7,709 homes in 129 sites of 10 or more have been granted permission in Kildare since 2021. A commencement notice was lodged for 48% of them. 3,817 still have a live permission and no start; 1,127 of those lapse within a year, and 46 have already lapsed.

7,709
homes permitted · 129 sites
48%
started · 3,722 homes
3,817
not started · live permission
1,127
lapse within 12 months
46
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 8

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Maynooth141,62013%1,353148—
Newbridge201,08313%93759610
Naas301,81556%75738336
Kildare241,01157%411——
Clane1442067%138——
Athy1252775%134——
Celbridge736669%76——
Leixlip886799%11——

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021746241%24626
2022201,23724%92110
20231672067%23110
2024331,83494%104—
2025331,55747%799—
2026201,89916%1,516—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 50% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Briargate Developments Newbridge Limited23290%329—
The Land Development Agency12190%219—
Lagan Homes South Salt Limited11640%164—
Cairn Homes11480%148—
Alchemy Homes Development (Kilcullen) Limited11250%125—
Ladas Property Company Limited11150%115—
Glan Developments1980%98—
Eurkon (Kildare) Limited1880%88—
Seattle Construction Limited1760%76—
David Walsh Homes Limited1740%74—
Killross Properties Limited37713%67—
Kilcullenbridge Developments Limited1670%67—
Tapeford Limited1580%58—
Balyna Hotel Limited1540%54—
Debussy Properties Limited216470%50—
Nua Healthcare Services Limited1500%50—
Clúid Housing1340%34—
Kestorra Limited24745%26—
O’Flynn Construction (Dublin) Limited1250%25—
Mayra Homes Limited1200%20—
Clonmel Enterprises Limited1160%16—
MA Tudor Investments Limited1140%14—
Andrews Construction Limited1140%14—
Ascot Construction Limited1120%12—
Elmendorf Limited1110%11—
Resource Five Limited1100%10—
Cairn Homes Properties Limited2380100%0—
Westar Homes Limited2291100%0—
Ballymore Land Limited3187100%0—
Randelswood Holdings Limited1172100%0—

Work started 75 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
“Harpur Lane” 246005524329 Apr 2024Started notice 16 Sept 2024Leixlip
Leixlip Demesne 2351323718 Dec 2023Started notice 9 Feb 2024Leixlip
Devoy Quarter 2393117215 Jan 2024Started notice 7 Feb 2024Naas
Westfield 2144415510 Sept 2021Started notice 21 Oct 2021Easton
West Naas 256051515218 Aug 2025Started notice 23 Sept 2025Naas
Naas West 2394213919 Jan 2024Started notice 20 Mar 2024Naas
“Leixlip Gate” in the townlands of Kilmacredock Upper and Ca 236048513717 Jul 2024Started notice 16 Sept 2024Leixlip
Magee Quarter 256146613631 Mar 2026Started notice 27 Jul 2026Kildare
Shackleton Road 24604971324 Sept 2024Started notice 23 Sept 2024Celbridge
Prosperous Road 2397211429 May 2024Started notice 16 Sept 2024Clane
Branganstown East 256000310722 Oct 2025Started notice 25 Sept 2026Maynooth
Blackparks 236561029 Feb 2024Started notice 20 Sept 2024Athy
Tomard 241129122 Sept 2025Started notice 26 Feb 2026Athy
Whitelands East 2110338728 Jun 2023Started notice 20 Sept 2024Kildare
Stonehaven Phase 2 24610857227 May 2025Started notice 29 May 2025Oakfield
Stonehaven Phase 1B 24600296923 Apr 2024Started notice 24 Apr 2024Oakfield
Ferns Bridge 211729677 Dec 2022Started notice 11 Apr 2024Kildare
An Post Depot 23750658 Nov 2024Started notice 23 Dec 2024Naas
Millview Demesne 23602296525 Jun 2024Started notice 19 Dec 2025Kildare
Townland of Kildare and Whitesland East, Kildare Town 25602746028 Jan 2026Started notice 29 Jul 2026Kildare
Oldtown 24603715722 Oct 2025Started notice 20 Mar 2026Celbridge
Tipper Road 23749558 Nov 2024Started notice 23 Dec 2024Naas
Kilmalum 211606559 Sept 2022Started notice 29 Mar 2024Naas
Shanrath 2460683484 Dec 2024Started notice 27 Dec 2024Athy
Oldtown Demesne 23794822 May 2023Started notice 30 Nov 2023Naas
Stonehaven Phase 3 25613154628 Jul 2026Started notice 21 Jul 2026Oakfield
Railpark 211554613 Feb 2024Started notice 18 Sept 2024Maynooth
Droichead Nua 24604384520 Jan 2025Started notice 20 Dec 2024Newbridge
Kilbeg 23600634429 Feb 2024Started notice 5 Sept 2024Athy
Eascanrath Brook 232014118 Dec 2023Started notice 30 Jun 2025Suncroft
Tomard 241113822 Sept 2025Started notice 27 Feb 2026Athy
Curryhills 2211353411 Apr 2024Started notice 22 Sept 2026Prosperous
Capdoo 2114003415 Mar 2022Started notice 27 Jul 2022Clane
Droichead Nua 24604123220 Jan 2025Started notice 20 Dec 2024Newbridge
Station Road 216553120 Jan 2022Started notice 10 Jun 2022Leixlip
Retronix Semiconductor Factory 2310572816 Dec 2024Started notice 8 May 2026Donaghcumper
Green Lane 228792826 Jan 2023Started notice 30 Jun 2023Leixlip
Leixlip Gate Leixlip South 2461073252 Apr 2025Started notice 16 Jun 2025Leixlip
Marsville House 23986259 Jul 2024Started notice 12 Aug 2024Kill
Oldgrange 23602962218 Jun 2024Started notice 4 Dec 2025Kildare
Glencarrig House 222210522214 Mar 2023Started notice 24 Apr 2024Celbridge
Millview Demesne 24611832122 Apr 2025Started notice 8 Jul 2026Kildare
Ballitore 2460189211 Nov 2024Started notice 5 Feb 2025Ballitore
Railpark 211562113 Feb 2024Started notice 18 Sept 2024Maynooth
Fasagh 25609192015 Jul 2026Started notice 19 Aug 2026Athy
Cooleragh 2360353202 Oct 2024Started notice 2 Dec 2024Coolearagh
Rathbride Road 23600502022 Aug 2024Started notice 16 Sept 2024Kildare
Beechmount 21481926 Jan 2022Started notice 15 Aug 2023Newbridge
Doctor's Lane 24611391813 Oct 2025Started notice 4 Aug 2026Maynooth
Oldtown Demesne 2117401828 Nov 2022Started notice 5 Jan 2023Naas
Sallins Road 2460485174 Nov 2024Started notice 10 Aug 2026Alexandra Bridge
Kildare Road 236731725 Jun 2024Started notice 16 Sept 2025Kildare
Mullen Park 25614961621 May 2026Started notice 17 Jul 2026Maynooth
Rickardstown 24604461624 Jan 2025Started notice 24 Feb 2025Byrnes Crossroads
Fuller's Court Road 221166163 Jul 2023Started notice 6 Dec 2023Ballitore
Cois Abhainn 216921628 Jun 2022Started notice 23 Nov 2022Alexandra Bridge
Dublin Road 21575163 Mar 2022Started notice 26 Jan 2024Naas
Old Odlum’s Mill Site 221101515 May 2024Started notice 2 May 2025Naas
Ferns Bridge 25606581423 Mar 2026Started notice 8 Jun 2026Kildare
Sallins Wharf Osberstown Drive and Sallins Pier 2461359148 Dec 2025Started notice 30 Oct 2026Naas

1–60 of 75Next 60 →

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILDARE' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 22 Oct 2026, 23:33
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.022 Oct 2026, 23:33open
An Coimisiún Pleanála case listCC BY 4.022 Oct 2026, 23:33open
Building Control Management System commencement noticesCC BY 4.022 Oct 2026, 23:33open

Recomputed weekly from the store; last built 22 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness