Permitted, not started · Waterford · grants of 10+ homes since 2017

Waterford: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

6,014 homes in 115 sites of 10 or more have been granted permission in Waterford since 2017. A commencement notice was lodged for 57% of them. 2,026 still have a live permission and no start; 40 of those lapse within a year, and 327 have already lapsed.

6,014
homes permitted · 115 sites
57%
started · 3,457 homes
2,026
not started · live permission
40
lapse within 12 months
327
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017520070%060
2018948035%191123
20191469495%033
2020620546%0111
20211132796%12
20221683293%57
20231138878%85
2024121,26748%663
20251354241%321
2026181,07916%697

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 92% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Noel Frisby Construction Limited794238%582
Kilbarry Developments Limited853251%260
Vetra Construction Limited431638%197
Middlethird Estates Limited927761%107
Magna Capital Investments Limited31060%106
Rio Real Properties1990%99
Jackie Green Construction Limited1990%99
Spotterlane Limited1800%80
S & K Carey Limited731881%61
Dalira Limited1580%58
Jackie Greene Construction Limited1420%42
J & A Lynch Investments Limited1400%40
Celtic Showboat Limited1380%38
O'Brien Family Partnership1340%34
CFS Structures Limited1290%29
J & B Neville Construction Limited26255%28
Newpark Properties Limited1230%23
Causeway Group Limited1150%15
Glenveagh Homes Limited211388%14
T & M Fitzgerald Limited1120%12
Magna Construction Limited745381%084
S.E. Construction (Kent) Limited3177100%0
Kingscroft Developments Limited11670%0
SE Construction (Kent) Limited2167100%0
Monaco Developments(Tramore) Limited1166100%0
Liam Neville Developments Limited3122100%0
Kilkenny Investment Property Holdings Limited3109100%0
Liam Carey Homes Limited (t and a Carey Homes)2101100%0
Hollyhill Developments Limited1890%089
Cosmo Develoments Limited173100%0

Permission, no start 33 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Cork Road 246010058230 May 2024Not started lapses in 3 years
Lacken Road 25604879925 Aug 2026Not started lapses in 5 years
Mountneil 25609379920 Aug 2026Not started lapses in 5 years
Knockboy 25604049920 Nov 2025Not started lapses in 5 years
Kilbarry 178969915 Oct 2018Not started lapses in 2 years
Kilbarry 2560867987 Sept 2026Not started lapses in 5 years
Kilbarry 178959215 Oct 2018Not started lapses in 2 years
Newtown 25604688316 Apr 2026Not started lapses in 5 years
Ballinakill Shopping Centre 25609408010 Aug 2026Not started lapses in 5 years
Ballybeg Drive 25602755828 Jul 2025Not started lapses in 4 years
Lacken 25602515712 Jan 2026Not started lapses in 4 years
Killure Road 2560154513 Dec 2025Not started lapses in 5 years
Knockboy 23601064226 Oct 2023Not started lapses in 2 years
Clonmel, Co. Waterford 2560657408 Sept 2026Not started lapses in 5 years
Broad Street 26603584025 Aug 2026Not started lapses in 5 years
Coxtown 24604664015 Jan 2025Not started lapses in 4 years
James St & The Glen 232793813 Nov 2024Not started lapses in 3 years
Davitts Quay and TF Meagher Street 2560575348 Sept 2026Not started lapses in 5 years
Ballybeg Link Road 25609483420 Jul 2026Not started lapses in 5 years
Ballybeg Link Road 23604743221 Nov 2024Not started lapses in 3 years
Farrangarret 216042916 Jun 2022Not started lapses in 3 years
Radharc na Suire 21622284 Mar 2022Lapsing lapses in 5 months
Newtown 24605662425 Apr 2025Not started lapses in 4 years
Kilbarry 24604012321 Mar 2025Not started lapses in 3 years
Crooke 25609612111 Sept 2026Not started lapses in 5 years
Kill 23600171528 Nov 2023Not started lapses in 2 years
Church Field 2460812143 Sept 2025Not started lapses in 4 years
Townparks West 2324143 Nov 2023Not started lapses in 2 years
'The Paddocks' 23600561416 May 2023Not started lapses in 2 years
Lacken 2560553125 Mar 2026Not started lapses in 4 years
Kilminnin South 24605191219 Jun 2025Not started lapses in 4 years
Arlington Lodge 2010081211 Oct 2021Lapsing lapses within a month
45A The Glen 231421110 Apr 2024Not started lapses in 3 years

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WATERFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.