Permitted, not started · Kilkenny · grants of 10+ homes since 2017

Kilkenny: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

3,149 homes in 95 sites of 10 or more have been granted permission in Kilkenny since 2017. A commencement notice was lodged for 52% of them. 1,212 still have a live permission and no start; 322 of those lapse within a year, and 182 have already lapsed.

3,149
homes permitted · 95 sites
52%
started · 1,627 homes
1,212
not started · live permission
322
lapse within 12 months
182
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
201722560%010
2018713580%027
20191232468%0104
2020833546%16812
20211243277%8117
202259723%75—
2023941994%1212
20241763541%374—
20251140823%298—
2026123397%204—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 78% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cairn Homes Properties Limited230843%177—
Daly's Hill Limited11330%133—
Kingscroft Developments Limited11300%130—
Glenveagh Homes Limited214859%60—
Fox Meadow Homes Limited2600%60—
Noreside Construction Limited1540%54—
Finn Homes Limited2520%3517
Greenstripe Limited1350%35—
Corestone 4 Limited1350%35—
Art Generation Limited1290%29—
Michael Doyle Civil Engineering Limited29470%28—
Wallace Contracting Limited1280%28—
Minson Property Limited1230%23—
Sophia Housing Association CLG1220%22—
Creanross Limited1220%22—
RCC Care Limited1220%22—
Canview Limited1210%21—
Hansa Properties Limited1160%16—
Althorp Property Holdings Limited1120%12—
Denis Treacy Construction Limited1110%11—
Wisteria Developments Limited4181100%0—
Ormonde Homes Limited3172100%0—
Madill Property Limited4134100%0—
Hebron Ventures Limited3107100%0—
Kevin Moore Building Contractor Limited153100%0—
AMC Properties Limited149100%0—
PATRICK TALLIS and Company143100%0—
Dunmore Property Development Co Limited140100%0—
Bellerin 2 Limited1400%040
Bolton Homes Limited135100%0—

Lapses within a year 6 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Wetland Callan Road 236058017715 Mar 2024Lapsing lapses in 5 months
Granges Road 21464608 Nov 2021Lapsing lapses in 1 months
Tullaroan Road 22892916 Sept 2022Lapsing lapses within a year
Main Street Togher Road 20685218 Dec 2021Lapsing lapses in 2 months
Barrowmount Road 217361915 Aug 2022Lapsing lapses in 11 months
66 Upper Patrick Street 216091626 Jan 2022Lapsing lapses in 4 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILKENNY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness