Waterford: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
6,014 homes in 115 sites of 10 or more have been granted permission in Waterford since 2017. A commencement notice was lodged for 57% of them. 2,026 still have a live permission and no start; 40 of those lapse within a year, and 327 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 5 | 200 | 70% | 0 | 60 |
| 2018 | 9 | 480 | 35% | 191 | 123 |
| 2019 | 14 | 694 | 95% | 0 | 33 |
| 2020 | 6 | 205 | 46% | 0 | 111 |
| 2021 | 11 | 327 | 96% | 12 | — |
| 2022 | 16 | 832 | 93% | 57 | — |
| 2023 | 11 | 388 | 78% | 85 | — |
| 2024 | 12 | 1,267 | 48% | 663 | — |
| 2025 | 13 | 542 | 41% | 321 | — |
| 2026 | 18 | 1,079 | 16% | 697 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 92% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Noel Frisby Construction Limited | 7 | 942 | 38% | 582 | — |
| Kilbarry Developments Limited | 8 | 532 | 51% | 260 | — |
| Vetra Construction Limited | 4 | 316 | 38% | 197 | — |
| Middlethird Estates Limited | 9 | 277 | 61% | 107 | — |
| Magna Capital Investments Limited | 3 | 106 | 0% | 106 | — |
| Rio Real Properties | 1 | 99 | 0% | 99 | — |
| Jackie Green Construction Limited | 1 | 99 | 0% | 99 | — |
| Spotterlane Limited | 1 | 80 | 0% | 80 | — |
| S & K Carey Limited | 7 | 318 | 81% | 61 | — |
| Dalira Limited | 1 | 58 | 0% | 58 | — |
| Jackie Greene Construction Limited | 1 | 42 | 0% | 42 | — |
| J & A Lynch Investments Limited | 1 | 40 | 0% | 40 | — |
| Celtic Showboat Limited | 1 | 38 | 0% | 38 | — |
| O'Brien Family Partnership | 1 | 34 | 0% | 34 | — |
| CFS Structures Limited | 1 | 29 | 0% | 29 | — |
| J & B Neville Construction Limited | 2 | 62 | 55% | 28 | — |
| Newpark Properties Limited | 1 | 23 | 0% | 23 | — |
| Causeway Group Limited | 1 | 15 | 0% | 15 | — |
| Glenveagh Homes Limited | 2 | 113 | 88% | 14 | — |
| T & M Fitzgerald Limited | 1 | 12 | 0% | 12 | — |
| Magna Construction Limited | 7 | 453 | 81% | 0 | 84 |
| S.E. Construction (Kent) Limited | 3 | 177 | 100% | 0 | — |
| Kingscroft Developments Limited | 1 | 167 | 0% | 0 | — |
| SE Construction (Kent) Limited | 2 | 167 | 100% | 0 | — |
| Monaco Developments(Tramore) Limited | 1 | 166 | 100% | 0 | — |
| Liam Neville Developments Limited | 3 | 122 | 100% | 0 | — |
| Kilkenny Investment Property Holdings Limited | 3 | 109 | 100% | 0 | — |
| Liam Carey Homes Limited (t and a Carey Homes) | 2 | 101 | 100% | 0 | — |
| Hollyhill Developments Limited | 1 | 89 | 0% | 0 | 89 |
| Cosmo Develoments Limited | 1 | 73 | 100% | 0 | — |
Permission, no start 33 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Cork Road 2460100 | 582 | 30 May 2024 | Not started lapses in 3 years | |
| Lacken Road 2560487 | 99 | 25 Aug 2026 | Not started lapses in 5 years | |
| Mountneil 2560937 | 99 | 20 Aug 2026 | Not started lapses in 5 years | |
| Knockboy 2560404 | 99 | 20 Nov 2025 | Not started lapses in 5 years | |
| Kilbarry 17896 | 99 | 15 Oct 2018 | Not started lapses in 2 years | |
| Kilbarry 2560867 | 98 | 7 Sept 2026 | Not started lapses in 5 years | |
| Kilbarry 17895 | 92 | 15 Oct 2018 | Not started lapses in 2 years | |
| Newtown 2560468 | 83 | 16 Apr 2026 | Not started lapses in 5 years | |
| Ballinakill Shopping Centre 2560940 | 80 | 10 Aug 2026 | Not started lapses in 5 years | |
| Ballybeg Drive 2560275 | 58 | 28 Jul 2025 | Not started lapses in 4 years | |
| Lacken 2560251 | 57 | 12 Jan 2026 | Not started lapses in 4 years | |
| Killure Road 2560154 | 51 | 3 Dec 2025 | Not started lapses in 5 years | |
| Knockboy 2360106 | 42 | 26 Oct 2023 | Not started lapses in 2 years | |
| Clonmel, Co. Waterford 2560657 | 40 | 8 Sept 2026 | Not started lapses in 5 years | |
| Broad Street 2660358 | 40 | 25 Aug 2026 | Not started lapses in 5 years | |
| Coxtown 2460466 | 40 | 15 Jan 2025 | Not started lapses in 4 years | |
| James St & The Glen 23279 | 38 | 13 Nov 2024 | Not started lapses in 3 years | |
| Davitts Quay and TF Meagher Street 2560575 | 34 | 8 Sept 2026 | Not started lapses in 5 years | |
| Ballybeg Link Road 2560948 | 34 | 20 Jul 2026 | Not started lapses in 5 years | |
| Ballybeg Link Road 2360474 | 32 | 21 Nov 2024 | Not started lapses in 3 years | |
| Farrangarret 21604 | 29 | 16 Jun 2022 | Not started lapses in 3 years | |
| Radharc na Suire 21622 | 28 | 4 Mar 2022 | Lapsing lapses in 5 months | |
| Newtown 2460566 | 24 | 25 Apr 2025 | Not started lapses in 4 years | |
| Kilbarry 2460401 | 23 | 21 Mar 2025 | Not started lapses in 3 years | |
| Crooke 2560961 | 21 | 11 Sept 2026 | Not started lapses in 5 years | |
| Kill 2360017 | 15 | 28 Nov 2023 | Not started lapses in 2 years | |
| Church Field 2460812 | 14 | 3 Sept 2025 | Not started lapses in 4 years | |
| Townparks West 2324 | 14 | 3 Nov 2023 | Not started lapses in 2 years | |
| 'The Paddocks' 2360056 | 14 | 16 May 2023 | Not started lapses in 2 years | |
| Lacken 2560553 | 12 | 5 Mar 2026 | Not started lapses in 4 years | |
| Kilminnin South 2460519 | 12 | 19 Jun 2025 | Not started lapses in 4 years | |
| Arlington Lodge 201008 | 12 | 11 Oct 2021 | Lapsing lapses within a month | |
| 45A The Glen 23142 | 11 | 10 Apr 2024 | Not started lapses in 3 years |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WATERFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.