Waterford planning permission: the homes nobody has started

Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness

4,859 homes in 80 sites of 10 or more have been granted permission in Waterford since 2021. A commencement notice was lodged for 55% of them. 2,000 still have a live permission and no start; 28 of those lapse within a year, and — have already lapsed.

4,859
homes permitted · 80 sites
55%
started · 2,655 homes
2,000
not started · live permission
28
lapse within 12 months
—
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 6

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Waterford City South201,61246%867——
Tramore-Waterford City West201,24828%694——
Waterford City East251,34380%26628—
Dungarvan626676%63——
Portlaw-Kilmacthomas531683%55——
Lismore47426%55——

By year granted

Granted inSitesHomesStartedNot startedLapsed
20215215100%0—
20221683293%57—
20231248785%71—
2024121,26748%663—
20251353968%170—
2026221,51918%1,039—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 18 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 54% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Noel Frisby Construction Limited479927%582—
Spotterlane Limited1800%80—
Magna Capital Investments Limited1400%40—
Magna Construction Limited4309100%0—
S & K Carey Limited4247100%0—
Glenveagh Homes Limited3212100%0—
Kingscroft Developments Limited11670%0—
Monaco Developments(Tramore) Limited1166100%0—
Kilbarry Developments Limited2114100%0—
Dalira Limited2113100%0—
S.E. Construction (Kent) Limited196100%0—
Middlethird Estates Limited494100%0—
Marina Quarter Limited173100%0—
Rolton Way Limited140100%0—
S+K Carey Limited127100%0—
ENK Beechouse Limited121100%0—
Kilkenny Investment Property Holdings Limited120100%0—
DFL Construction Limited119100%0—

Permission lapsed 0 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

Nothing in this list.

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WATERFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.06 Nov 2026, 23:00open
An Coimisiún Pleanála case listCC BY 4.06 Nov 2026, 23:00open
Building Control Management System commencement noticesCC BY 4.06 Nov 2026, 23:00open

Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.