Laois: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
4,782 homes in 108 sites of 10 or more have been granted permission in Laois since 2017. A commencement notice was lodged for 51% of them. 1,623 still have a live permission and no start; 226 of those lapse within a year, and 689 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 1 | 59 | 100% | 0 | — |
| 2018 | 12 | 420 | 66% | 0 | 144 |
| 2019 | 12 | 535 | 69% | 23 | 142 |
| 2020 | 9 | 289 | 20% | 17 | 215 |
| 2021 | 12 | 375 | 52% | 113 | 67 |
| 2022 | 11 | 521 | 70% | 158 | — |
| 2023 | 13 | 682 | 44% | 258 | 121 |
| 2024 | 11 | 608 | 57% | 263 | — |
| 2025 | 17 | 809 | 45% | 441 | — |
| 2026 | 10 | 484 | 21% | 350 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 86% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Bircrest Limited | 8 | 543 | 29% | 304 | 79 |
| The Maltings & Granary Limited | 7 | 285 | 47% | 151 | — |
| Whitehorse Developments TA Capital Homes | 2 | 107 | 0% | 107 | — |
| JC Brenco Developments Limited | 1 | 98 | 0% | 98 | — |
| Dargan Woods Devco Limited | 2 | 114 | 23% | 88 | — |
| Tullyagan Residential Limited | 1 | 86 | 0% | 86 | — |
| Whitehorse Developments Limited T and A Capital Homes Limited | 1 | 82 | 0% | 82 | — |
| Hebron Mooncoin Limited | 1 | 71 | 0% | 71 | — |
| Werdna Limited | 1 | 58 | 0% | 58 | — |
| A-Rated New Homes Limited | 1 | 44 | 0% | 44 | — |
| David Walsh Homes Limited | 5 | 248 | 83% | 42 | — |
| Kingscroft Developments Limited | 4 | 178 | 79% | 38 | — |
| Brook Advantage Limited | 2 | 63 | 56% | 28 | — |
| Cubic Housing Limited | 4 | 106 | 75% | 26 | — |
| M&M Prime Holdings Limited | 1 | 26 | 0% | 26 | — |
| Graham Developments | 1 | 23 | 0% | 23 | — |
| Vesta Construction | 1 | 18 | 0% | 18 | — |
| Twomilehouse Construction Limited | 2 | 58 | 71% | 17 | — |
| Superior Formwork Limited | 2 | 54 | 70% | 16 | — |
| Ardain Developments Limited | 1 | 14 | 0% | 14 | — |
| Furey Consulting Engineers Limited | 1 | 14 | 0% | 14 | — |
| Solus Developments Limited | 1 | 11 | 0% | 11 | — |
| Nyquist Property Limited | 2 | 20 | 0% | 10 | 10 |
| Salzagold Limited | 1 | 210 | 100% | 0 | — |
| Marina Quarter Limited | 1 | 175 | 100% | 0 | — |
| Boderg Developments Limited | 1 | 121 | 0% | 0 | 121 |
| Aston Homes Limited | 3 | 109 | 91% | 0 | 10 |
| Randelswood Holdings Limited | 1 | 97 | 100% | 0 | — |
| Thomas Kelly & Sons Group comprising O'Ceallaigh Westfield Limited&Thomas Kelly & Sons Limited | 1 | 95 | 100% | 0 | — |
| Alder Residential Limited | 1 | 79 | 100% | 0 | — |
Permission, no start 38 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Rahin 2360015 | 98 | 16 Feb 2024 | Not started lapses in 4 years | |
| Summerhill 19727 | 94 | 15 Mar 2021 | Not started lapses within a year | |
| Leighlin Road 2460700 | 90 | 20 May 2025 | Not started lapses in 2 years | |
| Colliers Lane Ballyroan 2660112 | 88 | 7 Aug 2026 | Not started lapses in 5 years | |
| Summerhill Portlaoise 2260011 | 86 | 29 May 2023 | Not started lapses within a year | |
| Crossneen 233 | 82 | 3 Jan 2024 | Not started lapses in 2 years | |
| Lands located between Harpur’s Lane and Mountrath Road 2660008 | 76 | 31 Aug 2026 | Not started lapses in 5 years | |
| Portlaoise 2560386 | 74 | 24 Feb 2026 | Not started lapses in 4 years | |
| N80 Mountmellick Road Maryborough 2560293 | 71 | 18 Nov 2025 | Not started lapses in 4 years | |
| Harpur's Lane 22581 | 68 | 13 Nov 2023 | Lapsing lapses in 1 months | |
| Station Road 21384 | 58 | 8 Feb 2022 | Lapsing lapses in 5 months | |
| Aghnaharna 21853 | 55 | 14 Mar 2022 | Lapsing lapses in 6 months | |
| Green Mill Lane 2260005 | 49 | 28 Aug 2023 | Not started lapses in 2 years | |
| Ballacolla Road 2460167 | 47 | 21 Mar 2025 | Not started lapses in 4 years | |
| Ballylinan 2560768 | 46 | 19 May 2026 | Not started lapses in 5 years | |
| Portlaoise 2360350 | 45 | 13 Mar 2024 | Not started lapses in 2 years | |
| Radharc Na Sleibhte 2460714 | 44 | 2 Sept 2025 | Not started lapses in 4 years | |
| Cooltederry 2460265 | 38 | 18 Jul 2025 | Not started lapses in 4 years | |
| Portlaoise 2560387 | 36 | 24 Feb 2026 | Not started lapses in 4 years | |
| Block 5 2460623 | 36 | 28 Jan 2025 | Not started lapses in 3 years | |
| Meadows Way 2360289 | 30 | 23 Oct 2023 | Not started lapses in 2 years | |
| Rathmoyle 2460001 | 28 | 21 Jan 2025 | Not started lapses in 4 years | |
| Harpur’s Lane 2460056 | 28 | 27 Aug 2024 | Not started lapses in 2 years | |
| Dunnes Hardware 2460769 | 26 | 12 Aug 2025 | Not started lapses in 4 years | |
| Townparks 215 | 26 | 8 Feb 2022 | Lapsing lapses in 5 months | |
| Maryborough East 18302 | 23 | 18 Jun 2019 | Not started lapses in 3 years | |
| Rivendell 2145 | 19 | 26 Jan 2022 | Not started lapses in 2 years | |
| part of former Minch Norton Maltings 2151 | 19 | 2 Nov 2021 | Lapsing lapses in 1 months | |
| Main Street 2560285 | 18 | 19 May 2026 | Not started lapses in 5 years | |
| Leighlin Road 2460798 | 17 | 9 Sept 2025 | Not started lapses in 4 years | |
| Kilminchy 19712 | 17 | 21 Sept 2020 | Not started lapses in 2 years | |
| Derrymore Gardens 2560051 | 16 | 29 Apr 2025 | Not started lapses within a year | |
| Rossleighan 2460291 | 14 | 8 Jul 2025 | Not started lapses in 4 years | |
| Maryville House 2460422 | 14 | 28 Jan 2025 | Not started lapses in 3 years | |
| Errill 22677 | 14 | 2 Oct 2023 | Not started lapses in 2 years | |
| Meadows Fort 2660314 | 12 | 25 Aug 2026 | Not started lapses in 5 years | |
| 10 Main St 2259 | 11 | 21 Feb 2023 | Not started lapses within a year | |
| Block A Parkside 2460415 | 10 | 15 Oct 2024 | Not started lapses in 3 years |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LAOIS' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness