PlanningRegister.ie
Permitted, not started · Kilkenny · grants of 10+ homes since 2021

Kilkenny planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

2,173 homes in 58 sites of 10 or more have been granted permission in Kilkenny since 2021. A commencement notice was lodged for 49% of them. 923 still have a live permission and no start; 212 of those lapse within a year, and 115 have already lapsed.

2,173
homes permitted · 58 sites
49%
started · 1,067 homes
923
not started · live permission
212
lapse within 12 months
115
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 4

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Kilkenny321,52054%519193115
Piltown1028732%195——
Castlecomer1023126%17019—
Callan-Thomastown613571%39——

By year granted

Granted inSitesHomesStartedNot startedLapsed
2021529465%0103
202248659%35—
2023941994%1212
20241763548%332—
20251140823%298—
20261233111%246—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 27 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 74% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Cairn Homes Properties Limited230843%177—
Kingscroft Developments Limited11300%130—
Noreside Construction Limited1540%54—
FINN HOMES Limited1350%35—
Greenstripe Limited1350%35—
Michael Doyle Civil Engineering Limited1280%28—
Wallace Contracting Limited1280%28—
Minson Property Limited1230%23—
RCC Care Limited1220%22—
Sophia Housing Association CLG1220%22—
Creanross Limited1220%22—
Hansa Properties Limited1160%16—
Althorp Property Holdings Limited1120%12—
Wisteria Developments Limited4181100%0—
Ormonde Homes Limited3172100%0—
Glenveagh Homes Limited214859%060
Fox Meadow Homes Limited260100%0—
Kevin Moore Building Contractor Limited153100%0—
Signbrook Limited1430%043
PATRICK TALLIS and Company143100%0—
Digital Wren RE Limited135100%0—
Hadview Taverns Limited133100%0—
Hebron Ventures Limited127100%0—
Ayrfield Homes Limited125100%0—
Tallywood Limited124100%0—
OLI Developments Limited114100%0—
Oakmane Limited1120%012

Work started 28 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Poulgour Road Kilkenny 236003713128 Jul 2023Started notice 30 Sept 2024Kilkenny
Townslands of Wetland and Poulgour 23600069230 Jun 2023Started notice 5 Feb 2024Kilkenny
Granges Road 21384888 Nov 2021Started notice 24 Feb 2023Kilkenny
Bishops Lough 24601926811 Sept 2024Started notice 30 Sept 2024Kilkenny
Loughmacask 23602975622 Dec 2023Started notice 18 Mar 2024Kilkenny
CLOGHABRODY 23600885429 Jan 2024Started notice 16 Sept 2024Callan-Thomastown
Ayrfield 212525312 Nov 2021Started notice 16 Jan 2024Kilkenny
Poulgour 213485015 Oct 2021Started notice 21 Dec 2021Kilkenny
Bohercrussia Street 24601834312 Jul 2024Started notice 30 Jun 2026Castlecomer
Loughmacask 25602033511 Jul 2025Started notice 13 Apr 2026Kilkenny
Rockshire Road 23117357 Dec 2023Started notice 27 Oct 2025Piltown
Archersleas 2331334 Jul 2023Started notice 8 Aug 2023Kilkenny
Tullaroan Rd 24600903115 Jul 2024Started notice 6 Sept 2024Kilkenny
Poulgour 23601963011 Sept 2023Started notice 23 Oct 2023Kilkenny
Tullaroan Road 22892916 Sept 2022Started notice 25 May 2023Kilkenny
Main Street & New Road 23605152718 Jun 2024Started notice 24 Nov 2025Piltown
Ayrfield 2560413252 Mar 2026Started notice 5 Aug 2026Kilkenny
Hebron Industrial Estate Road 1 25602792412 Aug 2025Started notice 20 Apr 2026Kilkenny
Loughmacask 24601502224 Jun 2024Started notice 30 Sept 2024Kilkenny
Junction of College Road 215772218 Feb 2022Started notice 31 Jan 2024Kilkenny
Waterford Road 24601671928 Jan 2025Started notice 23 Sept 2026Kilkenny
Friary Walk 23605161927 Sept 2024Started notice 6 Jan 2025Callan-Thomastown
Lumper Lane and New Road 23601321820 Dec 2023Started notice 22 Apr 2024Castlecomer
Abbeylands 2360578163 Sept 2024Started notice 27 Sept 2024Piltown
Arbourmount 24603081415 Apr 2025Started notice 9 Dec 2025Piltown
Green Street 2360286128 Apr 2024Started notice 18 Nov 2024Callan-Thomastown
Maudlin Street and Maudlin Court 23601041128 Feb 2024Started notice 21 Sept 2026Callan-Thomastown
Rath Ullord 25605741024 Feb 2026Started notice 5 Nov 2026Kilkenny

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'KILKENNY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness