Meath: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
17,000 homes in 276 sites of 10 or more have been granted permission in Meath since 2017. A commencement notice was lodged for 49% of them. 5,068 still have a live permission and no start; 385 of those lapse within a year, and 2,511 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 3
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Ratoath | 82 | 5,651 | 34% | 2,806 | 52 | 452 |
| Ashbourne | 19 | 1,283 | 42% | 664 | — | 75 |
| Laytown Bettystown-Lea-7 | 58 | 3,372 | 46% | 304 | 201 | 1,203 |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 14 | 994 | 65% | 0 | 349 |
| 2018 | 24 | 1,637 | 43% | 205 | 723 |
| 2019 | 27 | 968 | 61% | 185 | 197 |
| 2020 | 26 | 2,138 | 53% | 43 | 960 |
| 2021 | 25 | 1,198 | 71% | 213 | 135 |
| 2022 | 36 | 1,141 | 58% | 237 | 57 |
| 2023 | 26 | 1,218 | 84% | 154 | 35 |
| 2024 | 33 | 1,665 | 87% | 191 | 29 |
| 2025 | 37 | 3,045 | 31% | 2,069 | 26 |
| 2026 | 28 | 2,996 | 13% | 1,771 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 91% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| John Connaughton Limited | 1 | 810 | 0% | 810 | — |
| Glenveagh Homes Limited | 15 | 1,118 | 20% | 365 | 409 |
| Beo Properties Limited | 1 | 364 | 0% | 364 | — |
| Castlethorn Construction Unlimited Company | 3 | 369 | 9% | 314 | 21 |
| McGarrell Reilly Homes | 6 | 379 | 17% | 283 | 33 |
| Kingscroft Developments Limited | 3 | 305 | 0% | 251 | — |
| Arnub Limited | 2 | 251 | 7% | 233 | — |
| Azra Property Company Limited | 1 | 211 | 0% | 211 | — |
| Rockmill Limited | 1 | 201 | 0% | 201 | — |
| Andrews Construction Limited | 4 | 374 | 50% | 186 | — |
| Carroll Estates Dunboyne Limited | 1 | 171 | 0% | 171 | — |
| Marshall Yards Development Company Limited | 2 | 260 | 50% | 130 | — |
| Cairn Homes Properties Limited | 6 | 602 | 80% | 123 | — |
| Orion Wave Limited | 1 | 98 | 0% | 98 | — |
| The Academy Street Partnership | 1 | 95 | 0% | 95 | — |
| Apolloseven Investments Limited | 2 | 111 | 36% | 71 | — |
| Carroll Estates (Dublin) Limited | 5 | 306 | 39% | 56 | 130 |
| Aspect Houses (ADC) Limited | 1 | 56 | 0% | 56 | — |
| Rockture 1 Limited | 2 | 147 | 0% | 51 | 96 |
| Leinster Land Developments Limited | 1 | 43 | 0% | 43 | — |
| Rycroft Living Limited | 1 | 40 | 0% | 40 | — |
| Indus Properties Limited | 1 | 37 | 0% | 37 | — |
| Poplock Limited | 1 | 36 | 0% | 36 | — |
| Pavement Homes Limited | 1 | 36 | 0% | 36 | — |
| Elderwood Construction Limited | 1 | 35 | 0% | 35 | — |
| Hora Developments Limited | 3 | 75 | 55% | 34 | — |
| Danceglen Limited T | 1 | 30 | 0% | 30 | — |
| Quabury Limited | 1 | 29 | 0% | 29 | — |
| Sasula Unlimted Company | 1 | 25 | 0% | 25 | — |
| Minson Property Limited | 1 | 24 | 0% | 24 | — |
Permission, no start 69 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Station Road and Old Navan Road 2460709 | 810 | 27 Aug 2025 | Not started lapses in 9 years | Dunboyne |
| Ratoath 2560637 | 364 | 14 Aug 2025 | Not started lapses in 4 years | Ratoath |
| Dunboyne 2660481 | 314 | 6 Aug 2026 | Not started lapses in 8 years | Dunboyne |
| Academy Street 2660748 | 245 | 12 Aug 2026 | Not started lapses in 5 years | |
| Jamestown 2660045 | 240 | 16 Apr 2026 | Not started lapses in 5 years | Ratoath |
| Located within the townland of Baltrasna 2561044 | 233 | 23 Apr 2026 | Not started lapses in 5 years | Baltrasna |
| lands generally bound 2560854 | 211 | 21 Nov 2025 | Not started lapses in 7 years | Ratoath |
| Stamullen and Gormanston AA170505 | 205 | 28 Mar 2018 | Not started lapses in 2 years | Ashbourne |
| Dublin Road SH311028 | 201 | 23 Nov 2021 | Lapsing lapses in 2 months | Colp West |
| Old Navan Road 2460625 | 171 | 27 Mar 2025 | Not started lapses in 4 years | Dunboyne |
| Main Street R125 Ballybin Road 2561104 | 130 | 27 Jan 2026 | Not started lapses in 4 years | Moulden Bridge |
| With the townlands of Ferganstown and Ballymacon and Athlumn 2460799 | 98 | 3 Jan 2025 | Not started lapses in 2 years | Ferganstown and Ballymacon |
| Commons Road 2560718 | 96 | 7 Apr 2026 | Not started lapses in 5 years | Duffsland |
| Academy Street/Circular Road/Bridge Street 221421 | 95 | 14 Sept 2023 | Not started lapses in 2 years | Navan |
| Boyne Road 2660717 | 93 | 6 Aug 2026 | Not started lapses in 5 years | Athlumney Bridge |
| Boyne Road 2660256 | 93 | 3 Jun 2026 | Not started lapses in 5 years | Athlumney Bridge |
| Newtownmoyghy RA191018 | 78 | 5 Nov 2019 | Not started lapses within a year | Ratoath |
| Baltrasna 2561359 | 71 | 7 May 2026 | Not started lapses in 5 years | 9 Mile Stone |
| 10 The Oakwood 2560440 | 65 | 7 Aug 2025 | Not started lapses in 6 years | Ratoath |
| Bunboggan 24204 | 64 | 4 Mar 2025 | Not started lapses in 3 years | Athboy |
| Mahir House 2460684 | 63 | 18 Jun 2025 | Not started lapses in 4 years | 9 Mile Stone |
| Windtown/Proudstown Link Road NA181326 | 59 | 26 Feb 2019 | Not started lapses in 2 years | Clonmagaddan |
| Priestown 2561380 | 56 | 1 Apr 2026 | Not started lapses in 5 years | Kilbride |
| Site B Mornington 23885 | 56 | 17 Sept 2024 | Not started lapses in 3 years | Laytown Bettystown-Lea-7 |
| R147 / Dublin Road Dunshaughlin County Meath. 2561019 | 51 | 7 Apr 2026 | Not started lapses in 5 years | Zone 4, Dunshaughlin Business Park |
| Blackcastle Demesne NA191175 | 48 | 13 Dec 2019 | Lapsing lapses in 8 months | Athlumney Bridge |
| Charterschooland and Manorlands 2nd Division 2660278 | 43 | 15 Jun 2026 | Not started lapses in 5 years | Wellington Place |
| Irish National Forester's Hall NA190965 | 43 | 27 Mar 2020 | Not started lapses in 3 years | Navan |
| Glebe Manor Jamestown 2660470 | 40 | 28 Jul 2026 | Not started lapses in 4 years | Ratoath |
| Joe Molloy’s Bookmakers . 2460197 | 37 | 26 Nov 2024 | Not started lapses in 3 years | Clonee |
| Bridge Street and Bachelors Walk 2560600 | 36 | 22 Sept 2025 | Not started lapses in 4 years | Ashbourne |
| Clonee House 2460410 | 36 | 27 Mar 2025 | Not started lapses in 4 years | Clonee |
| Longwood 212073 | 35 | 8 Jun 2022 | Not started lapses in 2 years | Longwood |
| Dunboyne Castle Hotel & Spa 212141 | 30 | 11 May 2022 | Lapsing lapses in 8 months | Ratoath |
| Townparks 21548 | 29 | 7 Apr 2022 | Lapsing lapses in 7 months | |
| Johnstown 2560210 | 28 | 28 Nov 2025 | Not started lapses in 4 years | Ratoath |
| Commons Road 24357 | 27 | 28 Nov 2024 | Not started lapses in 3 years | Balreask Old |
| Dunsany 2561346 | 25 | 26 Mar 2026 | Not started lapses in 5 years | Ratoath |
| Johnstown 221640 | 24 | 19 May 2023 | Not started lapses in 3 years | Alexander Reid |
| Bridge St & The Banba Hall 22219 | 23 | 7 Dec 2022 | Not started lapses within a year | Navan |
| Knockboyne House 2460943 | 22 | 17 Dec 2025 | Not started lapses in 4 years | |
| Creevagh 2461110 | 22 | 3 Jul 2025 | Not started lapses in 4 years | Laytown Bettystown-Lea-7 |
| 2 The Burrows 221074 | 22 | 17 Nov 2022 | Not started lapses within a year | Killien |
| 17 Loughmore Walk 212291 | 22 | 23 Mar 2022 | Lapsing lapses in 6 months | Ratoath |
| Kildalkey Road 21387 | 17 | 21 Jan 2022 | Lapsing lapses in 4 months | |
| Commons 24440 | 15 | 22 Jan 2026 | Not started lapses in 4 years | Laytown Bettystown-Lea-7 |
| Town Parks & Fostersfields 2460241 | 15 | 29 May 2025 | Not started lapses in 4 years | Athboy |
| Hunters Yard 2560256 | 14 | 18 Sept 2025 | Not started lapses in 6 years | Ratoath |
| Greenane 2460325 | 14 | 7 Feb 2025 | Not started lapses in 4 years | Dunshaughlin |
| 9 The Paddocks Killeen Castle Demesne 2660688 | 13 | 9 Sept 2026 | Not started lapses in 2 years | Ratoath |
| 8 THE PADDOCKS KILLEEN CASTLE DEMESNE 2660814 | 13 | 21 Aug 2026 | Not started lapses in 5 years | Ratoath |
| No. 7 The Paddocks 2560841 | 13 | 7 Nov 2025 | Not started lapses in 2 years | Ratoath |
| 2 The Paddocks Killeen Castle 2560702 | 13 | 17 Oct 2025 | Not started lapses in 4 years | Ratoath |
| 4 The Paddocks 2460350 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 5 The Paddocks Killeen Castle Demesne 2360510 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 6 The Paddocks 2460583 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 12 The Paddocks 23159 | 13 | 23 May 2023 | Not started lapses in 2 years | Ratoath |
| Gibbstown 211530 | 13 | 30 Aug 2022 | Lapsing lapses in 11 months | Baile Ghib |
| Maudlin Friarspark 2nd Division and Iffernock 212161 | 13 | 24 Feb 2022 | Lapsing lapses in 6 months | |
| Summerhill 221276 | 12 | 13 Jan 2023 | Lapsing lapses in 6 months | Summerhill |
1–60 of 69Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'MEATH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.