Waterford: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
5,970 homes in 115 sites of 10 or more have been granted permission in Waterford since 2017. A commencement notice was lodged for 58% of them. 1,982 still have a live permission and no start; 40 of those lapse within a year, and 327 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 5 | 200 | 70% | 0 | 60 |
| 2018 | 9 | 480 | 35% | 191 | 123 |
| 2019 | 14 | 694 | 95% | 0 | 33 |
| 2020 | 6 | 205 | 46% | 0 | 111 |
| 2021 | 11 | 327 | 96% | 12 | — |
| 2022 | 16 | 832 | 93% | 57 | — |
| 2023 | 11 | 388 | 78% | 85 | — |
| 2024 | 12 | 1,267 | 48% | 663 | — |
| 2025 | 13 | 498 | 44% | 277 | — |
| 2026 | 18 | 1,079 | 16% | 697 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 72% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Noel Frisby Construction Limited | 6 | 852 | 32% | 582 | — |
| Kilbarry Developments Limited | 8 | 532 | 51% | 260 | — |
| Magna Capital Investments Limited | 3 | 106 | 0% | 106 | — |
| Vetra Construction Limited | 2 | 151 | 34% | 99 | — |
| Spotterlane Limited | 1 | 80 | 0% | 80 | — |
| Dalira Limited | 1 | 58 | 0% | 58 | — |
| Jackie Greene Construction Limited | 1 | 42 | 0% | 42 | — |
| CFS Structures Limited | 1 | 29 | 0% | 29 | — |
| J & B Neville Construction Limited | 2 | 62 | 55% | 28 | — |
| Middlethird Estates Limited | 8 | 194 | 88% | 24 | — |
| Causeway Group Limited | 1 | 15 | 0% | 15 | — |
| Glenveagh Homes Limited | 2 | 113 | 88% | 14 | — |
| T & M Fitzgerald Limited | 1 | 12 | 0% | 12 | — |
| Magna Construction Limited | 6 | 393 | 79% | 0 | 84 |
| S & K Carey Limited | 4 | 247 | 100% | 0 | — |
| Kingscroft Developments Limited | 1 | 167 | 0% | 0 | — |
| Monaco Developments(Tramore) Limited | 1 | 166 | 100% | 0 | — |
| S.E. Construction (Kent) Limited | 2 | 110 | 100% | 0 | — |
| Liam Carey Homes Limited (t and a Carey Homes) | 2 | 101 | 100% | 0 | — |
| Kilkenny Investment Property Holdings Limited | 2 | 94 | 100% | 0 | — |
| Hollyhill Developments Limited | 1 | 89 | 0% | 0 | 89 |
| Liam Neville Developments Limited | 2 | 80 | 100% | 0 | — |
| Marina Quarter Limited | 1 | 73 | 100% | 0 | — |
| SuirBay Limited | 1 | 69 | 100% | 0 | — |
| SE Construction (Kent) Limited | 1 | 69 | 100% | 0 | — |
| Jim Quinn (Dungarvan) Limited | 1 | 60 | 0% | 0 | 60 |
| Kilcarton Limited | 1 | 55 | 100% | 0 | — |
| DFL Construction Limited | 2 | 46 | 100% | 0 | — |
| Stratton Developments Limited | 1 | 44 | 100% | 0 | — |
| Michael Doyle Civil Engineering Limited | 1 | 41 | 0% | 0 | 41 |
Work started 72 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Railway Gardens 17837 | 17 | 7 Jun 2018 | Started notice 27 Aug 2019 | |
| Coxtown 21551 | 16 | 10 Mar 2022 | Started notice 30 May 2023 | |
| Lands accessed via Westside Business Park 21216 | 16 | 15 Jun 2021 | Started notice 19 Jan 2022 | |
| Newtown 1869 | 16 | 14 Feb 2019 | Started notice 1 Aug 2019 | |
| Kilbarry 2460101 | 15 | 28 Nov 2024 | Started notice 16 Sept 2026 | |
| Bounds Court 19923 | 15 | 29 Jul 2020 | Started notice 4 Jan 2021 | |
| Church Court 18646 | 15 | 2 May 2019 | Started notice 31 Jan 2023 | |
| Crobally Upper 2460482 | 14 | 23 Jan 2025 | Started notice 1 Dec 2025 | |
| Cluain Lárach 1718 | 14 | 13 Apr 2017 | Started notice 3 Apr 2017 | |
| Knightswood 20971 | 13 | 27 May 2021 | Started notice 5 Jul 2021 | |
| Mountfield 17266 | 12 | 14 Jul 2017 | Started notice 14 Apr 2017 | |
| Crooke 2560153 | 10 | 1 Dec 2025 | Started notice 5 Jan 2026 |
← Previous 6061–72 of 72
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WATERFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness