Kerry planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
3,187 homes in 55 sites of 10 or more have been granted permission in Kerry since 2021. A commencement notice was lodged for 51% of them. 1,112 still have a live permission and no start; 48 of those lapse within a year, and — have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 5
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Killarney | 22 | 1,517 | 48% | 406 | 18 | — |
| Tralee | 15 | 948 | 65% | 333 | 30 | — |
| Listowel | 6 | 190 | 6% | 178 | — | — |
| Corca Dhuibhne | 7 | 213 | 53% | 100 | — | — |
| Kenmare | 5 | 319 | 50% | 95 | — | — |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 2 | 98 | 82% | 18 | — |
| 2022 | 9 | 247 | 88% | 30 | — |
| 2023 | 8 | 566 | 81% | 109 | — |
| 2024 | 12 | 588 | 77% | 135 | — |
| 2025 | 9 | 469 | 23% | 362 | — |
| 2026 | 15 | 1,219 | 26% | 458 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 25 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 52% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Homeland Projects Limited | 2 | 217 | 0% | 217 | — |
| Focus Housing Association CLG | 1 | 67 | 0% | 67 | — |
| NED O'SHEA & SONS CONSTRUCTION (TRALEE Limited) | 2 | 43 | 0% | 43 | — |
| HRP CONSTRUCTION | 1 | 28 | 0% | 28 | — |
| TELLO DEVELOPMENTS (BALLYARD) LIMITED | 1 | 25 | 0% | 25 | — |
| OCTAVIUS PROPERTY COMPANY LIMITED | 1 | 18 | 0% | 18 | — |
| Goldstar 2 Limited | 1 | 14 | 0% | 14 | — |
| THE SOCIETY OF ST VINCENT DE PAUL | 1 | 12 | 0% | 12 | — |
| Cherryhill Developments Limited | 1 | 12 | 0% | 12 | — |
| KPH Construction | 2 | 325 | 100% | 0 | — |
| Dipharma Unlimited Company | 1 | 259 | 0% | 0 | — |
| Tulfarris CG Limited | 1 | 147 | 100% | 0 | — |
| AMHOLA OAKPARK LIMITED | 1 | 88 | 100% | 0 | — |
| OHR DEVELOPMENTS LIMITED AND CHERRYHILL DEVELOPMENTS LIMITED | 1 | 80 | 100% | 0 | — |
| Ross-Park Residential HS Limited | 1 | 70 | 100% | 0 | — |
| Barraduff Homes Limited | 2 | 62 | 100% | 0 | — |
| GM O' MURCHU CONSULTING Limited | 1 | 47 | 100% | 0 | — |
| RUSHPARK DEVELOPMENTS LIMITED | 2 | 38 | 100% | 0 | — |
| WRIGHTWOOD DEVELOPMENTS Limited | 1 | 17 | 100% | 0 | — |
| X DEV REAL ESTATE Limited | 1 | 16 | 100% | 0 | — |
| THERMO HOUSE Limited | 1 | 16 | 100% | 0 | — |
| NAILUN LIMITED | 1 | 14 | 100% | 0 | — |
| GOLDSTAR HOMES 2 Limited | 1 | 14 | 100% | 0 | — |
| ZINBAR GROVE DEVELOPMENTS | 1 | 12 | 100% | 0 | — |
| Xdev Real Estate Limited | 1 | 11 | 100% | 0 | — |
Permission, no start 24 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Ross Road 2560682 | 134 | 30 Sept 2025 | Not started lapses in 4 years | Killarney |
| Greenville LRD Development 2460120 | 102 | 6 Aug 2024 | Not started lapses in 3 years | Listowel |
| Bell Height 2560038 | 85 | 24 Jul 2026 | Not started lapses in 5 years | Kenmare |
| Caherslee 2660350 | 85 | 17 Jun 2026 | Not started lapses in 5 years | Tralee |
| Cloghers 2560574 | 83 | 30 Jul 2026 | Not started lapses in 5 years | Tralee |
| Grove 2460764 | 72 | 8 Oct 2025 | Not started lapses in 4 years | Corca Dhuibhne |
| Woodlands Industrial Estate 2560585 | 67 | 29 Sept 2025 | Not started lapses in 4 years | Killarney |
| Main Street 2560992 | 57 | 2 Nov 2026 | Not started lapses in 5 years | Killarney |
| N22 AND BALLYCASHEEN ROAD 23759 | 49 | 27 Jan 2025 | Not started lapses in 3 years | Killarney |
| Lios Iarr Estate 2560788 | 45 | 31 Aug 2026 | Not started lapses in 5 years | Tralee |
| PARK 2289 | 43 | 15 Feb 2023 | Not started lapses within a year | Killarney |
| Clash Road 2660705 | 34 | 19 Oct 2026 | Not started lapses in 5 years | Tralee |
| JOHN STREET 22542 | 28 | 6 Jan 2023 | Not started lapses in 3 years | Corca Dhuibhne |
| Church Road 2560172 | 27 | 12 Mar 2026 | Not started lapses in 4 years | Listowel |
| TRALEE BAY AND WETLANDS ECO AND ACTIVITY CENTRE 23251 | 25 | 7 Jun 2023 | Not started lapses in 2 years | Tralee |
| CLANMAURICE 2383 | 19 | 22 Feb 2024 | Not started lapses in 2 years | Listowel |
| Commons East 2561224 | 18 | 13 Oct 2026 | Not started lapses in 5 years | Tralee |
| Ballymacassy Main Street 2460922 | 18 | 23 Dec 2025 | Not started lapses in 4 years | Listowel |
| Scrahane 2460277 | 14 | 2 Aug 2024 | Not started lapses in 3 years | Killarney |
| NO. 10 BASIN ROAD/RAE STREET BUNGALOWS 22523 | 13 | 2 Mar 2023 | Not started lapses within a year | Tralee |
| SHRONEDARRAGH 2521 | 12 | 26 Feb 2026 | Not started lapses in 4 years | Killarney |
| Bellview Woods 2560737 | 12 | 19 Feb 2026 | Not started lapses in 4 years | Killarney |
| SANDHILL ROAD 25103 | 12 | 24 Oct 2025 | Not started lapses in 4 years | Listowel |
| Carhan Road 2460875 | 10 | 6 Nov 2025 | Not started lapses in 4 years | Kenmare |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KERRY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.