PlanningRegister.ie
Permitted, not started · Kilkenny · grants of 10+ homes since 2021

Kilkenny planning permission: the homes nobody has started

Data updated 30 Oct 2026 · register lag up to 7 days · sources & freshness

2,173 homes in 58 sites of 10 or more have been granted permission in Kilkenny since 2021. A commencement notice was lodged for 49% of them. 993 still have a live permission and no start; 272 of those lapse within a year, and 55 have already lapsed.

2,173
homes permitted · 58 sites
49%
started · 1,057 homes
993
not started · live permission
272
lapse within 12 months
55
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 4

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Kilkenny321,52053%58925355
Piltown1028732%195——
Castlecomer1023126%17019—
Callan-Thomastown613571%39——

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021529465%6043
202248659%35—
2023941994%1212
20241763548%332—
20251140823%298—
2026123318%256—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 27 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 74% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cairn Homes Properties Limited230843%177—
Kingscroft Developments Limited11300%130—
Glenveagh Homes Limited214859%60—
Noreside Construction Limited1540%54—
Greenstripe Limited1350%35—
FINN HOMES Limited1350%35—
Michael Doyle Civil Engineering Limited1280%28—
Wallace Contracting Limited1280%28—
Minson Property Limited1230%23—
RCC Care Limited1220%22—
Sophia Housing Association CLG1220%22—
Creanross Limited1220%22—
Hansa Properties Limited1160%16—
Althorp Property Holdings Limited1120%12—
Wisteria Developments Limited4181100%0—
Ormonde Homes Limited3172100%0—
Fox Meadow Homes Limited260100%0—
Kevin Moore Building Contractor Limited153100%0—
Signbrook Limited1430%043
PATRICK TALLIS and Company143100%0—
Digital Wren RE Limited135100%0—
Hadview Taverns Limited133100%0—
Hebron Ventures Limited127100%0—
Ayrfield Homes Limited125100%0—
Tallywood Limited124100%0—
OLI Developments Limited114100%0—
Oakmane Limited1120%012

Permission, no start 27 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Wetland Callan Road 236058017715 Mar 2024Lapsing lapses in 4 monthsKilkenny
William Robertson Way 256060013012 Dec 2025Not started lapses in 2 yearsKilkenny
Granges Road 21464608 Nov 2021Lapsing lapses within a monthKilkenny
Abbeygate 26600305424 Jul 2026Not started lapses in 5 yearsPiltown
Noreside Site 24603075427 Jun 2025Not started lapses in 4 yearsKilkenny
Abbeygate 2560570431 May 2026Not started lapses in 4 yearsPiltown
Deansground 24603504023 Apr 2025Not started lapses in 4 yearsKilkenny
Glanbia Site 23606103525 Oct 2024Not started lapses in 3 yearsCastlecomer
OAKRIDGE BELMOUNT 23605383515 Oct 2024Not started lapses in 3 yearsPiltown
Moatpark 24602412921 Jan 2025Not started lapses in 3 yearsCastlecomer
Margaret’s Fields 2660523289 Oct 2026Not started lapses in 5 yearsKilkenny
Lousybush Lane & Bishops Lough 25605572823 Feb 2026Not started lapses in 4 yearsKilkenny
Abbeylands 24604952821 Jan 2025Not started lapses in 4 yearsPiltown
O’Loughlin Road 25604862423 Apr 2026Not started lapses in 5 yearsKilkenny
Ogenty 2460234237 Nov 2024Not started lapses in 3 yearsCastlecomer
RCC Care Ltd 25603262216 Feb 2026Not started lapses in 4 yearsPiltown
Saint John of God Convent 23605712217 Jul 2024Not started lapses in 3 yearsKilkenny
Grenan 23600522212 Feb 2024Not started lapses in 3 yearsCallan-Thomastown
Barrack Street 2560447201 May 2026Not started lapses in 4 yearsCastlecomer
Barrowmount Road 217361915 Aug 2022Lapsing lapses in 9 monthsCastlecomer
Dublin Road 232161813 Sept 2024Not started lapses in 3 yearsCastlecomer
Millbanks 24605041712 Sept 2025Not started lapses in 4 yearsCallan-Thomastown
66 Upper Patrick Street 216091626 Jan 2022Lapsing lapses in 3 monthsKilkenny
'An Choill Rua' 25606411418 Sept 2026Not started lapses in 5 yearsCastlecomer
Narrabaun South 25607701324 Jul 2026Not started lapses in 5 yearsPiltown
Togher Crescent 227411219 Jan 2023Not started lapses in 2 yearsCastlecomer
Rath Ullord 25605741024 Feb 2026Not started lapses in 5 yearsKilkenny

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILKENNY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 30 Oct 2026, 10:12
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.030 Oct 2026, 10:12open
An Coimisiún Pleanála case listCC BY 4.030 Oct 2026, 10:12open
Building Control Management System commencement noticesCC BY 4.030 Oct 2026, 10:12open

Recomputed weekly from the store; last built 30 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness

Kilkenny planning permission: 993 homes not started · Planning Register