PlanningRegister.ie
Permitted, not started · Kildare · grants of 10+ homes since 2017

Kildare: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

14,572 homes in 249 sites of 10 or more have been granted permission in Kildare since 2017. A commencement notice was lodged for 42% of them. 4,364 still have a live permission and no start; 765 of those lapse within a year, and 3,625 have already lapsed.

14,572
homes permitted · 249 sites
42%
started · 6,178 homes
4,364
not started · live permission
765
lapse within 12 months
3,625
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 4

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Maynooth343,06035%1,244148694
Naas462,79244%61711947
Leixlip141,42544%243—551
Celbridge1590333%170—437

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017824242%0140
2018282,05443%01,162
2019341,77544%268724
2020402,66548%01,383
2021211,16329%294196
2022211,32329%93210
20231773547%38110
2024311,58175%400—
2025321,54342%870—
2026171,49115%1,219—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 74% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Briargate Developments Newbridge Limited23290%329—
Ardstone Homes Limited61,2251%268947
Cairn Homes Properties Limited51,04550%243283
The Land Development Agency12190%219—
Lagan Homes South Salt Limited11640%164—
Oakway Homes321529%152—
Cairn Homes11480%148—
Pousterle Limited11360%136—
Alchemy Homes Development (Kilcullen) Limited11250%125—
Ladas Property Company Limited11150%115—
Glan Developments1980%98—
Eurkon (Kildare) Limited1880%88—
Thoval Properties Limited1870%87—
Seattle Construction Limited1760%76—
David Walsh Homes Limited1740%74—
Killross Properties Limited510726%6712
Kilcullenbridge Developments Limited1670%67—
Tapeford Limited317867%58—
O'Flynn Construction Co. Unlimited Company22270%57170
Mountkerry Ventures Limited1550%55—
Balyna Hotel Limited1540%54—
Debussy Properties Limited1500%50—
Nua Healthcare Services Limited1500%50—
Springwood Limited26627%48—
Heathcote Holdings Limited1400%40—
Clúid Housing1340%34—
Masonbrook Holdings Limited627083%2916
Moortrim Limited1280%28—
Kestorra Limited24745%26—
O’Flynn Construction (Dublin) Limited1250%25—

Work started 130 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Mariavilla 183012303823 Jul 2018Started notice 4 Feb 2019Maynooth
Leixlip Demesne 2351323718 Dec 2023Started notice 11 Oct 2024Leixlip
Greyabbey 175232076 Mar 2018Started notice 19 Sept 2022Armour Bridge
South Green 1776418714 Jan 2020Started notice 30 Jul 2021Kildare
Devoy Quarter 2393117215 Jan 2024Started notice 7 Feb 2024Naas
Westfield 2144415510 Sept 2021Started notice 21 Oct 2021Easton
West Naas 256051515218 Aug 2025Started notice 23 Sept 2025Naas
“Leixlip Gate” in the townlands of Kilmacredock Upper and Ca 236048513717 Jul 2024Started notice 16 Sept 2024Leixlip
Magee Quarter 256146613631 Mar 2026Started notice 27 Jul 2026Kildare
Shackleton Road 24604971324 Sept 2024Started notice 23 Sept 2024Celbridge
Branganstown East 256000310722 Oct 2025Started notice 25 Sept 2026Maynooth
Blackparks 236561029 Feb 2024Started notice 20 Sept 2024
Glebelands 1931910031 Jul 2019Started notice 31 Oct 2019
Clonmullin & Gallowshill 18921983 Sept 2019Started notice 22 Apr 2024
Branganstown 2097956 Jul 2020Started notice 15 Jul 2020Maynooth
Greenfield 187629531 Jan 2019Started notice 13 Jan 2020Maynooth
Tomard 241129122 Sept 2025Started notice 26 Feb 2026
Tinnycross 197509130 Jun 2020Started notice 10 Jun 2021Ballymore Eustace
Blackrath and Athgarvan 19117881 Apr 2020Started notice 20 Oct 2023
Coneyboro 2012748710 Feb 2022Started notice 10 Mar 2024
Clonmullen and Gallowshill 192348611 Aug 2020Started notice 25 Mar 2025
Greenfield 187618431 Jan 2019Started notice 24 Apr 2019Maynooth
Ballymore Eustace East 1813478227 Aug 2019Started notice 19 Feb 2020Ballymore Eustace
Loughlion 19961793 Feb 2020Started notice 25 Mar 2020Hawk Hill
Oldtown Mill, Celbridge 1912827521 Jul 2020Started notice 16 Nov 2020Celbridge
Stonehaven Phase 2 24610857227 May 2025Started notice 29 May 2025Oakfield
Stonehaven Phase 1B 24600296923 Apr 2024Started notice 24 Apr 2024Oakfield
New Road 201516929 Jul 2020Started notice 14 Feb 2022Maynooth
Ferns Bridge 211729677 Dec 2022Started notice 11 Apr 2024
Ferns Bridge 199976716 Jul 2020Started notice 24 Sept 2020
Hartwell Road 19885661 Apr 2020Started notice 19 Oct 2020Naas
An Post Depot 23750658 Nov 2024Started notice 23 Dec 2024Naas
Millview Demesne 23602296525 Jun 2024Started notice 19 Dec 2025
Western Side of Barberstown Road 175656521 Nov 2017Started notice 7 May 2019Straffan
Tipper Road 23749558 Nov 2024Started notice 23 Dec 2024Naas
Kilmalum 211606559 Sept 2022Started notice 29 Mar 2024Naas
Cooleragh East 188515214 May 2019Started notice 10 Nov 2021Coolearagh
Allenwood Middle 20580511 Sept 2020Started notice 29 Sept 2020
Riverside Manor 1910005023 Sept 2020Started notice 7 Jun 2021Kilcullen
Johnstown 18585494 Feb 2019Started notice 13 May 2019Naas
Shanrath 2460683484 Dec 2024Started notice 27 Dec 2024
Stonehaven Phase 3 25613154628 Jul 2026Started notice 15 Sept 2026Oakfield
Railpark 211554613 Feb 2024Started notice 18 Sept 2024Maynooth
Droichead Nua 24604384520 Jan 2025Started notice 23 Dec 2024
Brownstown 18417457 Dec 2018Started notice 22 Jan 2020Brownstown
Kilbeg 23600634429 Feb 2024Started notice 5 Sept 2024
Rathangan Demesne 2014644228 Apr 2021Started notice 17 Aug 2022
Eascanrath Brook 232014118 Dec 2023Started notice 30 Jun 2025Suncroft
Tomard 241113822 Sept 2025Started notice 27 Feb 2026
Brockagh 1711533822 Jan 2018Started notice 12 Feb 2018Quigley's Bridge
Allenwood Middle 171203727 Nov 2017Started notice 9 Mar 2020Bond Bridge
Downings North 19483619 Dec 2019Started notice 20 Sept 2021Prosperous
Aughamore 183843625 Oct 2018Started notice 2 Jul 2019Clane
Elsmore 17853352 Feb 2018Started notice 1 Aug 2018Naas
Curryhills 2211353411 Apr 2024Started notice 22 Sept 2026Prosperous
Capdoo 2114003415 Mar 2022Started notice 10 Oct 2022
Downings North 2010803414 Dec 2020Started notice 22 Dec 2022Prosperous
Fuller's Court Road 201563330 Apr 2021Started notice 7 Oct 2021Ballitore
Bellingsfield 191783324 Jul 2019Started notice 19 Nov 2019Naas
Droichead Nua 24604123220 Jan 2025Started notice 23 Dec 2024

1–60 of 130Next 60 →

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILDARE' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.