Permitted, not started · Kilkenny · grants of 10+ homes since 2017

Kilkenny: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

3,135 homes in 94 sites of 10 or more have been granted permission in Kilkenny since 2017. A commencement notice was lodged for 52% of them. 1,198 still have a live permission and no start; 322 of those lapse within a year, and 182 have already lapsed.

3,135
homes permitted · 94 sites
52%
started · 1,627 homes
1,198
not started · live permission
322
lapse within 12 months
182
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
201722560%010
2018713580%027
20191232468%0104
2020833546%16812
20211243277%8117
202259723%75
2023941994%1212
20241763541%374
20251140823%298
2026113258%190

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 93% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cairn Homes Properties Limited230843%177
Daly's Hill Limited11330%133
Kingscroft Developments Limited11300%130
Abbeygate Properties Limited2970%97
Glenveagh Homes Limited214859%60
Fox Meadow Homes Limited2600%60
Noreside Construction Limited1540%54
Minson Property Limited2400%40
Gemstack Limited1400%40
Finn Homes Limited2520%3517
Greenstripe Limited1350%35
Corestone 4 Limited1350%35
Althorp Property Holdings Limited2320%32
Art Generation Limited1290%29
Michael Doyle Civil Engineering Limited29470%28
Wallace Contracting Limited1280%28
Creanross Limited1220%22
RCC Care Limited1220%22
Sophia Housing Association CLG1220%22
Canview Limited1210%21
Hansa Properties Limited1160%16
Eriglenda Holdings Limited1130%13
Hebron Ventures Limited513792%11
Denis Treacy Construction Limited1110%11
Madill Property Limited514493%10
Ormonde Homes Limited422277%0
Wisteria Developments Limited4181100%0
Kevin Moore Building Contractors Limited154100%0
Kevin Moore Building Contractor Limited153100%0
AMC Properties Limited149100%0

Permission, no start 31 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Wetland Callan Road 236058017715 Mar 2024Lapsing lapses in 6 months
Circular Road 1988713315 Jul 2020Not started lapses in 5 years
William Robertson Way 256060013012 Dec 2025Not started lapses in 2 years
Granges Road 21464608 Nov 2021Lapsing lapses in 2 months
Abbeygate 26600305424 Jul 2026Not started lapses in 5 years
Noreside Site 24603075427 Jun 2025Not started lapses in 4 years
Abbeygate 2560570431 May 2026Not started lapses in 5 years
Deansground 24603504023 Apr 2025Not started lapses in 4 years
Glanbia Site 23606103525 Oct 2024Not started lapses in 3 years
OAKRIDGE BELMOUNT 23605383515 Oct 2024Not started lapses in 3 years
Cois na Bearu 195943517 Jul 2020Not started lapses in 2 years
Tullaroan Rd 24600903115 Jul 2024Not started lapses in 3 years
Moatpark 24602412921 Jan 2025Not started lapses in 3 years
Tullaroan Road 22892916 Sept 2022Lapsing lapses within a year
Lousybush Lane & Bishops Lough 25605572823 Feb 2026Not started lapses in 4 years
Abbeylands 24604952821 Jan 2025Not started lapses in 4 years
Ogenty 2460234237 Nov 2024Not started lapses in 3 years
RCC Care Ltd 25603262216 Feb 2026Not started lapses in 4 years
Saint John of God Convent 23605712217 Jul 2024Not started lapses in 3 years
Grenan 23600522212 Feb 2024Not started lapses in 4 years
Main Street Togher Road 20685218 Dec 2021Lapsing lapses in 3 months
Barrack Street 2560447201 May 2026Not started lapses in 5 years
Barrowmount Road 217361915 Aug 2022Lapsing lapses in 11 months
Dublin Road 232161813 Sept 2024Not started lapses in 3 years
Millbanks 24605041712 Sept 2025Not started lapses in 4 years
66 Upper Patrick Street 216091626 Jan 2022Lapsing lapses in 4 months
Narrabaun South 25607701324 Jul 2026Not started lapses in 5 years
Togher Crescent 227411219 Jan 2023Not started lapses in 3 years
Maudlin Street and Maudlin Court 23601041128 Feb 2024Not started lapses in 2 years
Margaret's Fields 2110331123 Mar 2022Not started lapses in 2 years
Rath Ullord 25605741024 Feb 2026Not started lapses in 5 years

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILKENNY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.