Permitted, not started · Waterford · grants of 10+ homes since 2017

Waterford: homes with planning permission that nobody has started

Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness

5,970 homes in 115 sites of 10 or more have been granted permission in Waterford since 2017. A commencement notice was lodged for 58% of them. 1,982 still have a live permission and no start; 40 of those lapse within a year, and 327 have already lapsed.

5,970
homes permitted · 115 sites
58%
started · 3,457 homes
1,982
not started · live permission
40
lapse within 12 months
327
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017520070%060
2018948035%191123
20191469495%033
2020620546%0111
20211132796%12—
20221683293%57—
20231138878%85—
2024121,26748%663—
20251349844%277—
2026181,07916%697—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 72% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Noel Frisby Construction Limited685232%582—
Kilbarry Developments Limited853251%260—
Magna Capital Investments Limited31060%106—
Vetra Construction Limited215134%99—
Spotterlane Limited1800%80—
Dalira Limited1580%58—
Jackie Greene Construction Limited1420%42—
CFS Structures Limited1290%29—
J & B Neville Construction Limited26255%28—
Middlethird Estates Limited819488%24—
Causeway Group Limited1150%15—
Glenveagh Homes Limited211388%14—
T & M Fitzgerald Limited1120%12—
Magna Construction Limited639379%084
S & K Carey Limited4247100%0—
Kingscroft Developments Limited11670%0—
Monaco Developments(Tramore) Limited1166100%0—
S.E. Construction (Kent) Limited2110100%0—
Liam Carey Homes Limited (t and a Carey Homes)2101100%0—
Kilkenny Investment Property Holdings Limited294100%0—
Hollyhill Developments Limited1890%089
Liam Neville Developments Limited280100%0—
Marina Quarter Limited173100%0—
SuirBay Limited169100%0—
SE Construction (Kent) Limited169100%0—
Jim Quinn (Dungarvan) Limited1600%060
Kilcarton Limited155100%0—
DFL Construction Limited246100%0—
Stratton Developments Limited144100%0—
Michael Doyle Civil Engineering Limited1410%041

Work started 72 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Waterford Crystal Sports and Leisure Centre site 24603341669 Aug 2024Started notice 29 Jan 2026
Duckspool 256009711316 Apr 2025Started notice 19 Dec 2025
Killea 2111339914 Dec 2022Started notice 1 May 2023
"The Paddocks" 218339913 Oct 2022Started notice 23 Apr 2024
Graigueshoneen 2339982 Feb 2024Started notice 8 Sept 2025
Williamstown 223789822 Nov 2022Started notice 3 May 2023
Mountneil 2111889820 Jul 2022Started notice 1 Nov 2022
Adamstown 212149623 Aug 2021Started notice 20 Sept 2021
Williamstown 187169013 Aug 2019Started notice 30 Sept 2019
Lacken 187349029 Apr 2019Started notice 22 Apr 2024
Moonvoy 222758911 Aug 2022Started notice 28 Apr 2023
Kilbarry 2460052882 May 2024Started notice 14 Oct 2024
Deerpark Outer Ring Road 24603747923 Oct 2024Started notice 17 Dec 2025
Deerpark Outer Ring Road 24601137829 Aug 2024Started notice 30 Dec 2024
Kilbarry 17418749 Nov 2017Started notice 12 Dec 2018
Grantstown 2360349737 Nov 2023Started notice 11 Feb 2026
Carraig an Aird 187787310 Jun 2019Started notice 12 Mar 2020
Knockboy 22146698 Feb 2023Started notice 27 Dec 2024
Knockenduff 18544694 Jun 2019Started notice 26 Sept 2019
Lacken 187356829 Apr 2019Started notice 22 Apr 2024
Kilbarry 2560781675 Aug 2026Started notice 19 Aug 2026
Adamstown 225076713 Feb 2023Started notice 27 Mar 2023
Williamstown 18580652 Jul 2019Started notice 19 Jun 2020
Cul Dara 2560299631 Dec 2025Started notice 26 Dec 2025
Carrigroe and Lacken 22126214 Dec 2022Started notice 2 Feb 2026
Killea Road 183636110 Oct 2018Started notice 23 May 2019
Ballinakill Shopping Centre 217926020 Jan 2022Started notice 4 Oct 2024
Outer Ring Road 212156031 Aug 2021Started notice 14 Feb 2022
Foxwood 188676010 Jul 2019Started notice 31 Jul 2019
Lacken Road 17886554 Apr 2018Started notice 13 Sept 2018
Knightswood The Outer Ring Road 25603945224 Feb 2026Started notice 14 Mar 2026
Carrigroe and Lacken 22115214 Dec 2022Started notice 2 Feb 2026
Quarry Road - Bilberry Road 188044425 Sept 2019Started notice 3 Feb 2022
Williamstown Road 23604324223 May 2024Started notice 12 Aug 2024
Kilminion Ballinroad 2560754403 Feb 2026Started notice 28 May 2026
Croughtanaul 191684014 Oct 2019Started notice 27 Feb 2020
Fairfield Park 17674407 Dec 2017Started notice 30 Apr 2018
Duffcarrick 23606153811 Oct 2024Started notice 31 Aug 2026
Radharc na Siure 196363413 Jul 2020Started notice 16 Dec 2020
Mountfield 17894339 Jul 2018Started notice 26 Jul 2018
Old Tramore Road 181923123 Aug 2019Started notice 15 Feb 2019
Adamstown 204002815 Jun 2021Started notice 21 Mar 2023
Crooke 229232731 Jan 2023Started notice 1 May 2023
Crobally Upper 2080274 Jun 2020Started notice 5 Mar 2021
Ballycarnane 23602582528 Nov 2023Started notice 25 Mar 2024
Foxwood 213232510 Nov 2021Started notice 30 Nov 2021
Newtown 22398248 Mar 2023Started notice 24 Dec 2024
Cliffside 218362410 Mar 2022Started notice 30 Jun 2022
Newtown 24601472110 Feb 2025Started notice 8 Dec 2025
Killure Road 21595213 May 2022Started notice 15 Apr 2024
Woodbrook 205522128 Jan 2021Started notice 23 Apr 2024
Newtown 2112132022 Jun 2022Started notice 16 Apr 2024
Lands accessed via Westside Business Park 2110102014 Apr 2022Started notice 31 Oct 2022
Michael J. Prendergast Road 25608151927 Feb 2026Started notice 23 Mar 2026
St. Joseph's House 208711923 Sept 2021Started notice 18 Jul 2022
69 & 70 O'Connell Street 19714196 Apr 2021Started notice 15 Apr 2022
White Waves 221034188 Aug 2023Started notice 30 Aug 2023
Crooke 211891831 Aug 2021Started notice 18 Apr 2022
Newtown Hill 199221813 Jul 2020Started notice 7 May 2021
'Rathfadden Lodge' 219881722 Mar 2022Started notice 8 Jan 2024

1–60 of 72Next 60 →

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WATERFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.026 Sept 2026, 07:08open
An Coimisiún Pleanála case listCC-BY-4.026 Sept 2026, 07:08open
Building Control Management System commencement noticesCC-BY-4.026 Sept 2026, 07:08open

Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.