 Feb 2026Not started lapses in 4 years
SANDHILL ROAD 251031224 Oct 2025Not started lapses in 4 years
Carhan Road 2460875106 Nov 2025Not started lapses in 4 years

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KERRY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness