Meath: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
17,000 homes in 276 sites of 10 or more have been granted permission in Meath since 2017. A commencement notice was lodged for 49% of them. 5,068 still have a live permission and no start; 385 of those lapse within a year, and 2,511 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 3
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Ratoath | 82 | 5,651 | 34% | 2,806 | 52 | 452 |
| Ashbourne | 19 | 1,283 | 42% | 664 | — | 75 |
| Laytown Bettystown-Lea-7 | 58 | 3,372 | 46% | 304 | 201 | 1,203 |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 14 | 994 | 65% | 0 | 349 |
| 2018 | 24 | 1,637 | 43% | 205 | 723 |
| 2019 | 27 | 968 | 61% | 185 | 197 |
| 2020 | 26 | 2,138 | 53% | 43 | 960 |
| 2021 | 25 | 1,198 | 71% | 213 | 135 |
| 2022 | 36 | 1,141 | 58% | 237 | 57 |
| 2023 | 26 | 1,218 | 84% | 154 | 35 |
| 2024 | 33 | 1,665 | 87% | 191 | 29 |
| 2025 | 37 | 3,045 | 31% | 2,069 | 26 |
| 2026 | 28 | 2,996 | 13% | 1,771 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 91% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| John Connaughton Limited | 1 | 810 | 0% | 810 | — |
| Glenveagh Homes Limited | 15 | 1,118 | 20% | 365 | 409 |
| Beo Properties Limited | 1 | 364 | 0% | 364 | — |
| Castlethorn Construction Unlimited Company | 3 | 369 | 9% | 314 | 21 |
| McGarrell Reilly Homes | 6 | 379 | 17% | 283 | 33 |
| Kingscroft Developments Limited | 3 | 305 | 0% | 251 | — |
| Arnub Limited | 2 | 251 | 7% | 233 | — |
| Azra Property Company Limited | 1 | 211 | 0% | 211 | — |
| Rockmill Limited | 1 | 201 | 0% | 201 | — |
| Andrews Construction Limited | 4 | 374 | 50% | 186 | — |
| Carroll Estates Dunboyne Limited | 1 | 171 | 0% | 171 | — |
| Marshall Yards Development Company Limited | 2 | 260 | 50% | 130 | — |
| Cairn Homes Properties Limited | 6 | 602 | 80% | 123 | — |
| Orion Wave Limited | 1 | 98 | 0% | 98 | — |
| The Academy Street Partnership | 1 | 95 | 0% | 95 | — |
| Apolloseven Investments Limited | 2 | 111 | 36% | 71 | — |
| Carroll Estates (Dublin) Limited | 5 | 306 | 39% | 56 | 130 |
| Aspect Houses (ADC) Limited | 1 | 56 | 0% | 56 | — |
| Rockture 1 Limited | 2 | 147 | 0% | 51 | 96 |
| Leinster Land Developments Limited | 1 | 43 | 0% | 43 | — |
| Rycroft Living Limited | 1 | 40 | 0% | 40 | — |
| Indus Properties Limited | 1 | 37 | 0% | 37 | — |
| Poplock Limited | 1 | 36 | 0% | 36 | — |
| Pavement Homes Limited | 1 | 36 | 0% | 36 | — |
| Elderwood Construction Limited | 1 | 35 | 0% | 35 | — |
| Hora Developments Limited | 3 | 75 | 55% | 34 | — |
| Danceglen Limited T | 1 | 30 | 0% | 30 | — |
| Quabury Limited | 1 | 29 | 0% | 29 | — |
| Sasula Unlimted Company | 1 | 25 | 0% | 25 | — |
| Minson Property Limited | 1 | 24 | 0% | 24 | — |
Permission lapsed 52 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Rathmullan Road SH305552 | 661 | 5 Mar 2020 | Lapsed lapsed 2 years ago | Oldbridge |
| Cois Glaisin NA180135 | 264 | 11 May 2018 | Lapsed lapsed 3 years ago | Johnstown |
| Grange Hall RA170477 | 163 | 27 Sept 2017 | Lapsed lapsed 4 years ago | Dunshaughlin |
| Dublin Road Dunshaughlin RA171416 | 96 | 21 Aug 2018 | Lapsed lapsed 3 years ago | Zone 1, Dunshaughlin Business Park |
| Dun Eimear Donacarney Great LB180752 | 78 | 11 Oct 2018 | Lapsed lapsed 8 years ago | Laytown Bettystown-Lea-7 |
| Blackcastle Demesne NA200617 | 70 | 11 Sept 2020 | Lapsed lapsed 4 years ago | Blackcastle Demesne |
| Donacarney Great Mornington LB190333 | 65 | 4 Jul 2019 | Lapsed lapsed 2 years ago | Laytown Bettystown-Lea-7 |
| Donacarney Great LB170428 | 65 | 14 Sept 2017 | Lapsed lapsed 2 years ago | Laytown Bettystown-Lea-7 |
| Townparks NA180388 | 63 | 5 Dec 2018 | Lapsed lapsed 3 years ago | |
| Townparks Athboy Road KA171352 | 60 | 27 Apr 2018 | Lapsed lapsed 3 years ago | |
| Station Road LB170362 | 50 | 11 Oct 2017 | Lapsed lapsed 4 years ago | Duleek |
| Donacarney House LB180242 | 49 | 30 Oct 2018 | Lapsed lapsed 3 years ago | Mornington |
| Loughcrew Hills KA191563 | 48 | 5 Aug 2020 | Lapsed lapsed 14 months ago | |
| Ledwidge Hall LB190883 | 36 | 11 Mar 2020 | Lapsed lapsed 2 years ago | Slane |
| Balmoral Estate NA201713 | 35 | 5 May 2021 | Lapsed lapsed 3 years ago | Navan |
| Station Road LB200275 | 34 | 2 Nov 2020 | Lapsed lapsed 11 months ago | Laytown Bettystown-Lea-7 |
| Blackcastle Demesne na201798 | 31 | 15 Mar 2021 | Lapsed lapsed 4 years ago | Blackcastle Demesne |
| Bailis NA181229 | 31 | 31 May 2019 | Lapsed lapsed 2 years ago | Bailis |
| Oldbridge Manor LB191536 | 28 | 3 Mar 2020 | Lapsed lapsed 3 years ago | Rathmullan |
| Kestrel Manor 2560958 | 26 | 10 Dec 2025 | Lapsed lapsed 7 months ago | Lagavooren |
| Athboy Road TA181519 | 25 | 19 Jul 2019 | Lapsed lapsed 2 years ago | Athboy Gate |
| Sevitsland LB200998 | 24 | 21 May 2021 | Lapsed lapsed 2 years ago | Laytown Bettystown-Lea-7 |
| Castle Street AA201804 | 24 | 15 Mar 2021 | Lapsed lapsed 7 months ago | Ashbourne |
| Maelduin to the rear of Main Street RA171256 | 24 | 10 Jul 2018 | Lapsed lapsed 3 years ago | Zone 5, Dunshaughlin Business Park |
| Newtownmoyaghy RA170429 | 23 | 27 Jul 2017 | Lapsed lapsed 4 years ago | Ratoath |
| 12 Loughmore Walk 221320 | 22 | 20 Jan 2023 | Lapsed lapsed 3 years ago | Ratoath |
| Plot 13 Loughmore Walk 22338 | 22 | 23 Jun 2022 | Lapsed lapsed 3 years ago | Ratoath |
| 16 Loughmore Walk 212182 | 22 | 1 Mar 2022 | Lapsed lapsed 3 years ago | Ratoath |
| Beaufort Place Junction of Beaufort Road & Proudstown Road NA201771 | 21 | 15 Mar 2021 | Lapsed lapsed 3 years ago | Navan |
| Roestown Readsland & Knocks RA200041 | 21 | 10 Mar 2020 | Lapsed lapsed 14 months ago | Ratoath |
| Churchfields AA170427 | 21 | 27 Jul 2017 | Lapsed lapsed 4 years ago | Ashbourne |
| Abbeylands NA170800 | 20 | 11 May 2018 | Lapsed lapsed 3 years ago | |
| Dunshaughlin RA180862 | 19 | 14 Jun 2019 | Lapsed lapsed 2 years ago | Dunshaughlin |
| Priestown AA170905 | 19 | 7 Mar 2018 | Lapsed lapsed 4 years ago | Kilbride |
| Glebe TA170415 | 19 | 8 Feb 2018 | Lapsed lapsed 4 years ago | |
| Narrow Ways LB191154 | 18 | 11 Mar 2020 | Lapsed lapsed 2 years ago | Laytown Bettystown-Lea-7 |
| Station Road LB190747 | 18 | 13 Dec 2019 | Lapsed lapsed 2 years ago | Duleek |
| Iffernock TA190775 | 18 | 7 Nov 2019 | Lapsed lapsed 2 years ago | |
| Barstown Commercial Park RA171284 | 17 | 13 Aug 2018 | Lapsed lapsed 3 years ago | Ratoath |
| Dublin Road and Academy Street 2360450 | 16 | 20 Jun 2024 | Lapsed lapsed 15 months ago | |
| Kingsgate LB170361 | 15 | 23 Nov 2017 | Lapsed lapsed 4 years ago | Laytown Bettystown-Lea-7 |
| Posseckstown TA171227 | 14 | 22 Aug 2018 | Lapsed lapsed recently | Enfield |
| Sevitsland 2360380 | 13 | 1 Aug 2024 | Lapsed lapsed recently | Laytown Bettystown-Lea-7 |
| 13 The Paddocks 23593 | 13 | 7 Sept 2023 | Lapsed lapsed 3 years ago | Ratoath |
| Fennor Lodge 22930 | 13 | 18 Oct 2022 | Lapsed lapsed 2 years ago | Slane |
| Clos Na Croise TA200084 | 12 | 8 Sept 2020 | Lapsed lapsed 13 months ago | |
| Robinstown NA170689 | 12 | 14 Sept 2017 | Lapsed lapsed 4 years ago | Robinstown |
| Mine View NA201170 | 11 | 2 Dec 2020 | Lapsed lapsed 10 months ago | |
| Ashewood AA190915 | 11 | 3 Mar 2020 | Lapsed lapsed 2 years ago | Ashbourne |
| Fitzherbert Wood NA190173 | 11 | 19 Aug 2019 | Lapsed lapsed 5 years ago | Blackcastle Demesne |
| Newtownmoyaghy RA200216 | 10 | 6 Jul 2020 | Lapsed lapsed 15 months ago | Ratoath |
| Downstown LB181036 | 10 | 13 Mar 2019 | Lapsed lapsed 6 years ago | Laytown Bettystown-Lea-7 |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'MEATH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness