Laois: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
4,782 homes in 108 sites of 10 or more have been granted permission in Laois since 2017. A commencement notice was lodged for 51% of them. 1,623 still have a live permission and no start; 226 of those lapse within a year, and 689 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 1 | 59 | 100% | 0 | — |
| 2018 | 12 | 420 | 66% | 0 | 144 |
| 2019 | 12 | 535 | 69% | 23 | 142 |
| 2020 | 9 | 289 | 20% | 17 | 215 |
| 2021 | 12 | 375 | 52% | 113 | 67 |
| 2022 | 11 | 521 | 70% | 158 | — |
| 2023 | 13 | 682 | 44% | 258 | 121 |
| 2024 | 11 | 608 | 57% | 263 | — |
| 2025 | 17 | 809 | 45% | 441 | — |
| 2026 | 10 | 484 | 21% | 350 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 64% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Bircrest Limited | 7 | 449 | 36% | 210 | 79 |
| Whitehorse Developments TA Capital Homes | 2 | 107 | 0% | 107 | — |
| Dargan Woods Devco Limited | 2 | 114 | 23% | 88 | — |
| Tullyagan Residential Limited | 1 | 86 | 0% | 86 | — |
| The Maltings & Granary Limited | 5 | 151 | 45% | 83 | — |
| Hebron Mooncoin Limited | 1 | 71 | 0% | 71 | — |
| A-Rated New Homes Limited | 1 | 44 | 0% | 44 | — |
| David Walsh Homes Limited | 5 | 248 | 83% | 42 | — |
| Brook Advantage Limited | 2 | 63 | 56% | 28 | — |
| Cubic Housing Limited | 3 | 57 | 54% | 26 | — |
| Graham Developments | 1 | 23 | 0% | 23 | — |
| Vesta Construction | 1 | 18 | 0% | 18 | — |
| Twomilehouse Construction Limited | 2 | 58 | 71% | 17 | — |
| Superior Formwork Limited | 2 | 54 | 70% | 16 | — |
| Furey Consulting Engineers Limited | 1 | 14 | 0% | 14 | — |
| Nyquist Property Limited | 2 | 20 | 0% | 10 | 10 |
| Marina Quarter Limited | 1 | 175 | 100% | 0 | — |
| Kingscroft Developments Limited | 3 | 140 | 100% | 0 | — |
| Boderg Developments Limited | 1 | 121 | 0% | 0 | 121 |
| Aston Homes Limited | 2 | 99 | 100% | 0 | — |
| Randelswood Holdings Limited | 1 | 97 | 100% | 0 | — |
| Thomas Kelly & Sons Group comprising O'Ceallaigh Westfield Limited&Thomas Kelly & Sons Limited | 1 | 95 | 100% | 0 | — |
| Alder Residential Limited | 1 | 79 | 100% | 0 | — |
| Langville Properties Limited | 1 | 72 | 100% | 0 | — |
| Dunamaise Homes Designated Activity Company | 2 | 72 | 50% | 0 | 36 |
| Dunkeel Limited | 1 | 71 | 100% | 0 | — |
| Owenass Developments Ireland Limited | 2 | 67 | 0% | 0 | 67 |
| Creekberry Limited | 1 | 62 | 100% | 0 | — |
| Bridgedale Homes Limited | 1 | 59 | 100% | 0 | — |
| Garryduff Properties Limited | 1 | 48 | 0% | 0 | 48 |
Permission lapsed 19 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Foxburrow 2341 | 121 | 2 May 2023 | Lapsed lapsed 12 months ago | |
| Aghnaharna 19217 | 79 | 5 Jul 2019 | Lapsed lapsed 3 years ago | |
| Cullenbeg Park 19558 | 68 | 5 Oct 2020 | Lapsed lapsed 12 months ago | |
| Ballickmoyler road 18318 | 63 | 22 Jan 2019 | Lapsed lapsed 2 years ago | |
| Bellingham 18583 | 52 | 10 Dec 2018 | Lapsed lapsed 6 years ago | |
| Mountrath Road 19389 | 48 | 24 Aug 2020 | Lapsed lapsed 13 months ago | |
| Ballymorris Road 18129 | 44 | 13 Aug 2018 | Lapsed lapsed 14 months ago | |
| Dublin Road 20146 | 36 | 21 Sept 2020 | Lapsed lapsed 12 months ago | |
| Heathfield 19335 | 28 | 7 Jan 2020 | Lapsed lapsed 3 years ago | |
| Corrig Glen 19542 | 21 | 29 Jun 2020 | Lapsed lapsed 15 months ago | |
| Killeen Village 17499 | 20 | 6 Sept 2018 | Lapsed lapsed 3 years ago | |
| Raggetstown 20671 | 16 | 15 Mar 2021 | Lapsed lapsed 7 months ago | |
| Heywood 20289 | 16 | 5 Mar 2021 | Lapsed lapsed 7 months ago | |
| Kilcoke 18236 | 16 | 9 Jul 2018 | Lapsed lapsed 3 years ago | |
| Roselawn 20636 | 15 | 1 Mar 2021 | Lapsed lapsed 14 months ago | |
| Killeshin 19535 | 14 | 25 Nov 2020 | Lapsed lapsed 10 months ago | |
| Doírín Alaínn 17516 | 12 | 29 Aug 2018 | Lapsed lapsed 3 years ago | |
| Knocknamoe 20438 | 10 | 20 Jul 2021 | Lapsed lapsed 2 months ago | |
| Block A 20142 | 10 | 15 Mar 2021 | Lapsed lapsed 7 months ago |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LAOIS' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.